Merritt, Chapman & Scott Corporation, a Corporation, and the Savin Construction Corporation, a Corporation v. Guy F. Atkinson Company, a Corporation

295 F.2d 14, 1961 U.S. App. LEXIS 3575
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 22, 1961
Docket17056
StatusPublished
Cited by28 cases

This text of 295 F.2d 14 (Merritt, Chapman & Scott Corporation, a Corporation, and the Savin Construction Corporation, a Corporation v. Guy F. Atkinson Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merritt, Chapman & Scott Corporation, a Corporation, and the Savin Construction Corporation, a Corporation v. Guy F. Atkinson Company, a Corporation, 295 F.2d 14, 1961 U.S. App. LEXIS 3575 (9th Cir. 1961).

Opinion

BARNES, Circuit Judge.

This is a diversity case wherein the district court had jurisdiction pursuant to 28 U.S.C. § 1332, and this court has jurisdiction on appeal under 28 U.S.C. § 1291.

Appellants contracted to build the Folsom Dam, located on the American River fifteen miles east of Sacramento, California. This required the construction of a temporary or cofferdam above and one below the permanent dam site. A diversion tunnel from the upper cofferdam was required to divert the water below the lower cofferdam. The latter was to prevent backing up of water from below into the area where the permanent dam was being constructed.

Appellants raise two points: I — The “government contract defense,” and II— that certain damages were improper.

*15 It was the collapse of the upper cofferdam on two occasions (January 9, 1953, and May 20, 1953) which damaged appellee’s intermediate cellular steel cofferdam, its powerhouse installation, and the working area required therefor. Appellee was awarded damages totaling $519,-761.73.

It seems clear to this court that to enable appellants to rely on their claimed “government contract defense,” their obligation must have been contained within the contract appellants executed with the government. If that contract be uncertain, or ambiguous, or in need of interpretation, then only can the court go into the “surrounding circumstances.”

The government required originally only that the upstream cofferdam have a minimum crest elevation of 237 feet; the downstream cofferdam a minimum crest elevation of 218 feet; and that they be located at certain points. By “Supplemental Agreement No. 1” the government set a maximum elevation of 250 feet on the upper cofferdam.

We adopt the following language from the appellee’s brief, which we find undisputed by appellants:

“As to the upstream cofferdam, the plans and specifications were silent as to details, except for the reference to the minimum crest elevation, its general location, and eventually the permissible maximum crest elevation.
“They did not require or direct anything of the Appellants as the main dam contractor. Nothing was required or directed as to the materials to be used, the construction methods to be followed, the sequence or order of construction, or any other detail.
“Neither the Corps of Engineers, nor any of its employees prepared or submitted to Appellants any plan, or even any single drawing of the upstream cofferdam (Tr. 1045). Quite to the contrary, the Specifications (Exhibit A-16A, Paragraph 1-05) provided that:
“ ‘Details of the proposed plans for diversion and for the design of the cofferdams shall be submitted to the Contracting Officer for information only * * * prior to commencement of the construction of the cofferdams.’
“Actually only one drawing of the upstream cofferdam was ever made. Appellants’ Project Manager David E. Stinson conceived and prepared it (Tr. 767-768). No other drawings or plans of the upstream cofferdam were ever prepared by anyone.
“Prior to the execution of Appellants’ contract with the Corps of Engineers, on December 8, 1950, the Contracting Office, Lt. Col. C. C. Plaug, wrote an interpretive letter (Exhibit G-29-A) stating that it was the intent [of the contract executed] :
“ ‘to place the responsibility for diversion and de-watering on the Main Dam contractor except for the diversion tunnel.’
“This assignment of responsibility for diversion and de-watering to the main dam contractor (the Appellants) was never changed (Tr. 1037-1038) by any of the contract documents (which include the contract, the plans and specifications, Supplemental Agreement No. 1, and the change orders).” (Appellee’s Br., pp. 3-4.)

The negligence of defendants-appellants was charged in five respects. These were:

(1) Failure to select and use proper materials in the construction of the upstream cofferdam.

(2) Failure to install cut-off walls or collars, or to use special compaction, around the discharge pipes in the upstream cofferdam.

