Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC

CourtLouisiana Court of Appeal
DecidedOctober 22, 2025
Docket56,440-CA
StatusPublished

This text of Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC (Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC, (La. Ct. App. 2025).

Opinion

Judgment rendered October 22, 2025. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 56,440-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

ANDREW MCBRIDE AND Plaintiffs-Appellants GINGER MCBRIDE

versus

RAFAEL LARA Defendant-Appellee CONSTRUCTION, LLC

Appealed from the Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 20192395

Honorable Jefferson Bryan Joyce, Judge

TYLER GRAHAM STORMS Counsel for Appellants

DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: Martin Shane Craighead

Before STONE, ROBINSON, and HUNTER, JJ. ROBINSON, J.

Plaintiffs, Andrew and Ginger McBride (collectively, “Plaintiffs” or

“the McBrides”), filed suit in Ouachita Parish against Defendant, Rafael

Lara Construction, LLC (“Defendant” or “Lara”), for breach of a

construction contract entered into between the parties for various alleged

deficiencies in the construction of their home. Lara filed a reconventional

demand for the balance owed on the contract as of the date he was

terminated. Trial was held on February 26, 2024. The trial court issued a

judgment and written reasons for judgment on May 8, 2024, awarding the

McBrides a total of $35,400, offset by an award to Lara of $13,540 for its

reconventional demand, for a net award to the McBrides of $21,860. Both

parties filed motions for new trial. After a hearing on the motions, the trial

court issued its second judgment and written reasons for judgment on

October 24, 2024, reducing its total award to the McBrides by $13,500 and

Lara’s award by $3,800, for a net award to the McBrides of $12,160. The

McBrides filed a devolutive appeal.

For the following reasons, we AFFIRM the trial court’s judgment.

FACTS AND PROCEDURAL HISTORY

The McBrides and Lara entered into a contract for the construction of

the McBrides’ home on August 22, 2018. Plans and specifications had been

prepared by an architect, Allan Pogue (“Pogue”), in the summer of 2018 and

were incorporated into the contract. Construction of the home commenced

with the pouring of the foundation in early October 2018.

The McBrides complained of several deficiencies in the construction

of their home and ultimately terminated Lara. The McBrides paid third parties to complete the home after Lara’s termination. They claim they

spent approximately $45,000 over the maximum contract amount and

provided receipts therefor, although Lara claims that the McBrides

overstated the amount by approximately $25,000. Although there were

copies of estimates for certain repair work in the record, there were no

itemized receipts showing what was actually spent by the McBrides

following Lara’s termination.

Alleged Construction Defects

The McBrides first complained of construction defects when there

was exposed rebar in the foundation as well as wood forms that remained

embedded. Shortly after, during the framing process, the wall between the

garage and kitchen misaligned with the anchor bolts in the foundation. The

McBrides claim they did not terminate Lara at that time because they were

assured the wall could be pushed in, and they did not realize that the

embedded forms resulted in a likelihood of termite intrusion, rot, and

honeycombing of the slab. However, Chad Parker (“Parker”), of Inspections

Unlimited, testified that the open wall with exposed anchor bolts passed

inspection.

Rafael Lara (“Mr. Lara”) testified that conflicts with the McBrides

began when Lara used the Weyerhaeuser Gold brand of floor decking rather

than the Advantech brand orally requested by the McBrides. Mr. Lara

explained that he had intended to use Advantech, but that it was not in stock

at that time. Mr. Lara agreed to double the decking used with no charge in

order to satisfy the McBrides, and the McBrides stated that they accepted the

2 remedy because the contract specifications did not require the Advantech

product.

The roof was installed on the house in December 2018. Mr. Lara

testified that he chose to roof the house earlier than usual due to the

excessive amount of rain there had been during the project. He stated that he

was aware that there would be some damage to shingles from installing the

brick and siding after the shingles were in place, but he wanted the house to

be sealed as much as possible so that issues with water intrusion would be

minimized. Lara used 7/16” OSB (oriented strand board) roof decking,

while the specifications listed 5/8” foil-backed decking with plywood clips.

