Rice v. Mesa General Contractor, LLC

986 So. 2d 122, 2008 WL 2190803
CourtLouisiana Court of Appeal
DecidedMay 27, 2008
Docket08-CA-115
StatusPublished
Cited by7 cases

This text of 986 So. 2d 122 (Rice v. Mesa General Contractor, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rice v. Mesa General Contractor, LLC, 986 So. 2d 122, 2008 WL 2190803 (La. Ct. App. 2008).

Opinion

986 So.2d 122 (2008)

Carol RICE and Richard D. Rice
v.
MESA GENERAL CONTRACTOR, L.L.C. and Fred L. Mesa.

No. 08-CA-115.

Court of Appeal of Louisiana, Fifth Circuit.

May 27, 2008.

*123 Alan P. Dussouy, Metairie, Louisiana, for Plaintiffs/Appellees.

*124 Richard J. Tomeny, Jr., Metairie, Louisiana, for Defendant/Appellant.

Panel composed of Judges THOMAS F. DALEY, MARION F. EDWARDS, and GREG G. GUIDRY.

THOMAS F. DALEY, Judge.

Appellants, Mesa General Contractors, L.L.C. (Mesa) and Fred Mesa, appeal from a judgment finding that Mesa breached its construction contract with plaintiffs, Carol and Richard Rice (plaintiffs), and awarding damages in the amount of $79,539.08. Plaintiffs hired Mesa to construct an addition to their home over an existing garage. The trial court also rejected a reconventional demand made by Mesa against plaintiffs for the amount of $6,668.34, representing the amount allegedly due Mesa from plaintiffs under the contract. The trial court further declined to find Fred Mesa personally liable under the contract. The trial court awarded the plaintiffs $79,539.08 in damages.

Mesa appeals the trial court's judgment.[1] Mesa argues in brief that the evidence shows that Mesa did fully perform the construction in accordance with its contract, and further, that it was not responsible to supervise the work, as it was not hired as a general contractor. Mesa argues that the trial court erred in holding it liable for the differences in its contract with the owner and the specifications in the plans drawn up by the architectural designer, when those plans were not part of the contract between the owner and Mesa.

Mesa also argues that plaintiffs cannot now complain of different materials being used than the ones specified in the plans, because they were present when the alternate materials were installed/used, and failed to complain at that time, only complaining after the work was completed.

Mesa further argues that plaintiffs did not bear their burden of proof regarding breach of contract, nor the amount of damages. Mesa argues that the trial court erred in allowing into evidence an accounting ledger prepared by plaintiff, when the document was not listed on the pre-trial order, nor produced during discovery.

We affirm the judgment of the trial court that Mesa breached the contract with the plaintiffs, but on a different basis. We further amend the damage award as noted below.

FACTS

In 2003, plaintiffs desired to build a second floor addition on top of their existing garage. They had plans for the addition drawn up by Ronald Authement, an architectural designer and draftsman. He testified that he visited the property several times and drew up a plan, which was then reviewed by a civil engineer to determine structural load requirements, something that Authement was not qualified to do on his own, not being an architect. After the plans were finished, the Rices sought bids from three contractors. They ultimately selected Mesa General Contractor to perform certain items of construction under the plans. The plaintiffs testified that they never met or talked with Mr. Mesa, but dealt with Mr. Alan Thibodeaux, the construction supervisor for Mesa.

Plaintiff, Carol Rice, testified that she gave Authement's plans to Mr. Thibodeaux in order for him to work up the bid. Mesa's contract proposal is dated May 25, 2003 and lists a contract price of $64,875.00 *125 for Mesa's work. The contract states that the job should be complete within 12 weeks. Testimony from Mrs. Rice and Thibodeaux established that work began within two weeks of the contract's execution. Testimony also revealed that the job lasted at least 36 weeks, and that the "punch" list was never finished due to a breakdown of the relationship and this suit being filed. Mrs. Rice testified that Mr. Thibodeaux's last day on the job was February 3, 2004, at which point she felt he had not finished the scope of his contract work.

