McShain v. Indemnity Insurance Co. of North America

12 A.2d 59, 338 Pa. 113, 1940 Pa. LEXIS 469
CourtSupreme Court of Pennsylvania
DecidedJanuary 26, 1940
DocketAppeal, 374
StatusPublished
Cited by16 cases

This text of 12 A.2d 59 (McShain v. Indemnity Insurance Co. of North America) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McShain v. Indemnity Insurance Co. of North America, 12 A.2d 59, 338 Pa. 113, 1940 Pa. LEXIS 469 (Pa. 1940).

Opinion

Opinion by

Mr. Justice Stern,

John McShain, plaintiff, recovered a verdict against Indemnity Insurance Company of North America, defendant, in the sum of $78,182.61, and defendant recovered ¿ verdict over against John F. McCarthy, additional defendant, in the same amount. The court in banc granted motions of defendant and additional defendant for a new trial. From this order plaintiff appeals.

The court below did not abuse its discretion in granting the new trial. On the contrary, to have refused would have been reversible error.

Plaintiff was the general contractor for the erection of the new Naval Hospital in Philadelphia. His contract with the United States government provided that *115 the wage rate for all laborers and mechanics employed by the contractor or any sub-contractor on the building should be not less than the rate prevailing in the locality for work of a similar nature; failure to observe this provision was to give the government the right to terminate the contract, take over the work, and hold the contractor liable for any excess cost thereby occasioned. Plaintiff sub-contracted the electrical work to additional defendant, the contract specifying that it was to be subject to the conditions governing the general contract. Additional defendant gave his bond to plaintiff with defendant as surety in the sum of $132,500, conditioned for the faithful performance of the sub-contract.

After the work had been in progress for some time, plaintiff claimed that additional defendant was violating the wage provision, and that, on the basis of the prevailing rate, there was a large unpaid balance of wages due additional defendant’s workmen; accordingly, plaintiff notified him that the contract was cancelled. Plaintiff then took over and completed the work, and also discharged some unpaid obligations of additional defendant for material, and it was to recover his resulting loss that he brought the present suit against the Indemnity Insurance Company on the basis of its several liability as surety on the bond. Defendant by scire facias brought in McCarthy as additional defendant. The latter contended at the trial that he had paid the prevailing rate for non-union labor and was not obliged to employ union labor; moreover, that plaintiff knew the rate of wages being paid but impliedly waived objection thereto and thus precluded himself from suddenly thereafter terminating the contract on that ground. Considerable evidence was presented by the parties on both phases of this defense.

The court below granted the motions of defendant and additional defendant for a new trial because, although the trial judge had properly instructed the jury that under the ,Act of June 22, 1931, P. L. 663, they might *116 bring in a verdict in favor of plaintiff against both defendant and additional defendant, the verdict was inconsistently rendered in favor of plaintiff against the surety only and not against the principal, and, in the opinion of the court, this anomaly resulted from the fact that the trial judge had erroneously admitted in evidence certain letters from defendant to plaintiff, erroneously interpreted their import, and erroneously charged in regard to their possible effect upon the verdict. .

It appears that when .plaintiff gave notice to additional defendant of the cancellation of the contract between them, as to which additional defendant immediately protested, plaintiff also furnished notice of this action to defendant, and of his intention to complete the work if defendant did not elect to do so itself. Defendant did not challenge plaintiff’s action, as additional defendant had done, but merely replied that it elected not to complete, and desired to cooperate with plaintiff in every way to bring about a satisfactory completion; at the same time it called plaintiff’s attention to his obligation, in completing, to do so at a fair and reasonable cost. Subsequently plaintiff wrote several letters to defendant setting forth claims of additional defendant’s mechanics and laborers to wages alleged to have been improperly withheld from them by additional defendant and asking defendant’s approval of plaintiff’s payment of these claims, to which, in each case, defendant replied that, if it should develop at a later date that plaintiff had a valid claim on the bond, defendant would raise no objection to the sum stated by plaintiff as an amount payable to the laborer or mechanic in question. In a final letter, defendant again stated to plaintiff its desire for cooperation to bring about a satisfactory completion of the work and repeated its reminder of his obligation to complete at a reasonable cost.

All of the letters constituting this correspondence were admitted in evidence, and in his charge to the jury the *117 learned trial judge referred to them in the following manner: “Now, while those letters aren’t too clear, I construe them as an admission of liability by the Indemnity Company to McShain. They admit in those letters that they are liable to them. And that is evidence you must consider against the Indemnity Company, but not against McCarthy, because McCarthy didn’t write the letters. ... If that is just the little thing that turns the balance in your mind, in favor of the plaintiff, if you feel that because of that the plaintiff should recover, and if without that you would be quite divided in your mind as to whether or not he should . . . and if that is the only thing upon which you decide in his favor, then you couldn’t decide in favor of 1 McCarthy; you would have to decide in favor of 1 the Indemnity Company only and not in favor of 1 McCarthy. However, that makes very little difference, because if you find a verdict for the plaintiff against the Indemnity Company, then you must, under the state of this, case and the record and pleadings, find a verdict for the Indemnity Company against McCarthy for the same amount. ... If you decide ... in favor of the plaintiff . . . your verdict should be for him, and it should be against the two companies, 2 unless, as I say, you are swayed by that one little fact; and then if you are swayed by that one fact, it should be against the Indemnity Company alone, and then you have to find a separate verdict in favor of the Indemnity Company against McCarthy. It is just a difference in the form of the verdict.”

Since the jury were instructed they might bring in a verdict against both defendant and additional defendant, but, if they were swayed only by the letters, they should find in favor of plaintiff against defendant and not against additional defendant, and since the jury did so *118 find, they evidently were swayed only by the letters and must have concluded that without them plaintiff did not establish his case, that is, did not prove a breach of contract by additional defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eastern Steel Const. v. International Fidelity
2022 Pa. Super. 149 (Superior Court of Pennsylvania, 2022)
Superior Precast, Inc. v. Safeco Ins. Co. of America
71 F. Supp. 2d 438 (E.D. Pennsylvania, 1999)
General Equipment Manufacturers v. Westfield Insurance
635 A.2d 173 (Superior Court of Pennsylvania, 1993)
Havasy v. Resnick
609 A.2d 1326 (Superior Court of Pennsylvania, 1992)
Knecht, Inc. v. United Pacific Insurance Company
860 F.2d 74 (Third Circuit, 1988)
Semieraro v. Commonwealth Utility Equipment Corp.
544 A.2d 46 (Supreme Court of Pennsylvania, 1988)
Adams v. Mackleer
361 A.2d 439 (Superior Court of Pennsylvania, 1976)
Kuhns v. Brugger
135 A.2d 395 (Supreme Court of Pennsylvania, 1957)
Bergen v. Lit Bros.
47 A.2d 671 (Supreme Court of Pennsylvania, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
12 A.2d 59, 338 Pa. 113, 1940 Pa. LEXIS 469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcshain-v-indemnity-insurance-co-of-north-america-pa-1940.