Judgment rendered October 22, 2025. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 56,440-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
ANDREW MCBRIDE AND Plaintiffs-Appellants GINGER MCBRIDE
versus
RAFAEL LARA Defendant-Appellee CONSTRUCTION, LLC
Appealed from the Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 20192395
Honorable Jefferson Bryan Joyce, Judge
TYLER GRAHAM STORMS Counsel for Appellants
DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: Martin Shane Craighead
Before STONE, ROBINSON, and HUNTER, JJ. ROBINSON, J.
Plaintiffs, Andrew and Ginger McBride (collectively, “Plaintiffs” or
“the McBrides”), filed suit in Ouachita Parish against Defendant, Rafael
Lara Construction, LLC (“Defendant” or “Lara”), for breach of a
construction contract entered into between the parties for various alleged
deficiencies in the construction of their home. Lara filed a reconventional
demand for the balance owed on the contract as of the date he was
terminated. Trial was held on February 26, 2024. The trial court issued a
judgment and written reasons for judgment on May 8, 2024, awarding the
McBrides a total of $35,400, offset by an award to Lara of $13,540 for its
reconventional demand, for a net award to the McBrides of $21,860. Both
parties filed motions for new trial. After a hearing on the motions, the trial
court issued its second judgment and written reasons for judgment on
October 24, 2024, reducing its total award to the McBrides by $13,500 and
Lara’s award by $3,800, for a net award to the McBrides of $12,160. The
McBrides filed a devolutive appeal.
For the following reasons, we AFFIRM the trial court’s judgment.
FACTS AND PROCEDURAL HISTORY
The McBrides and Lara entered into a contract for the construction of
the McBrides’ home on August 22, 2018. Plans and specifications had been
prepared by an architect, Allan Pogue (“Pogue”), in the summer of 2018 and
were incorporated into the contract. Construction of the home commenced
with the pouring of the foundation in early October 2018.
The McBrides complained of several deficiencies in the construction
of their home and ultimately terminated Lara. The McBrides paid third parties to complete the home after Lara’s termination. They claim they
spent approximately $45,000 over the maximum contract amount and
provided receipts therefor, although Lara claims that the McBrides
overstated the amount by approximately $25,000. Although there were
copies of estimates for certain repair work in the record, there were no
itemized receipts showing what was actually spent by the McBrides
following Lara’s termination.
Alleged Construction Defects
The McBrides first complained of construction defects when there
was exposed rebar in the foundation as well as wood forms that remained
embedded. Shortly after, during the framing process, the wall between the
garage and kitchen misaligned with the anchor bolts in the foundation. The
McBrides claim they did not terminate Lara at that time because they were
assured the wall could be pushed in, and they did not realize that the
embedded forms resulted in a likelihood of termite intrusion, rot, and
honeycombing of the slab. However, Chad Parker (“Parker”), of Inspections
Unlimited, testified that the open wall with exposed anchor bolts passed
inspection.
Rafael Lara (“Mr. Lara”) testified that conflicts with the McBrides
began when Lara used the Weyerhaeuser Gold brand of floor decking rather
than the Advantech brand orally requested by the McBrides. Mr. Lara
explained that he had intended to use Advantech, but that it was not in stock
at that time. Mr. Lara agreed to double the decking used with no charge in
order to satisfy the McBrides, and the McBrides stated that they accepted the
2 remedy because the contract specifications did not require the Advantech
product.
The roof was installed on the house in December 2018. Mr. Lara
testified that he chose to roof the house earlier than usual due to the
excessive amount of rain there had been during the project. He stated that he
was aware that there would be some damage to shingles from installing the
brick and siding after the shingles were in place, but he wanted the house to
be sealed as much as possible so that issues with water intrusion would be
minimized. Lara used 7/16” OSB (oriented strand board) roof decking,
while the specifications listed 5/8” foil-backed decking with plywood clips.
Lara also used 26-gauge galvanized aluminum flashing for the roof in
locations where there would be brick and 26-gauge powder-coated
aluminum trim coil for the exterior flashing. The specifications listed 26-
gauge galvanized steel for the roof. The McBrides claim that they
specifically requested the 5/8” decking listed in the specifications because it
was a higher quality, stronger material, alleging later that the 7/16” decking
was an inferior product that caused the roof to sag. Mr. Lara testified that he
did not recall any specific direction from the McBrides regarding the
decking. Lara claims that both sizes of decking were code-compliant and
would work the same in this situation, because the product’s thickness
related more to snowpack, which was not applicable in this locale, especially
with the steep pitch of the McBrides’ roof. Pogue testified that the roof
decking on the house was appropriate and consistent with the specifications.
The McBrides also claim that the aluminum flashing used by Lara
was an inferior product and not as durable. Mr. Lara testified that he does
3 not like to use the galvanized sheet metal because it is not aesthetically
pleasing, and he prefers to use aluminum trim coil, because it will not rust
like the steel product, and it is powder coated to match the eaves and soffits
of the house. He noted that the product used was also a 26-gauge metal.
Following installation of the roof, there were leaks in three different
locations: between the garage and house below the laundry room; in front of
the dormer into the office; and over the back side of the garage into the
dining room area. Mr. Lara testified that at the time of the leaks, the
flashing had not yet been installed. Insulation had been sprayed into the
walls, but no sheetrock had been installed. He stated that, upon discovery of
the roof leaks, Lara removed the insulation to ensure there were no leaks
behind the wall. Once flashing was installed, Mr. Lara soaked all the
flashing with a pressure nozzle hose to check for leaks, which he videoed
and sent to the McBrides. At some point during this process, Mr. McBride
claimed that the walls were still leaking. Mr. Lara testified that he inspected
the walls by physically putting his hands between the walls and the delta
straw (plastic sheeting at the bottom of the house), applying paper towels to
the foam boards between the studs, and cutting holes in the upstairs
sheetrock, none of which indicated any moisture. Dakota Breshears
(“Breshears”), who was Lara’s project manager during the time of the
McBrides’ project, testified that a moisture meter was used on the entire wall
where there had been a leak, and the studs were checked top to bottom. Mr.