Lara also used 26-gauge galvanized aluminum flashing for the roof in

locations where there would be brick and 26-gauge powder-coated

aluminum trim coil for the exterior flashing. The specifications listed 26-

gauge galvanized steel for the roof. The McBrides claim that they

specifically requested the 5/8” decking listed in the specifications because it

was a higher quality, stronger material, alleging later that the 7/16” decking

was an inferior product that caused the roof to sag. Mr. Lara testified that he

did not recall any specific direction from the McBrides regarding the

decking. Lara claims that both sizes of decking were code-compliant and

would work the same in this situation, because the product’s thickness

related more to snowpack, which was not applicable in this locale, especially

with the steep pitch of the McBrides’ roof. Pogue testified that the roof

decking on the house was appropriate and consistent with the specifications.

The McBrides also claim that the aluminum flashing used by Lara

was an inferior product and not as durable. Mr. Lara testified that he does

3 not like to use the galvanized sheet metal because it is not aesthetically

pleasing, and he prefers to use aluminum trim coil, because it will not rust

like the steel product, and it is powder coated to match the eaves and soffits

of the house. He noted that the product used was also a 26-gauge metal.

Following installation of the roof, there were leaks in three different

locations: between the garage and house below the laundry room; in front of

the dormer into the office; and over the back side of the garage into the

dining room area. Mr. Lara testified that at the time of the leaks, the

flashing had not yet been installed. Insulation had been sprayed into the

walls, but no sheetrock had been installed. He stated that, upon discovery of

the roof leaks, Lara removed the insulation to ensure there were no leaks

behind the wall. Once flashing was installed, Mr. Lara soaked all the

flashing with a pressure nozzle hose to check for leaks, which he videoed

and sent to the McBrides. At some point during this process, Mr. McBride

claimed that the walls were still leaking. Mr. Lara testified that he inspected

the walls by physically putting his hands between the walls and the delta

straw (plastic sheeting at the bottom of the house), applying paper towels to

the foam boards between the studs, and cutting holes in the upstairs

sheetrock, none of which indicated any moisture. Dakota Breshears

(“Breshears”), who was Lara’s project manager during the time of the

McBrides’ project, testified that a moisture meter was used on the entire wall

where there had been a leak, and the studs were checked top to bottom. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
Virgil v. American Guar. & Liability Ins.
507 So. 2d 825 (Supreme Court of Louisiana, 1987)
Spurrell v. Ivey
630 So. 2d 1378 (Louisiana Court of Appeal, 1994)
Greene v. Fox Crossing, Inc.
754 So. 2d 339 (Louisiana Court of Appeal, 2000)
Ealy v. Bill Allen Dodge, Inc.
466 So. 2d 52 (Louisiana Court of Appeal, 1985)
Youn v. Maritime Overseas Corp.
623 So. 2d 1257 (Supreme Court of Louisiana, 1993)
Safeguard Storage Properties, LLC v. Donahue Favret Contractors, Inc.
13 So. 3d 244 (Louisiana Court of Appeal, 2009)
Dartlone v. Louisiana Power & Light Co.
763 So. 2d 779 (Louisiana Court of Appeal, 2000)
State v. Juniors
915 So. 2d 291 (Supreme Court of Louisiana, 2005)
Arceneaux v. Domingue
365 So. 2d 1330 (Supreme Court of Louisiana, 1978)
O'BRIEN v. Remington Arms Co., Inc.
601 So. 2d 330 (Louisiana Court of Appeal, 1992)
Crisler v. Paige One, Inc.
974 So. 2d 125 (Louisiana Court of Appeal, 2008)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Mayeaux v. McInnis
809 So. 2d 310 (Louisiana Court of Appeal, 2001)
State v. Cousin
710 So. 2d 1065 (Supreme Court of Louisiana, 1998)
Canter v. Koehring Company
283 So. 2d 716 (Supreme Court of Louisiana, 1973)
Kennedy v. Thomas
784 So. 2d 692 (Louisiana Court of Appeal, 2001)
Reck v. Stevens
373 So. 2d 498 (Supreme Court of Louisiana, 1979)
Lang v. Sproull
36 So. 3d 407 (Louisiana Court of Appeal, 2010)
Storey v. Weaver
139 So. 3d 1079 (Louisiana Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrew-mcbride-and-ginger-mcbride-v-rafael-lara-construction-llc-lactapp-2025.