Marin Municipal Water District v. Peninsula Paving Co.

94 P.2d 404, 34 Cal. App. 2d 647, 1939 Cal. App. LEXIS 156
CourtCalifornia Court of Appeal
DecidedSeptember 26, 1939
DocketCiv. 10539
StatusPublished
Cited by22 cases

This text of 94 P.2d 404 (Marin Municipal Water District v. Peninsula Paving Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marin Municipal Water District v. Peninsula Paving Co., 94 P.2d 404, 34 Cal. App. 2d 647, 1939 Cal. App. LEXIS 156 (Cal. Ct. App. 1939).

Opinion

PETERS, P. J.

Defendant, Peninsula Paving Company, appeals from a judgment against it and in favor of plaintiff, Marin Municipal Water District, rendered in an action brought by plaintiff for damages for injury to its pipe line alleged to have been caused by defendant’s negligence in constructing a state highway.

The basic facts are not materially in dispute. The plaintiff is a municipal water district engaged in the business of supplying water to various municipalities in Marin County. In the performance of this function it maintains various distributing water mains. One such main was a twelve-inch cast iron main leading to the town of Sausalito. This main, so far as pertinent here, was partially imbedded in the western shoulder of the state highway leading to Sausalito, and entirely within the state right of way. This highway, for a portion of its distance, crossed a mud swamp. In 1932 the defendant paving company entered into a contract with the *650 department of public works, division of highways of the State of California, to construct a new state highway from a point designated as Waldo Point to Sausalito. This new highway was to replace the old highway, and roughly paralleled it. Where the new highway crossed the swamp the mud was twenty to sixty feet deep. The mud area between the old and new highways in some places was but thirty feet wide. In constructing the new highway the method of construction called for by the plans and specifications was to pile sufficient rock and dirt on the mud to cause it to settle through the mud to solid ground. The inevitable effect was to displace the mud, a considerable portion of which was forced to the west. The westward displacement exerted pressure against the old highway and caused that highway to move westerly in some places as much as ten feet. This caused the plaintiff’s pipe line to buckle and break, resulting in the injury which forms the basis of this action.

The pipe line originally had been installed in the center of the old highway in 1909, at which time the road was a county road. It became part of the state highway system in 1914. In 1916 the pipe line was moved to the west shoulder of the old highway, where it remained until the occurrences here described.

The defendant contractor, as well as the state engineers, knew of the existence of the pipe line. The contract between the state and defendant expressly called the attention of defendant to the fact that certain water, gas and sewer lines were buried within the limits of the work to be done, and provided that: “The contractor shall take every precaution to protect and preserve such lines from injury or damage during construction operations.”

The evidence showed that the work of the defendant was planned by the state engineers, and that the actual construction work was supervised and directed by the state engineers. The work done conformed in every detail to the plans and specifications furnished by the state, and everything done by the defendant was approved by the state engineers.

Prior to the commencement of construction the state informed plaintiff by letter of the proposed construction and warned it to protect its property. Complete plans of the construction were forwarded to the plaintiff.

*651 The theory of the complaint and the theory at the trial was that defendant contractor had so negligently performed the work that plaintiff was injured. The charging paragraph of the complaint, after describing the method of construction above set forth, alleged that the defendant: " did impose upon the mud adjoining said old county road large and unusual loads of earth and rock, and did negligently and carelessly permit said fill to accumulate in' large quantities and to unusual heights above the grade of the new highway, at given points alongside of said old county road, whereby the mud underneath was caused to be displaced, and was caused to escape from beneath the load of said earth, rock and other filling material, to the sides and underneath the old county road in which the pipes and transmission lines of plaintiff were so lawfully laid and maintained as aforesaid, and did cause said old county road to heave, bulge and crack, and did cause the water pipes and mains of this plaintiff to heave and bulge with the said county road, and did cause the joints thereof to leak and the said pipes to buckle and permit the water thereof to escape, and that through and by the negligence and gross carelessness of the said defendant Peninsula Paving Company this plaintiff suffered damage and injury to its said pipes in the sum of Twenty-Six Hundred Dollars ($2,600.00)”.