Lara determined that the leaks in the garage/dining room area were due to
some holes in the shingles made from attaching the toeboards to the roof
during the vinyl installation. He stated that the holes were sealed, with the
4 intention to later replace the shingles, which stopped the leaks. Mr. Lara
also determined that the leak in the office area was from the off-centered
dormer. Lara adjusted the framing to center it up better.
Despite not finding any moisture following the repairs and testing,
Lara scheduled a sheet metal company to install additional flashing in the
roof valleys that may be prone to leaks. Because rain was predicted, Lara
installed temporary hog troughs (large metal sheets bent to the area) in the
roof valleys until the permanent custom flashing could be done in order to
prevent any further leaks. However, the McBrides ordered Lara to stop
work on the project immediately after Lara had installed the temporary hog
troughs and prior to the custom permanent flashing installation.
The McBrides also expressed concern over 10 of the 12 windows
being difficult to lock or open and close, especially regarding safety issues.
Mr. McBride testified that he had a window sales representative, Brian
Abernathy (“Abernathy”), inspect the windows. He told Mr. McBride that
the windows had not been installed properly and that the cavity was too
small. However, Dale Lusby (“Lusby”), a Russell Moore salesperson who
coordinated with the window manufacturers, testified that he also went to
the house to inspect the windows along with another Ply Gem sales
representative, Scott Hall (“Hall”). Lusby testified that he and Hall
concluded that only a few windows were “closing tight,” but they could be
improved by replacing the window sashes with a smaller size. Lusby stated
that the cost to replace the sashes would be approximately $400 to $500, but
they would have replaced them for free as a courtesy. Lusby further testified
that he received an email from Abernathy, who Mr. McBride testified had
5 also inspected the windows, in which Abernathy relayed that the windows
were actually installed pretty well. Abernathy stated that, although there
were some exceptions in which the window seals were slightly crowned,
resulting in preventing a sash from completely closing to lock, they were not
off by much. He also stated that he did not recommend changing out all the
windows.
The McBrides claim that front elevation was shoddy and defective, in
that the planned louvers and gables were either off center or not existing,
and otherwise not built to specifications. Lara reconstructed the gable and
dormer to recenter it. Mr. Lara testified that it measured within 1/16” from
center. However, Mr. McBride testified that, although the gable and dormer
were improved, they were still “off” and did not look like what they should
have per the plans. Mr. Lara further noted that the dormer was removed
altogether after the job was shut down and he was terminated.
Mr. McBride testified that the stones on the front façade were severely
gapped and only pressed in, there were sections with no mortar, and some
stones had fallen off. He stated that, following Lara’s termination, he had
someone replace the fallen stones and repaired sections in the front entry
area, but that it still looked terrible. Mr. Lara testified that the stones were
installed according to the manufacturer’s instructions, and he intended to
replace any missing stones prior to completion of the project as a “punch
list” item. Breshears testified that the stone façade was not complete
because it was installed prior to the vinyl, metal soffits, and fascia material.
He explained that the stone had to be left short in order to properly install the
6 metal on the bird boxes on the corners so that the vinyl could go all the way
in, then they would go back and fill in those sections.
The McBrides also complained that Lara used regular sheetrock
instead of moisture-resistant sheetrock in the garage. Mr. McBride testified
that Mr. Lara asked to change the wood paneling listed in the specifications
to drywall, and he agreed to the request, but only if it was moisture-resistant.
Mr. Lara testified that he intended for the “green rock” moisture-resistant
sheetrock to be used around the garage door only, and that regular drywall
was appropriate for the rest of the garage, but that he offered to use the
moisture-resistant product for the entire garage to satisfy the concerns of the
McBrides. He further noted that the wood paneling listed in the
specifications was not code-compliant. Parker also testified that the 3/8”
wood paneling was not code-compliant and would not have passed
Mr. McBride testified that he had two third-party contractors provide
estimates for certain repair work. Pike Bryant Construction provided an
estimate to reconstruct the roof per plans and specifications and change out
the garage drywall. Achievers of Louisiana, Inc. provided an estimate to
change out the windows, remove and replace the stone veneer, add
insulation, and redo drywall. However, neither contractor ever performed
any work for the McBrides’ home. Once Lara was terminated, Mr.
McBride, though unlicensed, assumed responsibility as the “contractor,” and
the McBrides hired Giovani Penada (“Penada), who is also unlicensed, as a
manager/consultant to complete the repairs they alleged were necessary.
Notably, the McBrides complained that some of the alleged deficiencies in
7 the construction were attributable to Lara using some unlicensed
subcontractors, to the extent the McBrides reported the issue to the
Louisiana State Licensing Board for Contractors.
The McBrides claim that they spent approximately $44,000 over the
contract price of $360,950.23 – approximately $405,000 total – to get the
house in a “livable condition.” However, there are no invoices or receipts in
the record to support the amounts claimed to have been spent by the
McBrides to finish the project. The McBrides claimed that it would be more
efficient to testify as to what was done and give the maximum contract
amount to support the amounts rather than introduce numerous receipts.
Megan Lara (“Mrs. Lara”), who handles all bookkeeping and general
office management for Lara, testified regarding the expenses of the McBride
project. She first pointed out that no profit was ever billed to the McBrides
since Lara was unable to complete the project. Mrs. Lara discussed at length
the information that Lara had received regarding the work performed on the
McBrides’ home by others following its termination (which was not
included in the record). She testified that there were multiple expenses for
work that were not included in the contract and plans, such as brick work on
the steps, additional dirt work, and even miscellaneous items like candy bars
and sodas. Mrs. Lara noted a particular invoice from Penada included an
expense of almost $20,000 for a driveway, at least in part due to higher labor
rates that were almost double those quoted by Lara, when Lara’s driveway
allowance was only $7,000. She also referred to expenses from change
orders, such as certain light fixtures, an outdoor kitchen, and running an
extra gas line. Mrs. Lara testified that it was unnecessary to spend $405,000
8 to finish the job, because at the time that Lara was terminated, there was still
every amount left in the budget to finish the job in an acceptable manner,
and it was not Lara’s responsibility to incur the extra costs. She reiterated
that Lara was not allowed to correct any defects that they would have
corrected by the time the project had been completed, and she did not
believe Lara should be responsible for the premature cancellation of their
contract.
