Michael P. Moore v. California Institute of Technology Jet Propulsion Laboratory

275 F.3d 838, 18 I.E.R. Cas. (BNA) 1209, 2002 Cal. Daily Op. Serv. 82, 2002 Daily Journal DAR 103, 2002 U.S. App. LEXIS 68
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 4, 2002
Docket00-55958
StatusPublished
Cited by88 cases

This text of 275 F.3d 838 (Michael P. Moore v. California Institute of Technology Jet Propulsion Laboratory) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael P. Moore v. California Institute of Technology Jet Propulsion Laboratory, 275 F.3d 838, 18 I.E.R. Cas. (BNA) 1209, 2002 Cal. Daily Op. Serv. 82, 2002 Daily Journal DAR 103, 2002 U.S. App. LEXIS 68 (9th Cir. 2002).

Opinion

PREGERSON, Circuit Judge:

Plaintiff-Appellant Michael P. Moore (“Moore”) appeals the district court’s grant of summary judgment in favor of his former employer, Defendant-Appellee California Institute of Technology Jet Propulsion Laboratory (“JPL”), regarding *841 Moore’s retaliation claims against JPL under the False Claims Act, 31 U.S.C. § 3730(h), and the Major Fraud Act, 18 U.S.C. § 1031(h). Moore, who specialized in large antenna mechanics, told the National Aeronautics and Space Administration (“NASA”) Inspector General that he suspected fraud at JPL involving a large antenna JPL was building for NASA Af-terwards, JPL made several proposals to Moore concerning his work with JPL that he alleges were retaliatory. For example, JPL proposed that Moore transfer to another group without being able to take with him the projects he had been working on. JPL also proposed to eliminate Moore’s job title and put him under an intermediate supervisor. Because Moore protested, none of these proposals were implemented. The District Court held that these proposals did not amount to retaliation, because they were not “clearly unreasonable, such that an objective observer would understand that the proposal was nothing more than a means of harassing the employee.” As an alternative ground for granting summary judgment on the False Claims Act claim, the district court held that Moore’s conduct was not protected under the False Claims Act because the suspected fraud at JPL was not “directly related” to any government payment and could, therefore, not have possibly resulted in a False Claims Act case. We have jurisdiction pursuant to 28 U.S.C. § 1291 and reverse.

I.

From 1991 until his resignation in 1996, Moore worked for JPL as an engineer who specialized in the mechanical aspects of large antennas. The Department of Defense and the National Security Administration hired JPL to investigate structural problems that had arisen in connection with two large antennas which an outside contractor, GTE, had built for Department of Defense and National Security Administration in Puerto Rico. JPL assigned the task to Moore, who concluded that there were problems with the gears that moved the antennas and that the gears needed to be replaced. The investigation lead to an indictment of GTE under the Major Fraud Act. Moore was asked to be a technical witness for the government.

Moore also concluded that there were similar problems with the gears of an antenna JPL was building for NASA. Moore recommended replacing the gears. The gear manufacturer and an independent expert, Don McVittie (“McVittie”), also recommended replacing the gears. On November 1, 1996, Moore’s immediate supervisor, Chris Yung (‘Tung”), approved a lien on the transfer of the antenna which indicated that the gears needed to be replaced before the antenna could be delivered to NASA. The lien was given to Allied Signal, an outside contractor who acted as a monitor. When Allied Signal was satisfied that the problem had been solved, it would release the lien. Only then would JPL be able to transfer the antenna to NASA.

On November 8, 1996, Yung and others at JPL unsuccessfully tried to convince McVittie to change his recommendation that the gears needed to be replaced. On November 29, 1996, JPL circulated an internal memo that stated that for JPL to make a good impression on NASA, JPL needed to deliver the antenna to NASA as scheduled, i.e., no later than January 15, 1996. JPL’s contract with NASA covering, inter alia, the antenna project provided for a fixed Base Allowance of $6,000,000 and a discretionary Incentive Award of up to $12,000,000. The November 29 memo also stated that “[l]iens should only be used sparingly, and prompt action must be taken to ... close them in a timely man *842 ner.” On the same day, Robert White (“White”), the project manager who together with Yung was primarily responsible for completion and transfer of the antenna, sent a memo under his and Yung’s names to Tony Brydon (“Brydon”) at Allied Signal, the outside contractor responsible for releasing the lien on the antenna. The memo stated that “there is NO problem with the structural integrity of the gears.” The memo further stated that “there currently is no need ... to replace the gear[s] ... in the foreseeable future.” When Brydon asked JPL for McVittie’s report, JPL sent him the report but omitted the pages on which McVittie recommended replacing the gears.

Moore became concerned because as a technical witness in the GTE litigation, he planned to testify that misaligned antenna gears had to be replaced. He was concerned because he might also have to reveal that his employer had concluded that similarly misaligned antenna gears did not have to be replaced. Moore felt that his employer’s view might somehow undermine the government’s case. Moore consulted Sandra Cooper (“Cooper”), an attorney in JPL’s general counsel’s office. Cooper told Moore that he should reveal the problem to the Assistant U.S. Attorney and that as a whistle blower, he would be protected against retaliation by JPL. Moore followed Cooper’s advice and was told by a member of the government’s GTE investigation team to report the matter to the NASA Inspector General. On December 14, 1995, Moore called the NASA Inspector General’s office and stated, in the words of the NASA special agent who took the call, that he “suspected fraud at JPL.” On January 6, 1996, Moore sent an e-mail to the NASA Inspector General’s office that read as follows:

Management persons at JPL were aware of the existence of an [sic] report prepared by an expert regarding damaged gears, in which the expert recommended that the gears be replaced. JPL subsequently issued a memo to the NASA representative [Brydon] in which they stated that there was “NO structural problem” without revealing the outside expert’s opinion.

Later, Moore met with an individual from the NASA Inspector General’s office.

Moore told Cooper that he had reported the issue to the NASA Inspector General. Cooper again told Moore that as a whistle blower, he would be protected against retaliation by JPL. At the recommendation of Cooper, Moore also reported the matter to the head of ethics at JPL, who began an internal investigation.

In January 1996, Yung proposed to Moore that he transfer from Yung’s work group to another group headed by Michael Thorburn (“Thorburn”), a friend of Moore’s. Under the proposed transfer, Moore would not have been allowed to take with him any of the projects he had been working on. This arrangement would have left him without long-term funding and would have disconnected him from Department of Defense, the largest customer for his specialty of large antenna mechanics. In connection with this transfer proposal, Yung told Moore that he should not have gone outside the chain of command and that he should have informed Yung before he talked to the NASA Inspector General. Yung also told Moore that he should consider the possibility that there would be downsizing at JPL, although according to Moore, the downsizing concerns were no more significant in 1995 than previously. Moore objected to the proposed transfer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
275 F.3d 838, 18 I.E.R. Cas. (BNA) 1209, 2002 Cal. Daily Op. Serv. 82, 2002 Daily Journal DAR 103, 2002 U.S. App. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-p-moore-v-california-institute-of-technology-jet-propulsion-ca9-2002.