The trial court found this allegation to be generally true except that the court specifically found that the piling of the earth fill on the mud was “done and performed in accordance with the method ordered, directed and adopted by the Residence Construction Engineer of the Highway Department of the State of California; the Court further finds that under the plans and specifications of the contract between defendant and the State of California, the method and manner of performance of the aforesaid work by defendant at said time and place was specified to be so done under the direction and control of said State Highway Engineer”.

After finding that the plaintiff had received notice of the proposed construction and a copy of the plans, the court found that the plaintiff took no steps to protect its pipes at the place of damage (although it did make some 33 changes in its pipe line at other places along the line of construction), and that the plaintiff by the exercise of ordinary care “could not have discovered that in the performance of said contract by said defendant that the old road would shift”. *652 The court then made this finding: “The Court further finds that all materials deposited by defendant along and upon the right of way of said State Highway hereinabove mentioned, were deposited by defendant in conformity with the method and under the directions and orders of said State Highway Engineer, and that plaintiff had actual knowledge of the manner in which the work performed by defendant was being performed as it progressed from day to day.”

Appellant and respondent discuss at some length the nature of the right that plaintiff has in the state highway. By the provisions of section 19 of the Municipal Water District Act (Stats. 1.911, p. 1290; Deering’s Gen. Laws, 1931, Act 5243), under which plaintiff is organized, it is provided: “The right of way is hereby given, dedicated and set apart to locate, construct and maintain said works over and through any of the lands which are now or may be the property of this state, and to have the same rights and privileges appertaining thereto as have been or may be granted to municipalities within the state.”

. We do not find it necessary to now decide the exact nature of the right the plaintiff water district has in the state highway. We are not here involved with the question as to who shall bear the expense of any changes required by the construction of the new highway, or with any liability in eminent domain the state or .the highway department may owe to the plaintiff. So far as the contractor is concerned, the proper rule of liability is thus stated in Northwestern Pac. R. R. Co. v. Currie, 100 Cal. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrus v. State
541 P.2d 1117 (Utah Supreme Court, 1975)
Jefferson Incorporated v. City of Torrance
266 Cal. App. 2d 300 (California Court of Appeal, 1968)
State Highway Commission v. LA REYNOLDS COMPANY
159 S.E.2d 198 (Supreme Court of North Carolina, 1968)
Curtis v. Mississippi State Highway Commission
195 So. 2d 497 (Mississippi Supreme Court, 1967)
Smith v. Lockheed Propulsion Co.
247 Cal. App. 2d 774 (California Court of Appeal, 1967)
Strakos v. Gehring
360 S.W.2d 787 (Texas Supreme Court, 1962)
Southern California Gas Co. v. ABC Construction Co.
204 Cal. App. 2d 747 (California Court of Appeal, 1962)
Alisal Sanitary District v. Kennedy
180 Cal. App. 2d 69 (California Court of Appeal, 1960)
Steiger v. City of San Diego
329 P.2d 94 (California Court of Appeal, 1958)
Hamilton v. Harkins
304 P.2d 82 (California Court of Appeal, 1956)
Glade v. Dietert
295 S.W.2d 642 (Texas Supreme Court, 1956)
Anderson v. Fay Improvement Co.
286 P.2d 513 (California Court of Appeal, 1955)
Tidewater Construction Corp. v. Manly
75 S.E.2d 500 (Supreme Court of Virginia, 1953)
Moore v. Clark
70 S.E.2d 182 (Supreme Court of North Carolina, 1952)
Heimann v. City of Los Angeles
185 P.2d 597 (California Supreme Court, 1947)
Veterans' Welfare Board v. City of Oakland
169 P.2d 1000 (California Court of Appeal, 1946)
Beck v. Sirota
109 P.2d 419 (California Court of Appeal, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
94 P.2d 404, 34 Cal. App. 2d 647, 1939 Cal. App. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marin-municipal-water-district-v-peninsula-paving-co-calctapp-1939.