Repair Negotiations
On February 20, 2019, sometime during the process of Lara’s repair
of the roof flashing, McBride suspended work on the house. The McBrides
sent a demand letter to Lara on February 26, 2019, complaining primarily of
the roof leaks and improperly built roof gable and dormer over the front door
and stating that they had lost confidence in Lara’s ability to complete the
job. The McBrides proposed three options: (1) Lara remedies all defects
listed within the letter, which included 18 numbered items, at Lara’s expense
and at the direction of a consultant to be chosen by the McBrides, in single
stages to be approved by the McBrides upon completion of each stage, with
the home to be completely finished within 60 days; (2) Lara covers the
complete cost of another contractor of the McBrides’ choosing to repair and
finish the home, at a referenced approximate cost of $200,000; or (3) Lara
purchases the home in an “as is” state for $319,000, with any claims due
against the property being Lara’s sole responsibility.
Mr. Lara responded by letter to the McBrides on March 1, 2019,
stating that he disagreed with almost all the allegations. Mr. Lara
acknowledged some issues with water during the heavy rains in connection
9 with the steep roof valleys on the front of the house and recommended the
process for correction of the issue. He noted that he was unable to undertake
any of the recommended measures since the job had been shut down, but
that he was willing and ready to finish the project. He also proposed using a
mediator to work through any of their conflicts.
Following the initial correspondence between the parties regarding the
alleged defects, the McBrides hired Michael Burroughs (“Burroughs”) with
QED Service, a licensed home inspector, to conduct a visual inspection of
the property, which took place on April 29, 2019. The McBrides also
retained counsel, Charles Heck, Jr. (“Heck”), to represent their interests
regarding the dispute. Heck sent a follow-up demand letter to Lara on
behalf of the McBrides on June 3, 2019, regarding the initial alleged defects,
as well as those identified by Burroughs’ inspection. A copy of the
inspection report and third-party estimates for alleged necessary repairs were
attached to the letter. The letter referred to the following defective
conditions and repairs therefor:
1. Specified 5/8” decking was not used, requiring removal and replacement of the entire roof, since patching would result in mismatched shingles.
2. 26-gauge metal flashing specified was not used.
3. Insulation from the garage to the ceiling, garage to the house wall, roof line, and between floors, is either missing or improperly sealed.
4. Stone on the front of the home was incorrectly installed, some pieces are falling off, and corner pieces are missing.
5. Sheetrock is missing in certain areas and is either incorrectly installed in other areas or damaged from prior attempts to repair roof leaks.
6. Windows were improperly installed.
10 7. The window above the entry archway is off center, making the house appear crooked, necessitating replacement including stone repair.
8. Sheetrock in the garage must be replaced with moisture board.
Certain resolution options were again proposed. First, Lara may make all
repairs specified in the demand letters and finish the project but must be
under the supervision of a consultant. Second, the McBrides will transfer
the home for the sum of $325,000 plus attorney fees incurred. Third, Lara
may pay for the repairs to be performed by the third-party contractors who
provided the repair estimates to the McBrides. The letter stated that the
McBrides intended to file suit should Lara refuse to take action per their
demand.
In response to the McBrides’ demand, Lara retained Shane Craighead
(“Craighead”) as counsel. Craighead sent a response letter to Heck on June
13, 2019. Lara proposed to attempt a mediation conference to discuss all the
issues raised by the McBrides, using a mediator with experience in
construction. Craighead’s letter addressed all the issues raised in Heck’s
June 3 letter, as follows:
1. The reference in the specifications to 5/8” decking was innocuous, as industry standard is either 1/2” or 7/16” decking. There were never any discussions between the parties to use 5/8” decking and Lara did not charge for that product. Further, there are no defects with the roof as currently constructed, and it would be senseless to replace an entire roof simply based on the difference of 1/8” thickness in the decking.
2. The 26-gauge metal flashing specified used was industry standard, code compliant, and as obtained by the local supplier.
3. The garage, including the ceiling, is insulated. Should the McBrides wish to have additional insulation on the interior wall between the garage and the house, Lara is willing to do that. The
11 insulation between floors is not blown in until after wires are pulled for final light fixtures, at the end of construction.
4. The plans do not specify any stone material that would be deemed a “corner piece.” The two places on the front porch area where stones fell off are easily repairable and demolition of the entire façade is unnecessary.
5. The missing sheetrock was removed in order to investigate the McBrides’ leak claims and Lara intended to replace them.
6. The window sales representative indicated a couple of windows have molding slightly intruding the window track, which is easily fixed.
7. The window above the entry archway was initially slightly off center, but it was already taken down and corrected where it is now centered.
8. The plans actually called for wood paneling/plywood with a paint finish for the garage interior, but was upgraded by Lara with sheetrock, which is code compliant. Nonetheless, Lara is willing to replace it with plywood.
Craighead sent an additional letter to Heck on July 2, 2019, in order to
further elaborate on the issues previously addressed in Craighead’s June 13
letter. It was reiterated that Lara stood ready to complete construction of the
home; however, Lara would not be responsible for completion of any work
or resulting expense should the McBrides choose other builders to complete
the home.
The McBrides provided Lara with written notice of official
termination due to its “failure … to comply with the terms of the agreement,
numerous deficiencies, and very poor workmanship,” noting that they would
be pursuing damages for breach of contract. The McBrides ultimately filed
suit on July 31, 2019. A one-day trial took place on February 26, 2024.
Dave Jackson Meeting and Phone Conversation
12 During the period in which the McBrides had suspended work, Mike
Hipp (“Hipp”), the McBrides’ loan officer, contacted Dave Jackson
(“Jackson”), another licensed contractor, hoping Jackson would get involved
as a mediator between the parties and facilitate completion of the project.
Jackson ultimately met with Mr. McBride and Hipp at the site to inspect the
construction project and discuss the McBrides’ concerns.