When Thibodeaux returned the contract, Mrs. Rice admittedly did not check to see if the contract provisions matched the plans, because she "assumed" they did match. It was shown at trial that in several respects, Mr. Thibodeaux's bid proposal contained differences with the plans, most notably changing Authement's specification for the floor joist system, using 2×10 joists instead of 2×12s as called for in the plans. This item, though not pointed out specifically by Thibodeaux, is clearly shown on page one of the contract. The evidence at trial showed that both parties went over the contract prior to signing it. There are several handwritten notations and changes that were made on the contract prior to signing it.

Whereas Mrs. Rice testified she felt Mesa was the "general contractor" on the job, the Mesa contract showed that Mesa did not undertake supervision of the entire job. The scope of Mesa's work was not to bring the project to completion, as the Rices would undertake interior finishing work after Mesa would finish their portion of the job. The plaintiffs secured their own building permit.

Mrs. Rice testified that problems started almost immediately; for instance, the contractor did not remove debris from her yard every day as he had promised, which prevented the plaintiffs' dogs' use of the yard until it was cleared every night.

In particular, plaintiff noted the following items with which she was dissatisfied. The window in the front of the addition was out of square. The floor joists were unevenly spaced, so hanging drywall was very problematic. The back door was not aligned properly, and there was a leak under the plate. Many of the floor joists sagged, as evidenced by photos entered into evidence. Ripped visquene covered the demolished ceiling of the garage and failed to protect areas underneath it from the elements. Hurricane clips (straps) in the roofing were either not used or were underused in areas.

Mrs. Rice noted that the roof of the addition did not tie in well to the existing structure. The plans had the hips and valleys lining up to each other in a parallel fashion. As built, the hips and valleys of the old house and the addition were not parallel to each other, but formed "parallelograms." It was visually displeasing, though Rice admitted the roof did not leak. Mrs. Rice noted that the contract called for the windows to match the existing structure, but the windows that Thibodeaux ordered did not match at all. Thibodeaux admitted that he did not take the time to find matching windows, but tried to blame that delay on Mrs. Rice. Mrs. Rice also noted that the contract called for hand-split cedar shake siding to match the existing house, but a different product was delivered. Mr. Thibodeaux admitted that he probably did not tell his supplier to order the correct item, but again tried to blame the resulting delay on Mrs. Rice. She was additionally unhappy that the weather sheathing underneath the siding was torn in places, which compromised the moisture barrier, and was apparently not corrected before the siding was installed. *126 (Thibodeaux testified that he did not know whether it got corrected.) The siding itself was installed incorrectly and had to be redone.

Other problems included water damage in the main house, along the outside wall and in the master bathroom, guest bedroom, and bath. It was discovered by Ron Daigle, a contractor whom the plaintiffs engaged to fix the floor joist system, that there was no a/c vent in the bathroom, and that there was only one (1) 6 inch a/c vent in the entire upstairs room, which was inadequate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Direct Tech Drilling, LLC v. Danrik Construction, Inc.
235 So. 3d 1173 (Louisiana Court of Appeal, 2017)
Lamar Contractors, Inc. v. Kacco, Inc.
174 So. 3d 82 (Louisiana Court of Appeal, 2015)
Diamond Cabinet Designs, L.L.C. v. Coxie
169 So. 3d 601 (Louisiana Court of Appeal, 2015)
Superior Derrick Svcs, L.L.C. v. Lonestar 203, et
547 F. App'x 432 (Fifth Circuit, 2013)
Henderson v. Ayo
96 So. 3d 641 (Louisiana Court of Appeal, 2012)
Melancon v. Tri-Dyne Tele-Pier, LLC
95 So. 3d 576 (Louisiana Court of Appeal, 2012)
Maxwell v. Cayse
54 So. 3d 118 (Louisiana Court of Appeal, 2010)
Donald Joe Maxwell v. Daniel (Danny") Cayse "
Louisiana Court of Appeal, 2010

Cite This Page — Counsel Stack

Bluebook (online)
986 So. 2d 122, 2008 WL 2190803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rice-v-mesa-general-contractor-llc-lactapp-2008.