Messerli v. Department of Natural Resources

768 P.2d 1112, 1989 Alas. LEXIS 9
CourtAlaska Supreme Court
DecidedFebruary 17, 1989
DocketS-1735, S-2188, S-2069 and S-2226
StatusPublished
Cited by32 cases

This text of 768 P.2d 1112 (Messerli v. Department of Natural Resources) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Messerli v. Department of Natural Resources, 768 P.2d 1112, 1989 Alas. LEXIS 9 (Ala. 1989).

Opinion

COMPTON, Justice.

I. INTRODUCTION

These consolidated appeals arise out of the granting of a preference right to Loyd Messerli by the Commissioner of the Alaska Department of Natural Resources (DNR). Messerli filed two lawsuits in connection with the preference right. In the first appeal, Messerli challenges a decision of Judge John Bosshard III finding no procedural irregularities in the DNR’s granting of his preference right. The state appeals Judge Bosshard’s finding of estoppel against it and his decision to award attorney’s fees to Mr. Messerli. In the second appeal, Messerli challenges the decision of Judge Milton M. Souter denying him a preliminary injunction.

II. FACTUAL AND PROCEDURAL BACKGROUND

Messerli entered onto a 160 acre tract of land under the federal homestead law in June 1959. He cleared one-half acre, erected a tent and helped neighbors build a road to the north shore of a lake adjoining the land. Messerli also bought a one-half interest in an airplane and learned to fly as the property was accessible only by air.

Soon after Messerli entered the land, problems arose with respect to the validity of his claim. The Bureau of Land Management (BLM) ultimately cancelled his claim, and in 1964 his case was closed.

In the years that followed, Messerli continued his efforts to obtain title to the land. In 1977, Messerli applied for a preference right from the state under AS 38.05.035(b). 1 *1115 DNR denied the application. After further dispute, in March 1984 Messerli succeeded in persuading newly appointed DNR Commissioner Esther Wunnicke to reopen his file.

Commissioner Wunnicke decided to offer a preference right under AS 38.05.035(b)(2) with conditions. Because the original homestead tract was no longer owned by the state, Messerli was given 150 days to nominate up to 160 acres in a compact, contiguous tract. The selection was limited to land designated for settlement in the Susitna Area Plan (the Plan). The selection was subject to the constitutional requirement of public notice and a best interest finding.

Messerli’s original entry was in a region entitled the Willow Sub-basin. The sub area is nearly surrounded by the Plan although it appears to be jurisdictionally separate for planning purposes. The Plan itself contains 15.8 million acres; approximately 130,000 acres are designated for settlement. At Messerli’s request the Director of the Division of Land and Water Management agreed to allow Messerli to expand his search area beyond the Susitna area. He also agreed to allow Messerli to choose up to four separate parcels not to exceed 160 acres and stated that a 30-day extension to the 150-day extension could be granted.

In June 1984 Messerli chose 102 acres of land above Potter Marsh in Anchorage. In August 1984 Messerli selected his remaining acreage — 58 acres at Jack Bay in the Municipality of Valdez.

The Commissioner denied both selections. She belatedly notified Messerli that she disapproved of the Director’s decision to expand the selection area, and she overruled his decision. She again indicated that Messerli’s selection must be one contiguous and compact tract within the area designated for settlement by the Plan. She cautioned that “it is not my intent that the preference right be exercised on a value-for-value basis, but rather on the basis of acre for acre.” Messerli claims this is the first time that he learned that the basis of the preference right would not be value for value. The Commissioner also granted Messerli another ninety days to select a parcel.

DNR and Messerli continued their efforts to locate a suitable parcel. In October 1984, Dale Tubbs, Messerli’s land consultant, conducted a search of land records for all lands within the Plan. (15.8 million acres) Tubbs concluded “[n]o areas having a comparable setting to your original claim on Carpenter Lake were found to exist.” Tubbs had established several criteria for evaluating the parcels. These included: amenities such as lake front or river front location and trees; development opportunity; reasonable road or plane access; “good” soils and a favorable compass orientation. In December 1984 Messerli, through counsel, wrote that he could not locate a comparable parcel. He decided to insist on the Potter Marsh and Valdez parcels. He requested that DNR record his nomination of those parcels on the land records and “take no action with respect to those lands without prior written notice.”