Jackson passed away prior to trial. Over Lara’s objection, Mr.
McBride was allowed to testify as to his version of what Jackson said during
the meeting. Mr. McBride testified that Jackson said he would tear off the
front veneer, and that Lara was “one hundred percent liable and responsible
for” using the wrong decking and “responsible for” the drywall in the
garage.
Mr. Lara learned of the meeting shortly after and called Jackson to
discuss, recording the telephone call conversation. Over the McBrides’
objection, the recorded call between Jackson and Mr. Lara was introduced
into evidence. Lara argues that the recorded conversation serves as
impeachment evidence because it directly conflicts with Mr. McBride’s
testimony regarding Jackson’s statements at the inspection.
During the phone call, Jackson first explained to Mr. Lara that he
knew Hipp from when he had built Winnsboro State Bank, and he agreed to
the meeting and inspection because of that business relationship. Jackson
stated that, before Mr. McBride arrived at the site, he had already looked at
the roof and told Hipp that there was nothing wrong with it and he did not
see any dipping and sagging between the rafters. Jackson stated that once
Mr. McBride arrived, they went through the house to discuss various
13 concerns of the McBrides. He said Mr. McBride pointed out issues with the
cabinets, but that he explained that they were only roughed in at that stage
because they still needed to be painted, and they only needed adjustments.
Jackson then stated that Mr. McBride referred to issues with the flashing and
roof leaks. He explained that there were different ways to install flashing.
Mr. Lara told Jackson that it was double-flashed, and Jackson commented
that the leak was an easy fix. Jackson stated that Mr. McBride never said
anything to him about the windows during the meeting, though he noticed
that they just needed to be caulked. Jackson said he told Mr. McBride that
he needed to bushhog the property, telling Mr. Lara that it looked like it had
been neglected. Jackson said that he told Hipp after Mr. McBride had left
that it appeared the McBrides were complaining of punch list items while
construction was ongoing. Jackson commented to Mr. Lara that he did not
find a difference between 7/16” and 5/8” OSB roof decking. He further
noted that Hipp told him that the McBrides were not willing to drop the suit,
which would be a condition for him to mediate the project. Jackson also
commented that Mr. McBride seemed to “have it out” for Mr. Lara for
whatever reason.
Hipp also testified that he listened to the recorded conversation, and it
was consistent with Jackson’s statements that he had heard during their
meeting. Hipp also stated that he observed Jackson cleaning out the channel
of one of the windows and then operating it without problem.
Burroughs’ Inspection and Testimony
Burroughs was hired by the McBrides to conduct a visual inspection
of the property. Neither a technical (in depth) inspection nor a mold
14 inspection was conducted. Burroughs prepared a detailed inspection report
in which he referenced multiple findings regarding the grounds and concrete,
slab, framing, roof (shingles and flashing), siding and masonry, windows,
HVAC system, plumbing, electrical, walls and ceilings, carpentry. For the
majority of the findings in the report, a notation was included that read,
“Discretion advised. The significance of the finding is uncertain. Further
study by a qualified licensed contractor is advised.”
The McBrides later retained Burroughs as an expert in home
inspection and price estimation. Notably, he was not qualified as an expert
in construction. Burroughs testified as to the McBrides’ allegations and
elaborated upon the findings in his inspection report. He acknowledged that
the home was in an unfinished state, and his testimony regarding all issues
was in light of that.
Burroughs first pointed out that there were cracks in the concrete
driveway and parking areas. He also noted that he observed issues with the
foundation, including wood and rebar that remained exposed, honeycombing
in the concrete, and several anchor bolts that were not activated.
He also discussed several issues with the roof. He testified that the
improper flashing allowed too much runoff, which caused leaks. He stated
that he observed some cupping or sagging of the decking, there were nails
exposed that were not properly sealed, and the shingles were lifting because
they were either installed too tightly or improperly. He further stated that
the flashing was bent and improperly cupped in and was missing kickouts.
He testified that the lightweight metal is lower grade and does not hold up to
15 wind, but he could not tell whether the roof was “up to code” since he could
not see underneath.
Burroughs testified regarding the use of 7/16” versus 5/8” roof
decking. He explained that, in the past, 1/2” roof decking on 24” centers
was standard, but building codes have changed to increase the thickness of
the decking and to narrow the spacing in order to increase the PSF (pounds
per square foot) ratings, because roofs were getting “bellies,” sagging
between the rafters. Although he stated that he observed some sagging in
the roof, Burroughs did not specifically testify as to whether the use of the
7/16” decking was the reason for the sagging, only that the use of the
product generally may have that result.
Burroughs pointed out that there were areas in the siding with no
moisture barriers or extreme gapping, though the siding installation was not
complete. He testified that there was loose siding, cracks in several
locations, and gaps in the fascia, soffit boxes, and cornices. He explained
that construction/installation of the soffits and fascia was complete.
Burroughs further testified that the windows were out of plumb and
pinched, and they should have been functioning at that stage. Instead, there
were gaps around the windows, headers missing weepholes, and the siding
was improperly flashed and caulked.
Burroughs was questioned regarding the stone façade. He stated that
the panels had large gaps where water could enter and get behind the
moisture barrier. He specifically testified that if it were his property, he
would tear off all the stone because the condition of the substrate was
16 unknown, in that damage from water intrusion could not be fully assessed
without destructive means.
Burroughs opined that the costs to correct the defects and replace
materials with those included in the specifications would be in the range of
$250,000 to $350,000, though most likely closer to $350,000 plus a 15%
contingency for potential damage done to otherwise proper work in the
process of making the corrections. This amount included but was not
limited to: $75,000 to demolish the roof, redo the decking, and replace the
roof; $15,000 – $20,000 to replace all of the stone façade, including redoing
the moisture barrier; $100,000 to remove and replace all the windows
because they could not be repaired; $15,000 to install moisture-resistant
sheetrock in the garage; $10,000 – $15,000 to correct the front gable and
dormer; and $2,000 – $3,000 to correct the exposed anchor bolts.
