Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC

Louisiana Court of Appeal·Decided October 22, 2025·No. 56,440-CA·Published

Opinion

Judgment rendered October 22, 2025.

Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 56,440-CA

COURT OF APPEAL

SECOND CIRCUIT

STATE OF LOUISIANA

*****

ANDREW MCBRIDE AND Plaintiffs-Appellants GINGER MCBRIDE

versus

RAFAEL LARA Defendant-Appellee CONSTRUCTION, LLC

*****

Appealed from the

Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 20192395

Honorable Jefferson Bryan Joyce, Judge

*****

TYLER GRAHAM STORMS Counsel for Appellants

DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: Martin Shane Craighead

*****

Before STONE, ROBINSON, and HUNTER, JJ.

ROBINSON, J.

Plaintiffs, Andrew and Ginger McBride (collectively, “Plaintiffs” or “the McBrides”), filed suit in Ouachita Parish against Defendant, Rafael Lara Construction, LLC (“Defendant” or “Lara”), for breach of a construction contract entered into between the parties for various alleged deficiencies in the construction of their home. Lara filed a reconventional demand for the balance owed on the contract as of the date he was terminated. Trial was held on February 26, 2024. The trial court issued a judgment and written reasons for judgment on May 8, 2024, awarding the McBrides a total of $35,400, offset by an award to Lara of $13,540 for its reconventional demand, for a net award to the McBrides of $21,860. Both parties filed motions for new trial. After a hearing on the motions, the trial court issued its second judgment and written reasons for judgment on October 24, 2024, reducing its total award to the McBrides by $13,500 and Lara’s award by $3,800, for a net award to the McBrides of $12,160. The McBrides filed a devolutive appeal.

For the following reasons, we AFFIRM the trial court’s judgment.

FACTS AND PROCEDURAL HISTORY The McBrides and Lara entered into a contract for the construction of the McBrides’ home on August 22, 2018. Plans and specifications had been prepared by an architect, Allan Pogue (“Pogue”), in the summer of 2018 and were incorporated into the contract. Construction of the home commenced with the pouring of the foundation in early October 2018.

The McBrides complained of several deficiencies in the construction of their home and ultimately terminated Lara. The McBrides paid third

parties to complete the home after Lara’s termination. They claim they spent approximately $45,000 over the maximum contract amount and provided receipts therefor, although Lara claims that the McBrides overstated the amount by approximately $25,000. Although there were copies of estimates for certain repair work in the record, there were no itemized receipts showing what was actually spent by the McBrides following Lara’s termination. Alleged Construction Defects The McBrides first complained of construction defects when there was exposed rebar in the foundation as well as wood forms that remained embedded. Shortly after, during the framing process, the wall between the garage and kitchen misaligned with the anchor bolts in the foundation. The McBrides claim they did not terminate Lara at that time because they were assured the wall could be pushed in, and they did not realize that the embedded forms resulted in a likelihood of termite intrusion, rot, and honeycombing of the slab. However, Chad Parker (“Parker”), of Inspections Unlimited, testified that the open wall with exposed anchor bolts passed inspection.

Rafael Lara (“Mr. Lara”) testified that conflicts with the McBrides began when Lara used the Weyerhaeuser Gold brand of floor decking rather than the Advantech brand orally requested by the McBrides. Mr. Lara explained that he had intended to use Advantech, but that it was not in stock at that time. Mr. Lara agreed to double the decking used with no charge in order to satisfy the McBrides, and the McBrides stated that they accepted the

remedy because the contract specifications did not require the Advantech product.

The roof was installed on the house in December 2018. Mr. Lara testified that he chose to roof the house earlier than usual due to the excessive amount of rain there had been during the project. He stated that he was aware that there would be some damage to shingles from installing the brick and siding after the shingles were in place, but he wanted the house to be sealed as much as possible so that issues with water intrusion would be minimized. Lara used 7/16” OSB (oriented strand board) roof decking, while the specifications listed 5/8” foil-backed decking with plywood clips. Lara also used 26-gauge galvanized aluminum flashing for the roof in locations where there would be brick and 26-gauge powder-coated aluminum trim coil for the exterior flashing. The specifications listed 26- gauge galvanized steel for the roof. The McBrides claim that they specifically requested the 5/8” decking listed in the specifications because it was a higher quality, stronger material, alleging later that the 7/16” decking was an inferior product that caused the roof to sag. Mr. Lara testified that he did not recall any specific direction from the McBrides regarding the decking. Lara claims that both sizes of decking were code-compliant and would work the same in this situation, because the product’s thickness related more to snowpack, which was not applicable in this locale, especially with the steep pitch of the McBrides’ roof. Pogue testified that the roof decking on the house was appropriate and consistent with the specifications.