In February 1985 DNR located parcels of suitable lake front property on Diamond and Stephan Lakes. These parcels were road accessible with soils suitable for development. Messerli rejected both proposed parcels, claiming that neither parcel met his criteria.

In March 1985 the Director issued a decision closing Messerli’s case file. Messerli appealed to Commissioner Wunnicke. She upheld the rejection of the Anchorage and Valdez parcels, but agreed to reopen the case file. She reasoned that the Director did not have authority to close the case because the case had not been remanded to him. She also clarified the terms and conditions of the original grant of the preference right by means of an amendment to the original decision. The amendment *1116 specified that the preference right was for a single parcel of 160 acres and that the land be within those areas designated for settlement by the Plan. The nomination had to be made by August 12, 1985. If no state parcel was located by August 16, 1985 Messerli was given until August 23 to notify the director that he “wishe[d] the Director to pursue a reconveyance from the Mat-Su borough ... [of the parcels] at either Diamond Lake or Stephan Lake parcels.” That paragraph concluded “there are no guarantees that the land will be reconveyed. The director shall notify Mr. Messerli by October 1, 1985 if the land will be reconveyed, or if the case is closed.”

On August 12, 1985 Messerli requested reconsideration and made six selections under protest. 2 On August 16 the Director rejected selections 1 through 5 because they were not lands designated for settlement in the Plan and approved selection 6, Also on August 16, the Commissioner denied the request for reconsideration, advised Messerli of his appeal rights and stated selection 6 would be conveyed if no appeal was filed.

On August 23, 1985 DNR received a letter from Messerli’s attorney dated August 22, 1985, indicating that Messerli would only accept “under protest” any selection other than the Potter Marsh or Valdez parcels, and that he intended to appeal to the superior court. The same day, the Commissioner again refused to alter the terms and conditions of the grant of the preference right, and advised that the grant would expire at 4:30 p.m. that day.

In September 1985 Messerli filed an appeal of the administrative action in the superior court, Case No. 3AN 85-13294. The appeal was assigned to Judge John Bosshard III. The appeal raised two issues.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alsworth v. Seybert
323 P.3d 47 (Alaska Supreme Court, 2014)
Holmes v. Wolf
243 P.3d 584 (Alaska Supreme Court, 2010)
Smart v. State
237 P.3d 1010 (Alaska Supreme Court, 2010)
Smart v. State, Department of Health & Social Services
237 P.3d 1010 (Alaska Supreme Court, 2010)
Anderson v. State, Department of Revenue
26 P.3d 1106 (Alaska Supreme Court, 2001)
Jerrel v. State, Department of Natural Resources
999 P.2d 138 (Alaska Supreme Court, 2000)
Aloha Lumber Corp. v. University of Alaska
994 P.2d 991 (Alaska Supreme Court, 1999)
Mathis v. Sauser
942 P.2d 1117 (Alaska Supreme Court, 1997)
Brodigan v. Alaska Department of Revenue
900 P.2d 728 (Alaska Supreme Court, 1995)
Brandon v. Department of Corrections
865 P.2d 87 (Alaska Supreme Court, 1993)
Mortvedt v. State, Department of Natural Resources
858 P.2d 1140 (Alaska Supreme Court, 1993)
Longwith v. State, Department of Natural Resources
848 P.2d 257 (Alaska Supreme Court, 1992)
State v. Morry
836 P.2d 358 (Alaska Supreme Court, 1992)
Olsen Logging Co. v. Lawson
832 P.2d 174 (Alaska Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
768 P.2d 1112, 1989 Alas. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/messerli-v-department-of-natural-resources-alaska-1989.