Autumn Acres Senior Village Inc v. Village of Mayville

CourtMichigan Court of Appeals
DecidedNovember 19, 2019
Docket343492
StatusUnpublished

This text of Autumn Acres Senior Village Inc v. Village of Mayville (Autumn Acres Senior Village Inc v. Village of Mayville) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Autumn Acres Senior Village Inc v. Village of Mayville, (Mich. Ct. App. 2019).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

AUTUMN ACRES SENIOR VILLAGE, INC., UNPUBLISHED November 19, 2019 Plaintiff/Counterdefendant- Appellant,

v No. 343485 Tuscola Circuit Court VILLAGE OF MAYVILLE, LC No. 15-029068-CZ

Defendant/Counterplaintiff- Appellee.

AUTUMN ACRES SENIOR VILLAGE, INC.,

Plaintiff/Counterdefendant- Appellee,

v No. 343492 Tuscola Circuit Court VILLAGE OF MAYVILLE, LC No. 15-029068-CZ

Defendant-Appellant.

Before: M. J. KELLY, P.J., and FORT HOOD and SWARTZLE, JJ.

PER CURIAM.

In Docket No. 343485, plaintiff/counterdefendant, Autumn Acres Senior Village, Inc., appeals by right the trial court’s order declaring no cause of action on its contract and regulatory taking claims against defendant/counterplaintiff, the Village of Mayville. In Docket No. 343492, defendant appeals by right the same order dismissing its counterclaims seeking declaratory relief on the basis that plaintiff violated the Safe Drinking Water Act (SDWA), MCL 325.1001 et seq., and the Village of Mayville Code. Because there are no errors warranting relief, we affirm.

-1- I. BASIC FACTS

The dispute in this case arose after the installation of a nonfunctional meter pit on plaintiff’s property. Relevant to this appeal, in 2007, approximately 360 feet of eight-inch water main was extended north along Roller Way on plaintiff’s property from defendant’s Main Street. A permit, however, was obtained for only 140 feet of water main, and at trial the parties disputed whether and to what extent defendant’s public-works superintendent, Roger Sweet, was involved in installing the extra water main. The record reflects that Sweet did not inform defendant of the additional main and, following Sweet’s death in 2011, there was a question regarding when defendant’s new public-works superintendent became aware of the water-main extension.

Over a period of time, plaintiff and defendant discussed adding additional housing to plaintiff’s development,1 and in 2013, the parties’ representatives discussed how the new housing would be serviced by water and sewer. Andy Hecht, defendant’s new public-works superintendent, testified that plaintiff and defendant agreed that a meter pit and master meter would be installed on plaintiff’s property for a one-time tap-in fee of $1,800, with plaintiff able to add water connections to the master meter, and his testimony was corroborated by testimony from some of defendant’s council members. In contrast, plaintiff’s owner, Clare Roller, testified that there was no agreement to install a meter pit, but rather that there was only an agreement that the housing would be provided with water service.

In August 2013, a meter pit was installed on plaintiff’s property, but after its installation the pit filled with groundwater. Hecht testified that the pit had not been finished and required a riser and metal cover. However, Roller asserted that defendant simply refused to fix the pit. During the ensuing dispute, plaintiff attached its new housing into the water system with unauthorized connections, and defendant eventually discovered that the eight-inch water main extended more than 140 feet into plaintiff’s property. Hecht stated that he attempted to finish or fix the meter pit but was ordered off the property, and that was the only thing that prevented him from completing the work. Roller denied that assertion, testifying that while he was in Florida for the winter Hecht called him and said “he was gonna finish the pit,” but Roller told Hecht not to put anything on the pit and charge him for it until after Roller got back.

During an action in the district court, plaintiff was ordered to disconnect its additional housing from the water system. Plaintiff subsequently filed claims for breach of contract, equitable contract, unjust enrichment, promissory estoppel, and regulatory taking. Defendant filed a counterclaim that sought declaratory judgment for violations of the SDWA and Mayville Code, asking the trial court to order plaintiff to disconnect the rest of plaintiff’s properties from the water system on the basis that they were attached to the unapproved eight-inch water main. Following a jury trial, the jury returned a verdict finding that the parties had a contract but defendant did not breach it. Thereafter, the trial court determined that plaintiff had no cause of action for equitable contract or regulatory taking and that defendant had no cause of action for declaratory relief.