(3) Railing the upstream cofferdam from elevation 237 to 250 during the flood season.

(4) Maintaining the upstream cofferdam without a prudent plan for the con *16 trolled release of the water in the flood season.

(5) Failure to breach the upstream cofferdam and the downstream cofferdam on the days of the floods. 1

The first three acts were finally admittedly not subject to any direct government control and were entirely within the discretion of the appellants. (Appellants’ Br., p. 10; Stipulation (as to point (3) ), Tr. 1086-87.)

We find nothing in the record either by way of terms of the contract, or even “in the context of surrounding circumstances,” to convince us that appellants were required by any government directive or authority to do that which was charged against them as negligent acts (4) and (5). We find no evidence of government compulsion with respect thereto. It is elementary that compulsion must exist before the “government contract defense” is available. Hence we find no error in the court having held, as a matter of law, there was no factual question to present to the jury. It was a question of law. No interpretation was required of the terms of the contract. Although appellants content themselves with repeated general statements that they were required to follow the government’s instruction, appellee has specifically pointed out, by reference to the record, that:

A. Appellants had discretion in the design.
B. Appellants had freedom of selection of materials used.
C. Appellants voluntarily added the sheet-piling cut-off wall.
D. Appellants provided the discharge pipes.
E. Appellants increased the elevation of the upstream cofferdam from 237 to 250 feet without direction from the Corps of Engineers.

The eases cited by appellants to establish the general rule of “Government contract defense” are cases in which plans and specifications were drawn and adopted prior to the contract. Then the contractor is entitled to follow such plans and specifications, exercising due and proper care and skill, and require parties damaged to look to the government, which has required such a contract, for relief; provided such plans and specifications are inadequate, and where there has been no departure from the plans, and when the work has not been done in an improper, careless or negligent manner by the contractor. Marin Municipal Water Dist. v. Peninsula Paving Co., 1939, 34 Cal.App.2d 647, 94 P.2d 404

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anchorage v. Integrated Concepts & Research Corp.
1 F. Supp. 3d 1001 (D. Alaska, 2014)
Conner v. Quality Coach, Inc.
750 A.2d 823 (Supreme Court of Pennsylvania, 2000)
Bd. of Educ. of Clifton v. WR Grace
609 A.2d 92 (New Jersey Superior Court App Division, 1992)
Trevino v. General Dynamics Corp.
865 F.2d 1474 (Fifth Circuit, 1989)
State Ex Rel. Department of Transportation v. Guy F. Atkinson Co.
187 Cal. App. 3d 25 (California Court of Appeal, 1986)
McDermott v. TENDUN CONSTRUCTORS, ROHR INDUSTRIES, INC.
511 A.2d 690 (New Jersey Superior Court App Division, 1986)
Lerakoli, Inc. v. Pan American World Airways, Inc.
783 F.2d 33 (Second Circuit, 1986)
Daniel Edward Bynum v. Fmc Corporation
770 F.2d 556 (Fifth Circuit, 1985)
In Re All Maine Asbestos Litigation
575 F. Supp. 1375 (D. Maine, 1983)
McLaughlin v. Sikorsky Aircraft
148 Cal. App. 3d 203 (California Court of Appeal, 1983)
McKay v. Rockwell International Corp.
704 F.2d 444 (Ninth Circuit, 1983)
Koutsoubos v. Boeing Vertol, Div. of Boeing Co.
553 F. Supp. 340 (E.D. Pennsylvania, 1982)
Pratt v. Hercules, Inc.
570 F. Supp. 773 (D. Utah, 1982)
Brown v. Caterpillar Tractor Co.
554 F. Supp. 1269 (W.D. Pennsylvania, 1981)
In Re "Agent Orange" Product Liability Litigation
506 F. Supp. 762 (E.D. New York, 1980)
Sanner v. Ford Motor Co.
364 A.2d 43 (New Jersey Superior Court App Division, 1976)
Donham v. United States
536 F.2d 765 (Eighth Circuit, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
295 F.2d 14, 1961 U.S. App. LEXIS 3575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merritt-chapman-scott-corporation-a-corporation-and-the-savin-ca9-1961.