The McBrides also claim that the aluminum flashing used by Lara was an inferior product and not as durable. Mr. Lara testified that he does

not like to use the galvanized sheet metal because it is not aesthetically pleasing, and he prefers to use aluminum trim coil, because it will not rust like the steel product, and it is powder coated to match the eaves and soffits of the house. He noted that the product used was also a 26-gauge metal.

Following installation of the roof, there were leaks in three different locations: between the garage and house below the laundry room; in front of the dormer into the office; and over the back side of the garage into the dining room area. Mr. Lara testified that at the time of the leaks, the flashing had not yet been installed. Insulation had been sprayed into the walls, but no sheetrock had been installed. He stated that, upon discovery of the roof leaks, Lara removed the insulation to ensure there were no leaks behind the wall. Once flashing was installed, Mr. Lara soaked all the flashing with a pressure nozzle hose to check for leaks, which he videoed and sent to the McBrides. At some point during this process, Mr. McBride claimed that the walls were still leaking. Mr. Lara testified that he inspected the walls by physically putting his hands between the walls and the delta straw (plastic sheeting at the bottom of the house), applying paper towels to the foam boards between the studs, and cutting holes in the upstairs sheetrock, none of which indicated any moisture. Dakota Breshears (“Breshears”), who was Lara’s project manager during the time of the McBrides’ project, testified that a moisture meter was used on the entire wall where there had been a leak, and the studs were checked top to bottom. Mr. Lara determined that the leaks in the garage/dining room area were due to some holes in the shingles made from attaching the toeboards to the roof during the vinyl installation. He stated that the holes were sealed, with the

intention to later replace the shingles, which stopped the leaks. Mr. Lara also determined that the leak in the office area was from the off-centered dormer. Lara adjusted the framing to center it up better.

Free access — add to your briefcase to read the full text and ask questions with AI

Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC, (La. Ct. App. 2025).

Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC (Andrew McBride and Ginger McBride v. Rafael Lara Construction, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
Virgil v. American Guar. & Liability Ins.
507 So. 2d 825 (Supreme Court of Louisiana, 1987)
Spurrell v. Ivey
630 So. 2d 1378 (Louisiana Court of Appeal, 1994)
Greene v. Fox Crossing, Inc.
754 So. 2d 339 (Louisiana Court of Appeal, 2000)
Ealy v. Bill Allen Dodge, Inc.
466 So. 2d 52 (Louisiana Court of Appeal, 1985)
Youn v. Maritime Overseas Corp.
623 So. 2d 1257 (Supreme Court of Louisiana, 1993)
Safeguard Storage Properties, LLC v. Donahue Favret Contractors, Inc.
13 So. 3d 244 (Louisiana Court of Appeal, 2009)
Dartlone v. Louisiana Power & Light Co.
763 So. 2d 779 (Louisiana Court of Appeal, 2000)
State v. Juniors
915 So. 2d 291 (Supreme Court of Louisiana, 2005)
Arceneaux v. Domingue
365 So. 2d 1330 (Supreme Court of Louisiana, 1978)
O'BRIEN v. Remington Arms Co., Inc.
601 So. 2d 330 (Louisiana Court of Appeal, 1992)
Crisler v. Paige One, Inc.
974 So. 2d 125 (Louisiana Court of Appeal, 2008)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Mayeaux v. McInnis
809 So. 2d 310 (Louisiana Court of Appeal, 2001)
State v. Cousin
710 So. 2d 1065 (Supreme Court of Louisiana, 1998)
Canter v. Koehring Company
283 So. 2d 716 (Supreme Court of Louisiana, 1973)
Kennedy v. Thomas
784 So. 2d 692 (Louisiana Court of Appeal, 2001)
Reck v. Stevens
373 So. 2d 498 (Supreme Court of Louisiana, 1979)
Lang v. Sproull
36 So. 3d 407 (Louisiana Court of Appeal, 2010)
Storey v. Weaver
139 So. 3d 1079 (Louisiana Court of Appeal, 2014)