Mentor v. Kitsap County

588 P.2d 1226, 22 Wash. App. 285, 1978 Wash. App. LEXIS 2777
CourtCourt of Appeals of Washington
DecidedDecember 28, 1978
Docket3115-2
StatusPublished
Cited by10 cases

This text of 588 P.2d 1226 (Mentor v. Kitsap County) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mentor v. Kitsap County, 588 P.2d 1226, 22 Wash. App. 285, 1978 Wash. App. LEXIS 2777 (Wash. Ct. App. 1978).

Opinion

Petrie, J.

Respondent Larry Larson obtained permission from the Kitsap County Board of Commissioners to develop certain property in Silverdale, Washington. Petitioners, Joseph P. Mentor and Fred Hill, who own nearby lots, were displeased with the board's decision and sought review in Superior Court. They now appeal to this court from judgment entered in Superior Court approving the board's actions. By stipulation, petitioner Hill has been *287 dismissed from the appeal. For facility of discussion of the issues, however, we choose to continue reference to both petitioners at trial as the appellants. We affirm.

In late 1976, Larson, the owner of beachfront property in Silverdale, applied for a planned unit development permit (PUD) for a hotel facility; the plans included construction of a bulkhead along the beach. He also sought a rezone of the area. Both requests received affirmative recommendations from the Kitsap County Planning Commission. After the board approved the plans, petitioners obtained a writ of review challenging that decision. The matter was set for trial on June 20, 1977.

Meanwhile, Larson became aware that his 1976 application might, indeed, have been defective. He submitted a letter seeking reapproval of his plans and was informed by James Tracy, the Kitsap County Planning Director, that the letter would be sufficient to initiate a second proceeding. He was also told that the information would be incorporated into the second file. The first of several hearings was held by the commission in March 1977. On May 5, Larson resubmitted the requests for reapproval using the forms generally employed by the planning department. On May 31, the rezone and PUD were unanimously approved by the commission.

In order to avoid the need to try this matter twice, the parties stipulated that the challenge of the first approvals would be consolidated with any court challenge to the second proceeding. The first case was stayed pending resolution of the issues. On June 27, the board heard arguments concerning Larson's request and also discussed the adequacy of the environmental impact statement (EIS) submitted in this matter. Thereafter, orders conditionally approving the rezone and the PUD were issued and petitioners timely obtained a writ of review in Superior Court challenging the second approvals. This appeal follows judgment in favor of Larson and the board.

Petitioners' assignments of error can be grouped into two clusters — dissatisfaction with the planning department's *288 procedure, and a challenge to the adequacy of the EIS. We discuss first the procedural aspect of this case.

Petitioners maintain that the planning commission exceeded its authority by treating Larson's letter as a petition. There is no doubt that the letter of reapplication did not meet the formal requirements adopted by the planning agency pursuant to Kitsap County zoning ordinance No. 5.8.1. 1 An agency, however, may relax or modify its procedural rules when justice so requires. Such an action is reviewable only upon a showing of substantial prejudice to the complaining party. American Farm Lines v. Black Ball Freight Serv., 397 U.S. 532, 25 L. Ed. 2d 547, 90 S. Ct. 1288 (1970); NLRB v. Monsanto Chem. Co., 205 F.2d 763 (8th Cir. 1953). We find that the agency did not abuse its discretion by permitting Larson's letter to be used as a petition.

Three of petitioners' procedural arguments (admissibility of the transcript of an earlier contempt proceeding, preclusion of inconsistent positions, and estoppel) are attempts to "prove" that the reapplication was actually a separate action. All parties agree that the reapplication was a new action. Accordingly, we see no benefit in discussing these procedural arguments in detail. Although not completely clear, it appears that the three arguments were intended to buttress petitioners' belief that the commission acted improperly in supplementing the second application with materials submitted in support of the earlier request. As a general rule, an agency may base its decision on information gathered from other files or from independent investigations if such other material is introduced into evidence in the subsequent proceeding. State ex rel. Country Club v. Department of Pub. Serv., 198 Wash. 37, 86 P.2d 1104 (1939); Annot., 18 A.L.R.2d 552, § 11 (1951). In the case at bench, the Board of County Commissioners *289 had before it all the information previously compiled by the Planning Commission. We find no merit in petitioners' contentions.

We discuss next the substance of this appeal. Was Larson's environmental impact statement adequate? RCW 43.2lC.030(2)(c) requires that an EIS be prepared whenever "major actions significantly affecting the quality of the environment," is under consideration. Courts review the EIS to determine whether the environmental effects of the proposed action are disclosed, discussed, and substantiated by opinion and data. Ullock v. Bremerton, 17 Wn. App. 573, 565 P.2d 1179 (1977). The adequacy of an EIS is judged by the "rule of reason," however, and we need not concern ourselves with the remote and speculative consequences of the proposed action. Cheney v. Mountlake Terrace, 87 Wn.2d 338, 552 P.2d 184 (1976). Although the question of the adequacy of an EIS is one of law, Leschi Improvement Council v. State Highway Comm'n, 84 Wn.2d 271, 525 P.2d 774 (1974), the decision of the agency relative to the adequacy of an EIS is "accorded substantial weight." RCW 43.21C.090.

Petitioners first claim that the EIS does not contain sufficient information concerning the environmental consequences of constructing a bulkhead along the beachfront of the property. We disagree. The statement does briefly discuss the potential long-term effects of the bulkhead. Furthermore, it points out that a substantial development permit pursuant to the provisions of RCW 90.58 — the Shoreline Management Act of 1971 — must be obtained before commencing bulkhead construction. 2 We find that the EIS does meet the requirements of WAC 197-10-060(4), which provides:

Proposals involving extensive future actions may be divided, at the option of the lead agency, into segments *290

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Fork Hills Rural Ass'n v. Clark County
965 P.2d 650 (Court of Appeals of Washington, 1998)
Kiewit Construction Group, Inc. v. Clark County
920 P.2d 1207 (Court of Appeals of Washington, 1996)
Klickitat County Citizens Against Imported Waste v. Klickitat County
866 P.2d 1256 (Washington Supreme Court, 1993)
Solid Waste Alternative Proponents v. Okanogan County
832 P.2d 503 (Court of Appeals of Washington, 1992)
SEAPC v. Cammack II Orchards
744 P.2d 1101 (Court of Appeals of Washington, 1987)
Rauch v. Fisher
696 P.2d 623 (Court of Appeals of Washington, 1985)
City of Richland v. Franklin County Boundary Review Board
676 P.2d 425 (Washington Supreme Court, 1984)
Barrie v. Kitsap County
613 P.2d 1148 (Washington Supreme Court, 1980)
Wilson v. Nord
597 P.2d 914 (Court of Appeals of Washington, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
588 P.2d 1226, 22 Wash. App. 285, 1978 Wash. App. LEXIS 2777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mentor-v-kitsap-county-washctapp-1978.