Lang v. Sproull

36 So. 3d 407, 2010 La. App. LEXIS 588, 2010 WL 1688636
CourtLouisiana Court of Appeal
DecidedApril 28, 2010
Docket45,208-CA
StatusPublished
Cited by6 cases

This text of 36 So. 3d 407 (Lang v. Sproull) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lang v. Sproull, 36 So. 3d 407, 2010 La. App. LEXIS 588, 2010 WL 1688636 (La. Ct. App. 2010).

Opinion

STEWART, J.

|, The plaintiff, Shonna Caldwell Lang (“Shonna”), sued the defendants, Dawn Sproull (“Dawn”) d/b/a Ark-La-Tex Shop Builders (“ALT”) and Howard “Rowdy” Prince (“Rowdy”) d/b/a ALT, for damages due to breach of a contract to build a metal shop next to her home and unfair trade practices. Dawn reconvened for the balance due under the contract.

Finding that Rowdy was not an owner of ALT, the trial court denied all claims against him. However, the trial court rendered judgment against Dawn as owner of ALT in the amount of $36,800 for damages due to breach of the contract to build and $3,004.50 for deposition costs and expert witness fees, plus additional court costs. *411 Shonna’s remaining claims were denied. The trial court granted Dawn’s reconven-tional demand, awarding her $6,747.

Shonna now appeals the award of $6,747, the finding that Rowdy was not an owner of ALT, and the denial of her other claims. Answering the appeal, Dawn asserts that the damages awarded to Shonna were excessive. For the reasons that follow, we find that the trial court erred in granting the reconventional demand, in finding that Rowdy was not a partner in ALT, and in awarding certain damages for breach of the contract to build.

FACTS

On September 13, 2005, Shonna contracted with ALT for the construction of a metal building measuring 30 feet by 50 feet to be used as a boat storage area, a workshop for her husband, and a play area for her children. The contract provided that ALT would furnish dirt for the pad totaling 10 loads. No other specifications regarding elevation or preparing |2the site for construction were included in the contract. The contract also provided for a slab inside the building and a porch. The contract price was $23,147, but this amount was reduced to $21,747 when the parties agreed to shorten the height of the walls from 12 feet to 10 feet.

ALT constructed the building and completed the porch in about a week in October of 2005. Shortly after completion, Shonna met with Rowdy and Derek Gore, an ALT employee who had previously met with Shonna and had prepared ALT’s proposal for the job, to address issues concerning the poor appearance of the porch and problems with drainage. Thereafter, ALT poured additional concrete over the porch area and then applied a finish after the concrete hardened. To address problems with drainage, ALT dug a swell or ditch along the side of the building to direct the flow of rainwater around the building. ALT also sent someone to move dirt that had been piled against Shonna’s trees.

Despite ALT’s efforts to address the drainage issues, problems persisted. Water entered the front of the building flooding the floor area. Water also settled in the swell creating a muddy mess. Though there is much dispute in the record regarding the communications between ALT and Shonna about the drainage problems and attempts by ALT to collect payment, Shonna ultimately tendered payment in the amount of $15,000 to ALT on November 21, 2005. Because the amount tendered was less than the contract price, ALT placed a lien on the property on November 23, 2005. Thereafter, Shonna sought the advice of other contractors who offered proposals for addressing the drainage problems and who revealed other problem areas with the construction.

| ¡¡Asserting that the building was not constructed in a workmanlike manner and seeking damages for numerous alleged defects and unfair trade practices, Shonna filed suit for breach of contract on August 17, 2006, against Rowdy and Dawn as the owners of ALT. In their answers, both Rowdy and Dawn asserted that ALT was a sole proprietorship owned by Dawn and that Rowdy was merely an independent contractor. Dawn also reconvened against Shonna for the balance due on the contract.

At the close of the bench trial, the trial court found that ALT was owned by Dawn and that Rowdy was merely an employee of the business. Upon finding that the workmanship by ALT was substandard and considering the expert testimony offered by Shonna, the trial court awarded her the following damages:

• $13,000 to remedy elevation and drainage problems.
*412 • $5,000 to remove and repour concrete that ALT had poured directly against the vinyl skirting on the mobile home when constructing the porch.
• $400 for new skirting on the mobile home.
• $800 to repair gaps in a doorway area of the building.
• $15,000 to remove and repour the concrete slab inside the building.
• $8,100 to remove and replace metal siding that had corroded along part of the building where dirt was piled against it.

The trial court also ordered Dawn as owner of ALT to pay expert fees, deposition costs, and court costs. All other claims by Shonna were denied. Though the trial court said it was rejecting the reconven-tional demand by Dawn for the contractual balance due, it entered an order by minute entry the next day to allow Dawn the credit for the balance due on the contract.

| Judgment was rendered on April 16, 2009, against Dawn d/b/a ALT in the amount of $36,800 in damages, $3,004.50 in expert fees and deposition costs, plus additional court costs, and against Shonna in the amount of $6,747 on the reconventional demand. The judgment also provided for cancellation of the lien. All claims against Rowdy were denied and all other claims asserted by Shonna were denied.

Following the denial of her motion for a new trial, Shonna appealed. Dawn answered the appeal to assert that the award of damages was excessive. We will now address the issues raised in the appeal and answer.

DISCUSSION

Because the issues on appeal are factual, our review is limited to a determination of whether the trial court’s findings of fact are manifestly erroneous or clearly wrong. We do not determine whether the factfinder was right or wrong but whether its conclusions were reasonable. Stobart v. State, Through DOTD, 617 So.2d 880 (La.1993). Reasonable evaluations of credibility and inferences of fact should not be disturbed on review where there is conflicting testimony. Id. Where documentary or objective evidence contradicts a witness’s story or the story itself is internally inconsistent or implausible such that no reasonable trier of fact would credit it, then we may find manifest error even in a finding purportedly based on a credibility determination. Id. But in general, where there are two permissible views of the evidence, the factfinder’s choice between them cannot be manifestly erroneous or clearly wrong. Id.

\ friability of Howard “Rowdy” Prince

Dawn argues that the trial court erred in failing to find that Rowdy was a partner in ALT. We agree.

Our law defines a partnership as a “juridical person, distinct from its partners, created by a contract between two or more persons to combine their efforts or resources in determined proportions and to collaborate at mutual risk for their common profit or commercial benefit.” La. C.C. art. 2801.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coleman v. Querbes Co. No. 1
218 So. 3d 665 (Louisiana Court of Appeal, 2017)
Debaillon v. Alfred (In re Anderson)
539 B.R. 277 (W.D. Louisiana, 2015)
Melancon v. Tri-Dyne Tele-Pier, LLC
95 So. 3d 576 (Louisiana Court of Appeal, 2012)
Settles v. Paul
61 So. 3d 854 (Louisiana Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
36 So. 3d 407, 2010 La. App. LEXIS 588, 2010 WL 1688636, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lang-v-sproull-lactapp-2010.