Trahan v. Broussard

399 So. 2d 782
CourtLouisiana Court of Appeal
DecidedMay 27, 1981
Docket8234
StatusPublished
Cited by10 cases

This text of 399 So. 2d 782 (Trahan v. Broussard) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trahan v. Broussard, 399 So. 2d 782 (La. Ct. App. 1981).

Opinion

399 So.2d 782 (1981)

Richard Dale TRAHAN, Plaintiff-Appellee,
v.
Harold L. BROUSSARD et al., Defendants-Appellants.

No. 8234.

Court of Appeal of Louisiana, Third Circuit.

May 27, 1981.

*783 Darrell J. Hartman, Kaplan, for defendants-appellants.

Cooper & Sonnier, John Ortego, Abbeville, for plaintiff-appellee.

Before GUIDRY, FORET and CUTRER, JJ.

FORET, Judge.

Richard Dale Trahan (Plaintiff) brought this action for breach of a building contract or, in the alternative, redhibition against Harold L. Broussard d/b/a H. L. Broussard Builders (Defendant), to recover damages for the alleged faulty construction of a pool house and game room.

The trial court rendered judgment in favor of plaintiff and defendant appealed. Defendant presents two issues:

(1) Whether the trial court committed manifest error in finding defendant liable to plaintiff;

(2) Whether the trial court used the proper measure in determining the amount of damages it awarded plaintiff.

FACTS

Plaintiff and defendant entered into an oral contract whereby defendant agreed to construct an addition to plaintiff's home, consisting of a pool room and a game room on a cost-plus basis. The final price for the addition was approximately $18,700.00 and construction was completed around the end of October, 1977.

Plaintiff first began to notice deficiencies in the structure in August, 1978, which grew worse with the passage of time. The building is now in such condition that it is unsafe to use and would probably collapse but for the extraordinary measures taken by plaintiff.

Plaintiff instituted this action on July 27, 1979, alleging that defendant (who was the general contractor for the project) had breached the implied warranty of fitness in the building contract, and his duty to perform in a workmanlike manner. Plaintiff further alleged, in the alternative, that he had purchased the addition or the services provided by defendant in constructing the addition and that certain defects in the building rendered it unfit for the purposes for which it had been constructed (i. e., redhibition).

The trial court rendered judgment against the defendant and awarded plaintiff the sum of $29,385.35 in damages. Defendant was granted a devolutive appeal.

DEFENDANT'S LIABILITY

Plaintiff asserted two causes of action against the defendant in the court below. The first was that there existed a construction contract between the parties which was breached when defendant failed to perform properly under it. Plaintiff's second cause of action, plead in the alternative, was that a contract of sale existed between the parties which was breached when the defendant delivered a construction which was so defective that it was unfit for the purposes it was intended to serve, i. e., redhibition.

We must first determine whether the contract is a construction contract or a contract of sale. In Duhon v. Three Friends Home Builders Corporation, 396 So.2d 559 (La.App. 3 Cir. 1981), we had occasion to resolve an identical issue. Plaintiffs there brought an action in redhibition seeking to recover for an allegedly defective house built for them by defendant. Plaintiffs had negotiated with defendant to build the house and choose the floor plan and color scheme they desired. Defendant then constructed the house and it was moved onto plaintiffs' lot. Thereafter, plaintiffs noticed several major defects in the house. Defendant was unsuccessful in its attempts to repair the house, and plaintiff's brought suit, demanding a rescission of the sale or in the alternative, a reduction in price, plus attorney's fees.

Defendant filed a motion for summary judgment contending that the contract entered into between the parties was a contract to build and, therefore, plaintiffs could not recover in redhibition. Plaintiffs, *784 on the other hand, contended that the contract was a contract to sell a future thing, the sale becoming effective on completion of the house.

Duhon set forth three major factors which distinguish a contract to build from a contract of sale. First, in a contract to build, the "buyer" has some control over the specifications of the object. Second, the negotiations in a contract to build take place before the object is constructed. Third, and perhaps most importantly, a building contract contemplates not only that one party will supply the materials, but also that that party will furnish his skill and labor in order to build the desired object.