Rafael Lara Testimony
Mr. Lara testified on behalf of himself and the company and was
qualified and accepted by the court as a construction expert. He testified
that he had been a licensed contractor since 2010, approximately 98% of his
work was residential and 90% of the residential work was custom homes.
He further testified that he had built between 140 and 150 homes since being
licensed, and he also had four years of university training in construction
management, though he had not obtained a degree in that curriculum. Also,
other than one dispute in which he still completed the project, he has had no
significant complaints from customers.
Mr. Lara testified regarding the roof decking thickness. He stated that
7/16” OSB decking is code compliant, and that he has used the product for
17 approximately 98% of his construction jobs without any complaint. He
explained that 5/8” decking was unnecessary in this climate because we did
not have to be concerned with snowpack. He pointed out that it was also not
necessary for the McBrides’ home due to the pitch of the roof. He also
provided an explanation regarding the use of foil backing, specifically in
conjunction with spray foam insulation, as was specified for the McBrides’
project. He stated that the spray foam insulation essentially will not bond,
that it will get so hot that the foam will shrink and fall off.
Mr. Lara also pointed out other instances in which the specifications
were not appropriate, and adjustments were made. He noted that they called
for 2500 PSI (pounds per square inch) concrete with fiberglass for the
foundation, which he did not recommend and was not used, because a 3,000-
3500 PSI should be used on a house foundation, the fiberglass makes the
concrete weaker, and some small strands of the fiberglass can stick up
through the surface. Also, the specifications called for 3/8” wood paneling,
which is plywood, which is not code compliant. Further, 26-gauge
galvanized steel was specified, but he opted to use powder-coated aluminum
trim coil for the exterior flashing because it was more aesthetically pleasing,
and it would not rust easily.
Mr. Lara maintained the position throughout his testimony that he
always intended for Lara to make any repairs necessary but was simply
prevented from finishing the project.
Trial Court Findings
Following trial, the court issued its original judgment and written
reasons for judgment on May 8, 2024, awarding the McBrides a total of
18 $35,400, offset by an award to Lara of $13,540 for its reconventional
demand, for a net damage amount to the McBrides of $21,860 plus judicial
interest. The court stated that, based on the testimony and exhibits
presented, there were multiple errors associated with the building of the
home; however, it was unable to determine the alleged damages as set forth
by the McBrides due to the lack of evidence supporting the damage claims
as well as several discrepancies between the filings and the evidence entered
at trial.
The court referred to the McBrides’ argument that they spent
$405,345.83 to substantially complete the house albeit with defects, alleging
an overpayment of $59,167.98, yet there was no evidence or proof of
payment of the amount, only some estimates for work that had not been
performed. It pointed out the discrepancy in the claims that work was
necessary to repair roof leaks, faulty stonework, windows, insulation, and
sheet rock, but there was no proof that any work was actually performed.
The court ultimately found that the McBrides should recover damages
for the numerous errors, including Lara’s use of 7/16” roof decking versus
the specified 5/8” decking, the leaks in the laundry room and dining room,
the dormer being off center in the office, and the windows having issues and
closing too tightly. Accordingly, the court awarded damages to the
McBrides in the amounts of $10,000 for the faulty stone façade, $12,500 for
the front elevation/dormer damage, $400 for window sash replacement,
$7,500 for drywall in the laundry room and dining room, and $5,000 for
installing the incorrect roof decking. The court also found that Lara was
19 entitled to recover the unpaid invoice amount of $13,540, noting it was not a
suit on an open account and Lara was not entitled to attorney fees.
Both parties filed motions for new trial. After a hearing on the
motions, the trial court found grounds to reconsider the previous judgment
and issued its second judgment and written reasons for judgment on October
24, 2024. The court reduced the total award to the McBrides by $13,500,
and reduced Lara’s award by $3,800, resulting in a net award to the
McBrides of $12,160 plus judicial interest. It found that the previous award
of $10,000 for the stone veneer was excessive and instead awarded $1,500
for repair. It also reduced the $7,500 amount for drywall in the laundry
room and dining room to $2,500 based on the arguments that the actual
repair costs would be much less because the affected area was relatively
small. As for the reduced amount due to Lara, the parties agreed and the
court recognized that the McBrides had paid separately for the septic system
installation, so the invoice amount should have been $3,800 less.
The McBrides filed a devolutive appeal.
DISCUSSION
Admissibility of Recorded Telephone Conversation
The McBrides argue that the recorded phone conversation between
Jackson and Mr. Lara should not have been considered, because it did not
serve to impeach anything that Mr. McBride said. They explain that Mr.
McBride testified about what Jackson observed and commented on at his
meeting with Jackson and Hipp, not about the telephone conversation that
occurred the day after the meeting. The McBrides also claim that the
recorded conversation was not admissible evidence, because it was not
20 considered a “present sense impression” since Jackson’s statements about
recollections of impressions made the day prior do not qualify. In addition,
the McBrides assert that they were not treated with fundamental fairness,
because they did not have the right to cross-examine the deceased Mr.
Jackson as a witness, even though Lara was able to cross-examine Mr.
McBride.
Lara points out that the recording of Jackson’s statements describing
the inspection and his conversation with Mr. McBride at their meeting is
trustworthy, as it is an accurate and very clear recording that was
authenticated by Lara at trial. Further, because Jackson had passed away
prior to trial, there was no way for Lara to adduce other admissible evidence
other than to cross-examine Mr. McBride and question Hipp at trial, as was
done. The McBrides also acknowledged that they received prior notice of
the recording long before the trial.
Lara argues that the content of the recording was admissible solely to
impeach Mr. McBride’s testimony regarding the conversation he had with
Jackson, which had been allowed over Lara’s objection, because Mr.
McBride’s version of what Jackson said during the inspection differed so
greatly from what Jackson relayed to Mr. Lara in their telephone
conversation. Lara claims the evidence did not constitute hearsay because it
was not offered to prove the truth of the matter asserted but to disprove Mr.
McBride’s testimony. La. C.E. art. 801(C).
The trial court is granted broad discretion in its evidentiary rulings,
which will not be disturbed on appeal absent a clear abuse of discretion.
