Miller-Davis Co. v. Ahrens Construction, Inc.

817 N.W.2d 609, 296 Mich. App. 56
CourtMichigan Court of Appeals
DecidedMarch 22, 2012
DocketDocket No. 284037
StatusPublished
Cited by31 cases

This text of 817 N.W.2d 609 (Miller-Davis Co. v. Ahrens Construction, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller-Davis Co. v. Ahrens Construction, Inc., 817 N.W.2d 609, 296 Mich. App. 56 (Mich. Ct. App. 2012).

Opinion

ON REMAND

Per Curiam.

In this case, defendant1 appealed the judgment entered for plaintiff after a bench trial on plaintiffs breach of contract claims. Plaintiff filed a cross-appeal of a judgment of no cause of action on its claim for contractual indemnity. This Court held that MCL 600.5839(1) time-barred plaintiffs claims. Miller-Davis Co v Ahrens Constr, Inc, 285 Mich App 289, 292, 312-313; 777 NW2d 437 (2009). Our Supreme Court reversed, holding that “MCL 600.5839 is limited to tort actions.” Miller-Davis Co v Ahrens Const, Inc, 489 Mich 355, 371; 802 NW2d 33 (2011). The Court concluded that the general six-year period of limitations applicable to actions for breach of contract, MCL 600.5807(8), which “runs from the date the ‘claim first accrued,’ ” applied in this case. Miller-Davis, 489 Mich at 358. “Because there [was] a question about the date plaintiffs action accrued,” the Court remanded the case to this Court “to resolve this issue, as well as other issues not yet considered.” Id. Later, the Court indicated that on remand this Court should apply MCL 600.5807(8) and, “if necessary, [consider] the remaining issues raised in the appeal and cross-appeal.” Id. at 372. We reverse in part, affirm in part, and remand for entry of judgment for defendant.

We review de novo as a question of law whether a claim is barred by a statute of limitations. Scherer v Hellstrom, 270 Mich App 458, 461; 716 NW2d 307 (2006).

We are to apply MCL 600.5807, which provides:

No person may bring or maintain any action to recover damages or sums due for breach of contract, or to enforce the specific performance of any contract unless, after the [60]*60claim first accrued to himself or to someone through whom he claims, he commences the action within the periods of time prescribed by this section.
(8) The period of limitations is 6 years for all other actions to recover damages or sums due for breach of contract. [Emphasis added.]

Thus, MCL 600.5807(8) requires that an action to recover damages for breach of contract must be brought within six years after the claim first accrued. Miller-Davis, 489 Mich at 358; Blazer Foods, Inc v Restaurant Properties, Inc, 259 Mich App 241, 245; 673 NW2d 805 (2003).

With respect to accrual of a claim, MCL 600.5827 provides that except for cases covered by MCL 600.5829 to MCL 600.5838, “[a] claim accrues at the time the wrong upon which the claim is based was done regardless of the time when damage results.” Sections 5829 to 5838 cover claims relating to possession of land, a mutual and open account, warranty, common carriers, life insurance, installment contracts, alimony, and malpractice. None of these provisions applies in this case. Although plaintiff presents arguments in its supplemental brief regarding certain warranty provisions, plaintiffs complaint did not include a claim for breach of warranty. Miller-Davis, 489 Mich at 359; Miller-Davis, 285 Mich App at 306.

A contract claim accrues when the wrong occurs, i.e., when the promise is breached, regardless of when damage results. MCL 600.5827; Seyburn, Kahn, Ginn, Bess, Deitch & Serlin, PC v Bakshi, 483 Mich 345, 355; 771 NW2d 411 (2009); Tenneco Inc v Amerisure Mut Ins Co, 281 Mich App 429, 458; 761 NW2d 846 (2008). The “wrong” on which the contract claim is based is determined by examining the parties’ contract. Tenneco, 281 [61]*61Mich App at 458, citing Scherer 270 Mich App at 463. Although plaintiff asserts the breach of a so-called charge-back clause and an indemnification clause, the underlying basis for its claim is that defendant breached a contract condition providing that “[a]ll materials and/or work furnished on this order shall comply with the terms and requirements of the plans and specifications - where applicable.”2

Plaintiff was the general contractor on a construction project that included building a natatorium for a YMCA recreational complex, and defendant was a subcontractor with the responsibility of installing a proprietary wooden roofing system over which other roofing materials would be installed by other subcontractors. MillerDauis, 285 Mich App at 292-293, 309. The wrong that plaintiff alleged with respect to defendant’s having failed to “comply with the terms and requirements of the plans and specifications” of the contract must have occurred on or before defendant completed its portion of the overall construction project. This conclusion is consistent with this Court’s prior decisions. “A cause of action for breach of a construction contract accrues at the time work on the contract is completed.” Employers Mut Cas Co v Petroleum Equip, Inc, 190 Mich App 57, 63; 475 NW2d 418 (1991), citing Buckey v Small, 52 Mich App 454, 455-456; 217 NW2d 422 (1974). In our prior opinion, we addressed the date when defendant completed its work on the project. In particular, we noted that defendant completed its work on the project by the end of February 1999 and certified to plaintiff that the work was complete on April 26, 1999, for the purpose of being paid.

[62]*62By the end of February 1999, defendant completed all its tasks regarding constructing the roof system, including installing all the wood parts, the vapor barrier, the T’s and sub-T’s [superstructures], the insulation, all of which were covered by [oriented strand board] nailed on top of two-by-four inch “sleepers” running perpendicular over the T’s to the top ridge of the roof.... Defendant certified to plaintiff that it had completed its work on the roof on April 26,1999, and plaintiff paid defendant for this work the next day.
. .. [I]t is undisputed, and the trial court so found, that defendant completed its work on its part of the natatorium’s roof by the end of February 1999. Thereafter, the evidence clearly establishes that another contractor completed the final phase of the roofs construction by attaching the roofing felt and the standing seam steel skin. Plaintiffs exhibit 9, the minutes of a work-progress meeting on February 18, 1999, indicates that over the prior two weeks Ahrens completed its roof work at the recreational building, and that work for the next two weeks contemplated subcontractor Architectural Glass & Metals’ completing the metal roof at the recreation building. [Miller-Davis, 285 Mich App at 296-297, 309.]

We have not been presented any reason to revisit this analysis of when defendant completed the work it contracted with plaintiff to perform. Because defendant completed its work on the roof by the end of February 1999, the breach that plaintiff alleged — that defendant had failed to comply with the terms and requirements of the plans and specifications — must have occurred by that date. Further, because plaintiff did not file its complaint until May 12, 2005, more than six years after February 1999 and more than six years after plaintiff accepted the work through its payment at the end of April 1999, the statute of limitations barred those claims. MCL 600.5807(8); Buckey, 52 Mich App at 455-456.

[63]*63Plaintiff asserts in its supplemental brief on remand that defendant waived application of the statute of limitations by not briefing and arguing the proper statute, MCL 600.5807(8). We find this argument disingenuous and reject it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
817 N.W.2d 609, 296 Mich. App. 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-davis-co-v-ahrens-construction-inc-michctapp-2012.