We find all three factors to be present in the action before us. Here, the contract contemplated the erection by defendant of an addition to plaintiff's home which would enclose a heated swimming pool and provide a game room. Therefore, we find that the contract in question was a construction contract, and thus plaintiff failed to state a cause of action in redhibition, as no contract of sale existed. See Mangin v. Jorgens, 24 So.2d 384 (La.App. Orl. Cir. 1946); Papa v. Louisiana Metal Awning Company, Inc., 131 So.2d 114 (La.App. 2 Cir. 1961); and Henson v. Gonzalez, 326 So.2d 396 (La.App. 1 Cir. 1976).

It is implicit in every construction contract that the work of the builder be performed in a good, workmanlike manner, free from defects in materials or workmanship. Martin v. AAA Brick Company, Inc., 386 So.2d 987 (La.App. 3 Cir. 1980); Neel v. O'Quinn, 313 So.2d 286 (La.App. 3 Cir. 1975), writ denied, 319 So.2d 440 (La.1975); Nichols Ford Company, Inc. v. Hughes, 292 So.2d 345 (La.App. 2 Cir. 1974); Merrydale Glass Works, Inc. v. Merriam, 349 So.2d 1315 (La.App. 1 Cir. 1977), writ denied, 350 So.2d 1211 (La.1977).

There was little dispute as to the present condition of the structure. The evidence shows that the walls of the structure are sagging or bowed to the outside; the roof ridge beam sags down approximately 8½ inches at one point; the roof leaks; the interior and exterior paneling in the bath area of the pool enclosure is warped; the interior and exterior paneling in the pool enclosure itself is warped; and, there are areas of the slab on which the structure was built that have no proper footing. Plaintiff had to stretch a wire rope from wall to wall and then tighten it with turnbuckles to prevent the structure from collapsing. There is also evidence of damage to plaintiff's home, to which the structure is attached.

Plaintiff argues that defendant failed to complete all of the work contracted for; used defective materials for construction; performed the work in an improper and unworkmanlike manner; and, used defective designs in constructing the building.

Plaintiff testified that defendant told him there would be no need to engage the services of an architect to design the building as defendant could take care of any problems which might arise during construction. Defendant's own testimony was to the effect that plaintiff had asked him if he would need an architect to design the building. Defendant testified that he asked plaintiff what he wanted in the building and plaintiff showed him. Defendant testified that he then replied, "What you need an architect for if you're going to show me what you want in the building?" Defendant is the one who designed the building.

David Burdette was accepted by the court as an expert in the field of civil engineering. It was his opinion that the design selected by defendant was defective and that it was inadequate to support the weight of the roof. Burdette stated he would have used a different design.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melancon v. Tri-Dyne Tele-Pier, LLC
95 So. 3d 576 (Louisiana Court of Appeal, 2012)
City of Plaquemine v. N. Amer. Constructors
832 So. 2d 447 (Louisiana Court of Appeal, 2002)
Bourgeois v. Arrow Fence Co., Inc.
592 So. 2d 445 (Louisiana Court of Appeal, 1991)
Larkins v. Cage Contractors, Inc.
580 So. 2d 1068 (Louisiana Court of Appeal, 1991)
Salard v. Jim Walter Homes, Inc.
563 So. 2d 1327 (Louisiana Court of Appeal, 1990)
Ellis Millwork, Inc. v. Frees, Inc.
493 So. 2d 696 (Louisiana Court of Appeal, 1986)
Crescent Coating Co., Inc. v. Berghman
480 So. 2d 1013 (Louisiana Court of Appeal, 1985)
Cell-O-Mar, Inc. v. Gros
479 So. 2d 386 (Louisiana Court of Appeal, 1985)
Fortier v. Sessum
441 So. 2d 1238 (Louisiana Court of Appeal, 1983)
Melder v. Gassiott
436 So. 2d 628 (Louisiana Court of Appeal, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
399 So. 2d 782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trahan-v-broussard-lactapp-1981.