Succession of Moore, 54,338 (La. App. 2 Cir. 5/19/22), 339 So. 3d 12, writ
21 denied, 22-00973 (La. 10/4/22), 347 So. 3d 859; State v. Smith, 54,489 (La.
App. 2 Cir. 6/29/22), 342 So. 3d 1108; Fields v. Walpole Tire Serv., LLC,
45,206 (La. App. 2 Cir. 5/19/10), 37 So. 3d 549, writ denied, 10-1430 (La.
10/1/10), 45 So. 3d 1097. Evidentiary rulings are subject to review for
abuse of discretion. State v. Willis, 55,165 (La. App. 2 Cir. 6/28/23), 367
So. 3d 948.
At trial, a party must make a timely objection to evidence that party
considers to be inadmissible and must state the specific ground for the
objection. La. C.E. art. 103(A)(1); La. C.C.P. art. 1635; Smith, supra. On
appeal, this court must consider whether the complained of ruling was
erroneous and whether the error affected a substantial right of the party.
Smith, supra; Fields, supra. The determination is whether the error, when
compared to the record in its entirety, has a substantial effect on the outcome
of the case, and it is the complainant’s burden to prove. Smith, supra. If
there is no substantial effect on the outcome, then a reversal is not
warranted. Id.; Fields, supra; Crisler v. Paige One, Inc., 42,563 (La. App. 2
Cir. 1/9/08), 974 So. 2d 125.
Hearsay is an oral or written assertion, other than one made by the
declarant while testifying at the present trial, ordered in evidence to prove
the truth of the matter asserted. La. C.E. art. 801(A)(1) and 801(C); Smith,
supra. Generally, an out-of-court statement is inadmissible as hearsay.
Smith, supra; State v. Cousin, 96-2976 (La. 4/14/98), 710 So. 2d 1065.
Hearsay evidence is inadmissible except as specified in the Louisiana Code
of Evidence or other legislation. La. C.E. art. 802; Smith, supra.
22 Hearsay evidence can be used as impeachment evidence. La. C.E. art.
607(D) states in pertinent part:
D. Attacking credibility extrinsically. Except as otherwise provided by legislation:
(1) Extrinsic evidence to show a witness’ bias, interest, corruption, or defect of capacity is admissible to attack the credibility of the witness.
(2) Other extrinsic evidence, including prior inconsistent statements and evidence contradicting the witness’ testimony, is admissible when offered solely to attack the credibility of a witness unless the court determines that the probative value of the evidence on the issue of credibility is substantially outweighed by the risks of undue consumption of time, confusion of the issues, or unfair prejudice.
The Louisiana Supreme Court has recognized that La. C.E. art. 607(D)(2)
permits the introduction of a prior inconsistent statement or evidence
otherwise contradicting a witness’ testimony, even though it is inadmissible
hearsay, for the limited purpose of attacking the credibility of the witness.
Smith, supra; Cousin, supra. The admissibility of extrinsic evidence to
impeach the credibility of a witness, however, is subject to the relevancy
balancing test of La. C.E. art. 607(D)(2), which requires the court to
determine whether the probative value of the evidence on the issue of
credibility is substantially outweighed by the risk of undue consumption of
time, confusion of the issues, or unfair prejudice. Smith, supra; State v.
Juniors, 03-2425 (La. 6/29/05), 915 So. 2d 291; Cousin, supra.
The McBrides appear to argue that the phone call between Jackson
and Lara was not “evidence contradicting the witness’ testimony” per La.
C.E. art. 607(D)(2), because Mr. McBride testified about the statements
made to him by Jackson during their meeting, not about anything discussed
between Jackson and Mr. Lara during their phone conversation. The trial
23 court admitted the entire phone call as extrinsic evidence to contradict Mr.
McBride’s testimony, an allowed exception per La. C.E. art. 607(D)(2). The
call included, among other discussions, Jackson’s statements to Mr. Lara
about what Jackson had told Mr. McBride during their meeting the previous
day. It is unclear what portions of the phone call the trial court did or did
not consider, but the court referenced its ability to distinguish what was
relevant.
Mr. McBride testified as to what Jackson said to him during their
meeting regarding various issues with the project. The phone call, at least
portions thereof, concerned the same content – what Jackson said to
McBride during their meeting. It was reasonable to determine that the
content of the phone call contradicted the content of Mr. McBride’s earlier
testimony; thus, it was within the trial court’s discretion to admit the phone
call as impeachment evidence.
Lara’s Qualification as an Expert
The McBrides claim that Mr. Lara should not have been allowed as an
expert witness because he lacked basic qualification. They also claim that
the record in this case alone – the shoddy construction and failures to follow
plans and specifications – showed that Mr. Lara lacked credibility as an
expert. They claim that his skill is highly in question, his experience could
not be objectively established, and he did not establish how he had any
special knowledge.
The McBrides further argue that Mr. Lara should not have been
allowed as an expert due to bias, because having the self-interest of a party
in the matter casts doubt on the ability of Mr. Lara to be able to assist the
24 court with an opinion. They refer to this Court’s decision in Dartlone v. La.
Power & Light Co., 33,597 (La. App. 2 Cir. 6/21/00), 763 So. 2d 779, 787,
as well as the Fourth Circuit’s decision in Safeguard Storage v. Donahue
Favret Construction, 09-0344 (La. App. 4 Cir. 5/27/09), 13 So. 3d 244, 246,
writ denied, 09-1413 (La. 9/16/09), 17 So. 3d 382, which reference that “an
expert is not a party.”
The facts and holding in Dartlone, supra, are not comparable to this
case. The City of Monroe retained Brooks, an electrical engineer who had
previously been retained as an expert in electrical engineering and safety by
a separate defendant who was later released from the suit. The trial court
reversed its original decision that there had been no conflict from Brooks’
prior association from the released defendant. Id. This Court reversed that
holding, explaining that the fact that Brooks had been an expert for the
released defendant did not equate to his being a representative of that party,
and there is no presumption that an expert is adverse or hostile to anyone.