1 Plaintiff is an independent living community.

-2- II. EQUITABLE CONTRACT

A. STANDARD OF REVIEW

Plaintiff argues that the trial court should have granted relief in equitable contract because the jury verdict was inconsistent and the court could have implied a contract between the parties in equity. A trial court’s dispositional ruling on an equitable matter is reviewed de novo. Morris Pumps v Centerline Piping, Inc, 273 Mich App 187, 193; 7zGATranscriptNew29 NW2d 898 (2006).

-3- B. ANALYSIS

An arguably inconsistent jury verdict must be upheld if there is an interpretation of the evidence that provides a logical explanation for the jury’s findings. Moore v Detroit Entertainment, LLC, 279 Mich App 195, 227; 755 NW2d 686 (2008). “A party asserting a breach of contract must establish by a preponderance of the evidence that (1) there was a contract (2) which the other party breached (3) thereby resulting in damages to the party claiming breach.” Miller-Davis Co v Ahrens Constr, Inc, 495 Mich 161, 178; 848 NW2d 95 (2014). A valid contract requires “mutual assent or a meeting of the minds on all the essential terms.” Kloian v Domino’s Pizza, LLC, 273 Mich App 449, 453; 733 NW2d 766 (2006). Furthermore, a party who first breaches a contract may not maintain an action against another party for a subsequent failure to perform the contract. Michaels v Amway Corp, 206 Mich App 644, 650; 522 NW2d 703 (1994).

At trial, Hecht and other water committee members testified that, during the June 2013 meeting on plaintiff’s property, it was agreed that a master meter pit would be installed on the property. While Roller testified that plaintiff had not agreed to the installation of a meter pit, the jury was free to reject his testimony because it is the role of the finder of fact to determine the credibility of the witnesses. See MCR 2.613(C). Similarly, although Roller testified that he did not order defendant’s agents off his property but merely asked them to wait for him to return from Florida, the jury could have chosen to credit defendant’s president and Hecht, who both testified that they were ordered off the property when they attempted to fix the meter pit. Based on the foregoing, we conclude that there was sufficient evidence to support that the jury’s verdict finding a contract but no breach. The verdict was, therefore, not inconsistent, so the court did not err by denying plaintiff relief on that basis.

Additionally, because the jury’s verdict was not inconsistent and because the jury found a contract existed, the trial court properly decided not to imply a contract in equity. See Morris Pumps, 273 Mich App at 194 (stating that courts will not imply a contract when there is an express contract between the same parties on the same subject).

III. REGULATORY TAKING

Plaintiff next argues that the trial court erred by concluding that there was no regulatory taking on the basis that it improperly applied the balancing test in Penn Central Transp Co v New York City, 438 US 104; 98 S Ct 2646; 57 L Ed 2d 631 (1978).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penn Central Transportation Co. v. New York City
438 U.S. 104 (Supreme Court, 1978)
Flanders Industries, Inc. v. State
512 N.W.2d 328 (Michigan Court of Appeals, 1993)
Moore v. Detroit Entertainment, LLC
755 N.W.2d 686 (Michigan Court of Appeals, 2008)
K & K Const. v. Dnr
575 N.W.2d 531 (Michigan Supreme Court, 1998)
Morris Pumps v. Centerline Piping, Inc.
729 N.W.2d 898 (Michigan Court of Appeals, 2007)
Kloian v. Domino's Pizza, LLC
733 N.W.2d 766 (Michigan Court of Appeals, 2007)
Michaels v. Amway Corp.
522 N.W.2d 703 (Michigan Court of Appeals, 1994)
Bevan v. Brandon Township
475 N.W.2d 37 (Michigan Supreme Court, 1991)
Widmayer v. Leonard
373 N.W.2d 538 (Michigan Supreme Court, 1985)
Miller-Davis Co. v. Ahrens Construction, Inc.
848 N.W.2d 95 (Michigan Supreme Court, 2014)
K & K Construction, Inc. v. Department of Natural Resources
456 Mich. 570 (Michigan Supreme Court, 1998)
Augustine v. Allstate Insurance
807 N.W.2d 77 (Michigan Court of Appeals, 2011)
Trader v. Comerica Bank
809 N.W.2d 429 (Michigan Court of Appeals, 2011)
Miller-Davis Co. v. Ahrens Construction, Inc.
817 N.W.2d 609 (Michigan Court of Appeals, 2012)
Lima Twp v. Bateson
302 Mich. App. 483 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Autumn Acres Senior Village Inc v. Village of Mayville, Counsel Stack Legal Research, https://law.counselstack.com/opinion/autumn-acres-senior-village-inc-v-village-of-mayville-michctapp-2019.