Metcalf Construction Co. v. United States

107 Fed. Cl. 786, 2012 U.S. Claims LEXIS 1576, 2012 WL 6177028
CourtUnited States Court of Federal Claims
DecidedDecember 10, 2012
DocketNo. 07-777C
StatusPublished
Cited by1 cases

This text of 107 Fed. Cl. 786 (Metcalf Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metcalf Construction Co. v. United States, 107 Fed. Cl. 786, 2012 U.S. Claims LEXIS 1576, 2012 WL 6177028 (uscfc 2012).

Opinion

MEMORANDUM OPINION AND FINAL ORDER REGARDING CONTRACT DISPUTES ACT DAMAGES

BRADEN, Judge.

I. BACKGROUND.1

On December 9, 2011, the court issued a Memorandum Opinion and Order determining that Metcalf Construction Company, Inc. (“Metcalf’) failed to establish liability for all claims alleged in the November 10, 2009 Amended Complaint, but identified two events that constituted a breach of contract. See Metcalf Const. Co. v. United States, 102 Fed.Cl. 334, 348-55, 369-70 (2011). First, the Department of the Navy (“Navy”) failed to provide Metcalf with consideration for the January 29,2003 Modification P00001. Id. at 369-70. To compensate Metcalf, the court ruled that Metcalf was entitled to a 73-day extension. Id. at 370.2 In addition, the court determined that the Navy violated Federal Acquisition Regulation (“FAR”) 48 C.F.R. § 52.236-2(b) (“FAR 52.236-2(b)”),3 by failing to investigate in a prompt manner Metcalf's June 24, 2003 notice of a differing site condition concerning an expansive soil condition. Id. at 353-55. To compensate Metcalf, the court ruled that Metcalf was entitled to an additional 306-day extension. Id.4

Thereafter, the court convened a conference in chambers with counsel of record, the client representative, and other entities with a financial interest in the case, in an attempt to reach a resolution regarding damages, without further adjudication. Since that effort was unsuccessful, the parties filed post-trial briefs on damages.5

II. DISCUSSION.

A. Whether Plaintiff Is Entitled To The Contract Balance Withheld By The Department Of The Navy.

1. The Plaintiff’s Argument.

The adjusted price of the October 22, 2002 Contract between Metcalf and the Navy, in-[789]*789eluding all modifications, was $49,947,872. See Metcalf, 102 Fed.Cl. at 338 (citing JX E32 at DEF0542523). To date, the Navy has paid Metcalf $49,050,899. 2/3/12 PI. PT D Br. at 6 (citing Metcalf 102 Fed.Cl. at 339); see also Jan. 4, 2010 Stip. ¶ 14. In light of the court’s redetermination that Metcalf is due a 260-day extension (see supra note 4), the 136-day delay that is the basis for the Government’s withholding is more than offset, and the $896,973 amount should be refunded to Metcalf. 2/3/12 PL PT D Br. at 3, 6-7.

2.The Government’s Response.

The Government responds that Metcalf is not entitled to receive the $896,973 amount withheld and also owes an additional $2,673,507 for the Navy’s counterclaim based on Metcalf s failure to complete the required work within the time specified by the October 22, 2002 Contract, as amended. 3/23/12 Gov’t PT D Br. at 36. The court’s finding that Metcalf is entitled to be “credited for an extension,” does not mean that the October 22, 2002 Contract’s completion date must be extended. 3/23/12 Gov’t PT D Br. at 36. Specifically, as to the extension that the court determined was due Metcalf, because of the Navy’s failure to provide consideration for Modification P00001, that extension was accounted for in other contract modifications extending the initial final completion date over a year, ie., from June 27, 2005 to October 17, 2006. 3/23/12 Gov’t PT D Br. at 36-37. As to the Navy’s delay in investigating Metcalf s June 24, 2003 notice of a differing site condition, Metcalfs schedule shows that, as late as July 1, 2006, Metcalf projected a completion date of October 6, 2006. 3/23/12 Gov’t PT D Br. at 27 (citing DX 2934A at 51-52). Since the court determined that post-January 2006 delays were not caused by the Navy, Metcalf is not entitled to the contract balance and remains liable for $2,673,507 in liquidated damages for its failure to complete the October 22, 2002 Contract on October 17, 2006. 3/23/12 Gov’t PT D Br. at 37 (citing Metcalf 102 Fed.Cl. at 370).

3.The Plaintiffs Reply.

Metcalf replies that the Government seeks an unwarranted reconsideration of the court’s determination that Metcalf is entitled to an extension that “subsumes” the 136-day delay on which the Government’s November 30, 2009 Counterclaim for Liquidated Damages is based.6 3/30/12 PL PT D Reply at 2-3.

4.The Court’s Resolution.

The court’s December 9, 2011 Memorandum Opinion and Order did not adjudicate the Government’s November 30, 2009 Counterclaim for Liquidated Damages. The court does so here.

Paragraph 1 D.2 of the October 22, 2002 Contract provides:

If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $290 per unit per calendar day not completed for each day of delay.

JX Al at DEF0498371.

The trial record establishes that the parties mutually agreed that October 17, 2006 was the final adjusted completion date. JX E26 at DEF0064694. The record also establishes that Metcalf did not actually complete performance until March 2, 2007. PX 455. Therefore, the Navy is entitled to liquidated damages of $290 per unit for each day of delay, or $3,570,480. PX 455.

Accordingly, the court has determined that Metcalf is not entitled to the $896,973 withheld by the Navy, but that amount must be deducted from the $3,570,480 liquidated damages due. Therefore, Metcalf owes the Navy $2,673,507, in addition to interest, as provided in FAR 32.608-1,7 at the rate established by the U.S. Treasury under Public Law 92-41.

[790]*790B. Whether Plaintiff Is Entitled To Direct And “Escalation” Costs.

1.The Plaintiff’s Argument.

The court determined that “on August 5, 2004, the date the Navy finally denied Met-calfs notice of a differing site condition, Met-calf was approximately 200 days behind schedule.” Metcalf, 102 Fed.Cl. at 370, n. 42 (citing PTX 779 at 17 (Stynchcomb)). Therefore, because of Metcalfs subsequent efforts to “catch up,” Metcalf argues that it should be compensated for “additional direct costs incurred as a result of the Navy’s failure to investigate in a timely manner, including both its net additional costs associated with the post-tension/slab[,] as well as other direct costs flowing from the breach.” 2/3/12 PL PT D Br. at 10. In addition, the court determined that the Navy’s “delay and Met-calfs effort to catch up resulted in Metcalf addressing the expansive soils situation by using a post-tension slab design that imposed significant costs on Metcalf, but were of greater benefit to the Navy than the plain concrete slabs typically used[.]” Metcalf, 102 Fed.Cl. at 370 n. 42. Therefore, Metcalf is entitled to $2,936,180 in “direct costs,”8 to the “escalation costs” of certain commodity items,9 and to “direct cost mark-ups of 1.96% for overhead and 10% for profit,” for a total of $3,903,382 for the “stronger post-tension slabs and material escalation costs.” 2/3/12 Pl. PT D Br. at 5,12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
107 Fed. Cl. 786, 2012 U.S. Claims LEXIS 1576, 2012 WL 6177028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metcalf-construction-co-v-united-states-uscfc-2012.