Id. This Court did not hold that a party could not also be considered an
expert. The Fourth Circuit in Safeguard Storage, supra, clarified that the
Dartlone, supra, holding represented that, once a party has declined the
future services of an expert, another party involved in the litigation is free to
retain him for consultation.
Mr. Lara testified as to his knowledge, skill, experience, training, and
education, and was approved by the trial court as an expert in construction.
La. C.E. art. 702(A) provides:
A. A witness who is qualified as an expert by knowledge, skill, experience, training, or education may testify in the form of an opinion or otherwise if the proponent demonstrates to the court that it is more likely than not that:
25 (1) The expert’s scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact in issue;
(2) The testimony is based on sufficient facts or data;
(3) The testimony is the product of reliable principles and methods; and
(4) The expert’s opinion reflects a reliable application of the principles and methods to the facts of the case.
Case law supports that a party can act as an expert witness. The fact that a
witness is a party, or an employee of a party, does not preclude his
qualification as an expert, because the potential bias of the witness may be
explored on cross-examination. O’Brien v. Remington Arms Co., 601 So. 2d
330, 336 (La. App. 2 Cir. 1992), writ denied, 604 So. 2d 1003 (La. 1992);
Harrington v. Velinsky, 567 So. 148 (La. App. 2 Cir. 1990); Ealy v. Bill
Allen Dodge, Inc., 466 So. 2d 52 (La. App. 2 Cir. 1985).
Damage Amounts
The McBrides claim that “damages are owed due to nonperformance
or delayed performance in the context of home construction,” citing Thomas
v. Housing La. Now. L.L.C., 24-0063 (La. 3/21/25), 403 So. 3d 570. They
claim that they are not required to prove the exact cost of repairs in order to
recover, citing the holdings in Spurrell v. Ivey, 25,359 (La. App. 2 Cir.
1/25/94), 630 So. 2d 1378, and Greene v. Fox Crossing, Inc., 32,774 (La.
App. 2 Cir. 3/1/00), 754 So. 2d 339, 344, writ denied, 00-0944 (La. 5/26/00),
762 So. 2d 1108, that “when damages are insusceptible of precise
measurement, much discretion is left to the trial court for the reasonable
assessment of these damages.” However, the McBrides make a seemingly
26 contradictory claim that the trial court “not only abused its discretion, but it
was legal error to treat this case like a tort and just throw numbers out and
then change those numbers arbitrarily.”
Both the McBrides and Lara refer to this Court’s holding in Mount
Mariah Baptist Church, Inc. v. Panell’s Associated Electric, Inc., 36,361
(La. App. 2 Cir. 12/20/02), 835 So. 2d 880, writ denied, 03-0555 (La.
5/2/03), 842 So. 2d 1101, as a basis for their respective arguments regarding
damages. In Mount Mariah, the plaintiff church, Mount Mariah, hired
Pannell’s, a licensed contractor, to renovate their existing building and add a
new building. Due to a dispute regarding who was to pay the architect, the
plans were never completed, and Pannell’s had to consult directly with
church representatives regarding the lack of specificity in the plans.
Numerous oral changes were made by Mount Mariah without paying for
change orders, which were implemented by a third-party unlicensed
contractor without consultation with Pannell’s. Mount Mariah presented
Pannell’s with bills for the changes that had been made that were neither
included in the plans nor approved by Pannell’s, which Pannell’s would not
agree to pay. At that point, Mount Mariah ordered Pannell’s off the job.
Mount Mariah filed suit against Pannell’s for breach of contract,
claiming that it had failed to complete the renovation and construction in
accordance with the design and specifications, failed to pay invoices, and
departed from design for the work resulting in extensive additional work to
meet fire code regulations. The trial court ultimately found that Mount
Mariah was entitled to damages for several deficiencies in materials and
construction, which were itemized by the court, reimbursement for several
27 liens against the property, a credit for the cost of a metal roof included in the
specifications, and a credit to complete the project. The trial court awarded
damages to Mount Mariah of $183,823.04, noting that the project cost more
than anticipated, the church was not satisfied with the quality of the work,
and some of the labor and materials were not paid for by Pannell’s. The
court also found that Pannell’s was entitled to an offset of $35,203.00,
resulting in a net judgment to Mount Mariah of $148,620.04.
This Court held in Mount Mariah, supra, among other things, that (1)
the evidence supported the finding that the contractor breached the contract
and was liable for damages; (2) the trial court acted within its discretion in
awarding $42,500 for repairs stemming from poor workmanship, $33,000
for the cost of completing the construction, and $14,300 for the difference
between the metal roof envisioned in the plans and the cheaper asphalt roof
actually installed; and (3) the trial court abused its discretion in awarding
damages for design-related defects. The damages awarded to Mount Mariah
were reduced by $20,000 from a duplicate award for finish problems such as
drywall and trim, and another $6,000 for repair of the porte cocheres,
because there was nothing in the record to show that the roof sagging was
the result of poor workmanship. Id.
La. C.C. art. 2769 provides:
If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract.
Id. A contractor is liable for damages if it is shown that he did not possess
the necessary skill, efficiency or knowledge, or did not exercise ordinary
care in performing work and is liable for losses, which the owner suffered
28 because of the contractor’s non-compliance with the contract. Id. An owner
seeking to recover from a contractor bears the burden of proving: (1) both
the existence and nature of the defects; (2) that the defects were due to faulty
materials or workmanship; and (3) the cost of repairing the defects. Id.
Under Louisiana law, a building contractor is entitled to recover the
contract price even though defects and omissions are present when he has
substantially performed the building contract. Id. “Substantial
performance” means that the construction is fit for the purposes intended
despite the deficiencies; this is a question of fact for the trial judge. Id. at
888, citing Mayeaux v. McInnis, 00-1540 (La. App. 1 Cir. 9/28/01), 809 So.
2d 310, writ denied, 01-3286 (La. 3/8/02), 810 So. 2d 1164. Factors to be
considered in concluding a contractor has provided substantial performance
include the extent of any defect or nonperformance, the degree to which any
such nonperformance has defeated the purpose of the contract, the ease of
correction, and the use or benefit to the owner of the work already
performed. Mount Mariah, supra.
