Alaska Public Utilities Commission v. Greater Anchorage Area Borough

534 P.2d 549, 1975 Alas. LEXIS 358, 1975 WL 350952
CourtAlaska Supreme Court
DecidedApril 4, 1975
Docket2314
StatusPublished
Cited by29 cases

This text of 534 P.2d 549 (Alaska Public Utilities Commission v. Greater Anchorage Area Borough) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alaska Public Utilities Commission v. Greater Anchorage Area Borough, 534 P.2d 549, 1975 Alas. LEXIS 358, 1975 WL 350952 (Ala. 1975).

Opinion

OPINION

BOOCHEVER, Justice.

This petition for review requires us to re-examine criteria to be applied by the superior court in ascertaining whether to overrule a decision of the Alaska Public Utility Commission (hereinafter the Commission) pertaining to interim relief sought by a public utility which had applied for authority to charge higher rates.

The Greater Anchorage Area Borough (hereinafter the Borough) assumed responsibility for the City of Anchorage sewer utility operation in 1970 after having received appropriate authorization from the *551 voters of the Borough. The Borough points to three factors which have led to drastic increases in operating costs in recent years. First, the earthquake of 1964 caused extensive damage to the sewer system in Anchorage. This greatly accelerated- the rate of deterioration of the system and has required constant attention involving repair and replacement of damaged lines ever since. Secondly, the passage of federal and state environmental legislation necessitated the construction of a sewage treatment plant at Point Woronzof. The construction of the facility was financed by the issuance of municipal revenue bonds. The substantial annual payments on these bonds along with the salaries of the 25 employees required to operate the plant constitute an additional drain on the resources available to the utility. Finally, the inflation of the past several years has greatly increased the cost of both labor and equipment.

On March 15, 1974, the Borough sewer utility sought a 17 percent increase in the basic user rate from $3.75 per month to $4.40 per month. 1 On April 15, 1974, the Commission ordered that the proposed tariff increase become conditionally effective, pending hearings and a final decision by the Commission. The Borough was to place these funds in escrow and keep accurate records so that, in the event the increase was eventually denied, the utility’s customers could receive refunds. This form of interim relief was granted pursuant to the Commission’s discretionary authority set forth in AS 42.05.421(c). 2

Subsequently, the utility concluded that its original request was still inadequate to meet operating expenses, and on July 2, 1974, the Borough filed a supplemental request for a tariff increase from the former $3.75 per month and from the previously proposed $4.40 (effective during the interim) to $7.65 per month. It also requested that this new rate become effective during the interim subject to the same conditions as the former proposed increased for the protection of the utility’s consumers. On July 30, 1974, the Commission denied this second request for an interim rate increase. The Commission, however, did realize the importance of an expeditious determination of the permanent rate, and it established a schedule for prefiled testimony shortly after denying the Borough petition.

The Commission, with one commissioner dissenting, found that it would be contrary to the public interest to grant such a substantial rate increase without the benefit of a full record or a public hearing. According to the Commission, the first interim rate increase would have allowed the collection of only $291,146 a year without benefit of hearing, whereas the second increase would have authorized the collection of $1,670,030 a year without such a hear *552 ing. The request for interim relief was denied even though evidence (financial statements, schedules, etc.) was presented by the Borough which showed without question that the utility was operating at a huge loss.

This evidence was uncontradicted, and it showed that for the fiscal year 1972-73 the utility operated at a loss of $580,000. The fiscal year 1973-74 showed a total cash deficit of $2,400,000 even after a transfer of $1,000,000 of the general Borough property tax revenue to the utility. 3 Finally, it was shown that the proposed $7.65 user rate, should it be approved, would forestall the need for further emergency infusions of cash, although it would leave the utility’s financial structure still dependent on some $1,600,000 from the general property tax levy of the Borough. 4

On August 21, 1974, three weeks after the Commission refused to invoke its discretionary authority under the said statute and grant the interim rate hike, the Borough sought a preliminary injunction from the superior court to enjoin that part of the Commission’s order which prevented it from imposing the increased rate during the period prior to the final hearings. The Borough pointed to its acute cash flow problem and to the fact that, should the $7.65 rate eventually be found by the Commission to be reasonable and fair, its losses during the interim period would be irreparable since the Alaska regulatory scheme does not provide a statutory means of re-coupment. While the Borough was faced with irreparable losses if injunctive relief were denied, the public, on the other hand, could be adequately safeguarded. The funds attributable to the proposed increase would be held in escrow and returned to the consumer should the Borough fail to prevail at the final hearing. The superior court issued such an injunction on August 26, 1974. This allowed the proposed $7.65 per month rate to go into effect.

Three days later the Commission moved for reconsideration, and the motion was heard on September 4, 1974. On September 5, 1974, the superior court denied the Commission’s request for reconsideration and left its injunction in force. 5

The Commission filed this petition for review on- September 16, 1974. The opposition brief was filed by the Borough on September 24, 1974. On September 26, 1974, the Commission filed an application to stay the effect of the preliminary injunction pursuant to Alaska R.App.P. 7(d) (2) 6 pending determination of this issue presented for review by this court in the aforementioned petition. We denied the application believing that the expedi *553 tion with which the petition for review would be handled would render a stay unnecessary and the issues raised therein moot. 7

In keeping with our desire to expedite disposition of this matter, we entered an order on November 7, 1974 granting the petition for review 8 and affirming the order of the superior court awarding interim relief to the utility. This opinion has been written because of the need to further elucidate the principles enunciated in A. J. Industries, Inc. v. Alaska Public Service Commission 9 and to give guidance for future cases as to the applicable considerations in reviewing a failure of the Commission to grant interim rate relief,

In general, a court in applying its equitable sanctions, must be most careful to avoid any semblance of judicial rate-making.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alsworth v. Seybert
323 P.3d 47 (Alaska Supreme Court, 2014)
Holmes v. Wolf
243 P.3d 584 (Alaska Supreme Court, 2010)
State, Department of Fish & Game, Sport Fish Division v. Meyer
906 P.2d 1365 (Alaska Supreme Court, 1995)
State v. Kluti Kaah Native Village of Copper Center
831 P.2d 1270 (Alaska Supreme Court, 1992)
State v. United Cook Inlet Drift Association
815 P.2d 378 (Alaska Supreme Court, 1991)
Messerli v. Department of Natural Resources
768 P.2d 1112 (Alaska Supreme Court, 1989)
VECO International, Inc. v. Alaska Public Offices Commission
753 P.2d 703 (Alaska Supreme Court, 1988)
Veco Intern. v. Alaska Pub. Off. Com'n
753 P.2d 703 (Alaska Supreme Court, 1988)
Noey v. Department of Environmental Conservation
737 P.2d 796 (Alaska Supreme Court, 1987)
United States v. RCA Alaska Communications, Inc.
597 P.2d 489 (Alaska Supreme Court, 1979)
Number One Rent-A-Car v. Ramada Inns, Inc.
587 P.2d 1329 (Nevada Supreme Court, 1978)
State v. Tanana Valley Sportsmen's Ass'n
583 P.2d 854 (Alaska Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
534 P.2d 549, 1975 Alas. LEXIS 358, 1975 WL 350952, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alaska-public-utilities-commission-v-greater-anchorage-area-borough-alaska-1975.