Melancon v. Tri-Dyne Tele-Pier, LLC

95 So. 3d 576, 11 La.App. 5 Cir. 1055, 2012 WL 1957526, 2012 La. App. LEXIS 756
CourtLouisiana Court of Appeal
DecidedMay 31, 2012
DocketNo. ll-CA-1055
StatusPublished
Cited by1 cases

This text of 95 So. 3d 576 (Melancon v. Tri-Dyne Tele-Pier, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Melancon v. Tri-Dyne Tele-Pier, LLC, 95 So. 3d 576, 11 La.App. 5 Cir. 1055, 2012 WL 1957526, 2012 La. App. LEXIS 756 (La. Ct. App. 2012).

Opinion

WALTER J. ROTHSCHILD, Judge.

|2Plaintiffs, Ellie and Steven Melancon, and defendant, Tri-Dyne Tele-Pier, L.L.C. (“Tri-Dyne”), appeal the trial court’s July 29, 2011 judgment awarding $39,016.50 to plaintiffs, as well as expert fees of $3,225.00 and court costs. For the following reasons, we reverse and vacate the award of $39,016.50 and we remand to the trial court for further proceedings.

FACTS AND PROCEDURAL HISTORY

The Melancons and Tri-Dyne entered into a contract for elevation work to be performed at the Melancons’ home at 2068 Camille Court in Lafitte, Louisiana. According to the Melancons, Tri-Dyne performed defective work and did not complete the work agreed upon by the parties. On May 5, 2009, the Melancons filed this lawsuit against Tri-Dyne alleging that Tri-Dyne breached the contract between the parties and that Tri-Dyne’s defective work caused them to suffer damages. On June 30, 2009, Tri-Dyne filed an Answer and Reconventional Demand, in which it generally denied the Melancons’ allegations and sought [s$9,757.46 as the remaining amount due to Tri-Dyne under the terms of the contract. Trial of this matter was held on June 20, 2011.

At trial, Joseph Sproules testified that he is the owner of Tri-Dyne, which is a foundation contractor. Mr. Sproules testified that Tri-Dyne entered into a contract with the Melancons to elevate their home for $47,016.50. According to Mr. Sproules, Tri-Dyne purchased additional 6 by 6 sill beams for the property for $2,550.00, making the total amount of the project $49,566.50. A set of plans for the project were prepared by Edmond Pepper of the engineering firm, Pepper and Associates, Inc. In his testimony, Mr. Sproules acknowledged that some defects were present, but he contended that all of the deficiencies could be repaired and that the Melancons did not give Tri-Dyne the opportunity to repair the problems complained of.

[578]*578Mr. Sproules testified that the contract between the parties was signed in the beginning of May 2007 and work began in June 2007. Shortly thereafter, the Melan-cons met with Mr. Sproules because they had an issue with the workmanship and procedures used by the subcontractor who was building the footings, Jericho Foundation. Mr. Sproules appeared at the site and instructed Jericho on how to build the forms correctly. Work on the project continued thereafter.

Mr. Sproules testified that he was at the property within six or seven months before trial and he discovered that the foundation was not constructed as per the plans drawn by Mr. Pepper, because the footings and the piers in one section were not put in. He also admitted that the plans call for six north-to-south chain walls, but only five were installed because there was “cribbing”1 where a beam should be. Mr. Sproules testified that he informed the Melancons that the sixth beam could not be poured and told them to let him know if there were any problems with the | ¿structure so that he could make the necessary adjustments. He asserted that the Melancons did not tell him that there was any floor deflection caused by the missing beam.

Mr. Sproules admitted that there were some other deviations from the plans and that he did not consult the engineer who prepared the plans before making the changes. However, he testified that plans have to be modified somewhat during a project. Mr. Sproules believes that TriDyne completed the project, with the exception of one grade beam that should be installed.

The Melancons made an initial payment of $30,000.00 for the project. Mr. Sproules stated that the Melancons continued to make payments of $500 per month to TriDyne for 18 months after Tri-Dyne left the job site and never made any complaints about the foundation during that time. The Melancons stopped making payments in March 2009 and Tri-Dyne contends that the remaining due under the contract is $9,757.46.

Prior to trial, Mr. Sproules and Mr. Pepper inspected the property and noted some deficiencies in the construction. TriDyne’s estimate of the cost to repair the defects is $5,059.85.

Steven Melancon testified that after Hurricane Katrina, he and his wife hired Tri-Dyne to elevate their home. In his testimony, Mr. Melancon complained that the project was never completed and that there were numerous defects in the work performed. He stated that he was told that the house would be raised one time, but he contends that it was actually raised five times. Mr. Melancon testified that he met with Mr. Sproules on June 11, 2007, shortly after work on the project began, because he was not satisfied with the work of a subcontractor, Jericho Foundation. He stated that Jericho’s workers were slow, did not always show up, and the forms they prepared were flimsy. He further testified that Jericho’s workers did not even 1¡¡have a copy of the plans for the project, so he gave them a copy. He stated that when Mr. Sproules came to the site, he had Jericho tear out the foundation work they had done.

During his testimony, Mr. Melancon identified pictures of the property and defects in the work, including a gap between the chain wall and webbing, a cracked pier, a repaired pier, and other damage. Mr. [579]*579Melancon also stated that he was inside the house one time when it was raised and the sunroom was not raised with the rest of the house, causing the floor to separate and an exterior wall to pull away. According to Mr. Melancon, he informed Mr. Sproules of the problems caused by failing to raise the sunroom, but Mr. Sproules did not try to remedy the problem. He stated that he and his wife paid $4,400 to have some repairs made, such as sheetrock repair and having doors replaced.

Mr. Melancon further testified that he was initially informed by Tri-Dyne that the project would take 14 days to complete, but he contends that Tri-Dyne has never completed the project. He stated that there is floor deflection in the area where the sill was left out and that the furniture moves when anyone walks across that area of the floor. Mr. Melancon admitted that he did not notify Mr. Sproules in writing or otherwise about the floor deflection, because Mr. Sproules had ignored other issues that were brought to his attention.

Elbe Melancon testified that she was at home when the house was raised five times and when the sunroom was not raised with the rest of the house. She stated that after the initial payments to Tri-Dyne, they paid $500.00 per month because they were waiting on funds from the Road Home program. Mrs. Melancon testified that Tri-Dyne did not complete the elevation project, did not follow the plans, and took out a support beam without replacing it.

| fiPressley Campbell, a structural engineer, testified on behalf of the Melancons. He stated that he inspected the property in July of 2010, looked at the design drawings, and prepared a report of his findings. Mr. Campbell identified several substantial deviations from the plans and numerous deficiencies or defects in the work performed. He noted that there was a section in the footprint of the foundation where footing and chain wall were missing. He also identified photographs of defects in the structure. He noted that there was deflection of the floor where the chain wall was missing, many foundations where bolts were not secure or were missing, and the width of the chain wall was supposed to be 18 inches but varied from 15 to 17 inches, which could affect the integrity of the chain wall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vinet v. D & M Renovation, LLC
235 So. 3d 1304 (Louisiana Court of Appeal, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
95 So. 3d 576, 11 La.App. 5 Cir. 1055, 2012 WL 1957526, 2012 La. App. LEXIS 756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/melancon-v-tri-dyne-tele-pier-llc-lactapp-2012.