A factfinder is free to accept or reject the conclusions of an expert
witness. State v. D.D., 18-0891 (La. App. 4 Cir. 12/27/19), 288 So. 3d 808,
writ denied, 20-00158 (La. 5/26/20), 296 So. 3d 1063. The trier of fact
should evaluate the expert testimony by the same rules which are applicable
to other witnesses and the trial court is not bound by expert testimony.
Kennedy v. Thomas, 34,530 (La. App. 2 Cir. 4/4/01), 784 So. 2d 692.
Where factual findings are pertinent to the interpretation of a contract,
those factual findings are subject to the manifest error standard of review.
Id. The trial court’s findings of fact are entitled to great discretion. Rosell v.
29 Esco, 549 So. 2d 840 (La. 1989); Spurrell, supra. Where there are two
permissible views of the evidence, the factfinder’s choice between them
cannot be manifestly erroneous or plainly wrong. Arceneaux v. Domingue,
365 So. 2d 1330 (La. 1978); Spurrell, supra. The trial court’s discretion is
premised largely on its ability to see and hear the witnesses and to make
credibility determinations. Canter v. Koehring Co., 283 So. 2d 716 (La.
1973); Spurrell, supra. However, the manifest error rule applies both to
testimonial and documentary evidence. Virgil v. American Guarantee &
Liab. Ins. Co., 507 So. 2d 825 (La. 1987); Spurrell, supra. Under this
standard, when reviewing a trial court’s findings of fact, the role of the Court
of Appeal is not to determine whether the lower court was right or wrong but
instead whether its conclusions were reasonable. Stobart v. State DOTD,
617 So. 2d 880 (La. 1993); Lang v. Sproull, 45,208 (La. App. 2 Cir.
4/28/10), 36 So. 3d 407. Reasonable evaluations of credibility and
inferences of fact should not be disturbed on review where there is
conflicting testimony. Spurrell, supra.
The standard for reviewing the award of damages for breach of
contract is whether the trial court abused its discretion. Id.; Storey v.
Weaver, 49,027 (La. App. 2 Cir. 5/14/14), 139 So. 3d 1079. La. C.C. art.
1999 provides:
When damages are insusceptible of precise measurement, much discretion shall be left to the court for the reasonable assessment of these damages.
An appellate court should rarely disturb an award for general damages. Hae
Woo Youn v. Maritime Overseas Corp., 623 So. 2d 1257 (La. 1993);
Spurrell, supra. Only if an award is first found to be inadequate or
30 excessive on the facts of the particular case may the appellate court refer to
the awards in “similar” cases. Reck v. Stevens, 373 So. 2d 498 (La. 1979);
Spurrell, supra.
Lara asserts that, although it didn’t appeal due to the standard of
review, that it disagrees with the court’s finding that the McBrides carried
their burden of proof to satisfy any damage award as set forth in Mount
Mariah, supra, as well as in Lang, supra. Lara further claims that it
substantially performed the contract up to the point of termination and is
entitled to the unpaid invoices.
The court ultimately awarded damages to the McBrides for the
following: $1,500 for the stone veneer repair; $12,500 for the front
elevation/dormer damage; $400 for window sash replacement; $2,500 for
drywall in the laundry room and dining room; and $5,000 for installing the
incorrect roof decking. It awarded an amount of $9,740 to Lara for unpaid
invoices. There was little dispute that there were at least some disrepairs for
the stone veneer and windows, there had been leaks at some point requiring
eventual repair to the laundry room/dining room drywall, and the roof
decking installed was not what was stated in the specifications. Lara claims
it already repaired the issues with the front elevation and dormer, though the
McBrides still claim it was not constructed according to the plans.
The court assessed the credibility of all the witnesses, lay and expert,
drawing inferences from their testimony, and made a reasonable factual
determination that there were numerous errors in the construction,
specifically those items for which damages were assessed. However, it also
found that it “has not been able to determine the alleged damages as set forth
31 by the Plaintiffs,” presumably as to the repairs they allege were made, since
no invoices were submitted to substantiate those amounts.
The court heard testimony from Mr. McBride regarding the
McBrides’ claims of multiple problems during the construction process and
the amounts they paid for alleged necessary, but no invoices or receipts were
submitted to support those claims. The McBrides also had Burroughs testify
on their behalf, who had inspected the home and provided a report regarding
certain deficiencies. Burroughs opined that the costs to correct the defects
noted in his report and to replace materials with those included in the
specifications would be approximately $350,000, essentially what it cost to
originally build the entire home. Burroughs was not a construction expert
qualified to provide opinions on what should be done to correct any alleged
defects. He was only able to opine on what it would cost if it were necessary
to make certain repairs or replacements, which was unsupported by any
other testimony or evidence and strongly contradicted by other testimony
and evidence in the record. The notion that a roof should be completely
replaced simply because the decking size differed from specifications was
neither supported by the record nor by case law, given this Court in Mount
Mariah, supra, upheld simply a credit for the difference between the cost of
a metal roof that had been specified and an asphalt shingled roof that was
applied.
Mr. Lara was qualified as a construction expert and explained all
alleged defects and the appropriate remedies. He also testified on his own
behalf, repeatedly asserting that he would have completed the job
satisfactorily had he not been prematurely removed from the project, and
32 most of the alleged defects were simply “punch list items” that would have
been completed at the end of the project. Lara provided other witnesses
such as their project manager, bookkeeper, the architect, the window
representative, and the bank representative, as well as evidence impeaching
testimony attempting to corroborate the McBrides’ claim that a third-party
contractor was in agreement with their claims.
The trial court acted well within its discretion in finding that only the
defects stated in the judgment warranted an award of damages. Further, it
did not abuse its discretion in awarding the respective damage amounts. The
trial court acted within its discretion and made a reasonable assessment of
damages in light of the scarcity of invoices and receipts and the fact that
there were only vague references throughout the record as to what it may
cost to repair the defects it found to have existed.
CONCLUSION
For the foregoing reasons, we AFFIRM the trial court’s judgment.
All costs of this proceeding are to be assessed to the McBrides.
AFFIRMED.