McKnight Construction Co. v. Perry

888 F. Supp. 1178, 1994 U.S. Dist. LEXIS 20388, 1994 WL 808564
CourtDistrict Court, S.D. Georgia
DecidedDecember 23, 1994
DocketNo. CV194-188
StatusPublished
Cited by1 cases

This text of 888 F. Supp. 1178 (McKnight Construction Co. v. Perry) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKnight Construction Co. v. Perry, 888 F. Supp. 1178, 1994 U.S. Dist. LEXIS 20388, 1994 WL 808564 (S.D. Ga. 1994).

Opinion

ORDER

BOWEN, District Judge.

The Plaintiff, McKnight Construction Company, Inc. (McKnight Construction), moves the Court for an injunction barring the Defendants from implementing and administering a federal construction contract awarded to Conner Brothers. Plaintiffs motion came on for hearing on December 12, 1994. Based on the evidence presented at the hearing and applicable authorities, Plaintiffs Motion for Temporary Restraining Order and Preliminary Injunction is GRANTED. The Court enters its findings pursuant to Rule 65(d), Fed.R.Civ.P., as follows.

On May 17, 1994, the U.S. Army Corps of Engineers, Savannah, Georgia, District (hereafter “the Corps”), issued invitation for bids (IFB) No. DACA21-94-B-0059, soliciting bids for the renovation of Army barracks at Kelly Hill, Fort Benning, Georgia. The bid schedule included 10 bid line items for an aggregate base bid plus one additive.2 The Corps received four bids on June 20, 1994:

Base Bid

Base Bid Plus Add. 1

McKnight Construction $16,707,000.00 $16,850,000.00

Conner Brothers 16,698,000.00 16,969,000.00

Dawson Const. Co. 16,938,000.00 17,213,000.00

Wright Assoc., Inc. 17,014,700.00 17,298,422.00

Government’s estimate 17,440,834.00 18,115,491.00

McKnight Construction was the apparent low bidder, by $119,000. A copy of the bid abstract showing the four lowest bidders and the Government’s estimate of costs by bid line items is appended to this Order.

Plaintiffs president, William Davis McKnight, prepared and submitted its bid. In completing the bid form, McKnight transposed his bids for line items one and two with bid line items four and five. Because of dramatic differences in costs associated with bid line items one and two compared to four and five, the mistake is obvious from a cursory inspection of the bid form, as well as the bid abstract.3 He allocated excessively high costs to bid line items one and two and very low figures to bid line items four and five, compared to the other contractors’ submissions.

By letter dated June 21, 1994, Conner Brothers, the next lowest bidder, informed the Corps that McKnight Construction’s bid was unbalanced and requested that it be rejected. Upon discovering the mistake on June 22, McKnight Construction contacted the Corps by telephone to apprise it of the mistake. The asserted basis for the mistake was that the unit prices for bid line items one and two were transposed with bid line items four and five. Plaintiff sent the Corps a letter to this effect via facsimile on June 28, 1994, requesting permission to correct its bid to reflect the intended allocation of bid line items; its base bid would be unchanged.

On June 24, 1994, the Corps received another letter from McKnight Construction, reiterating the transpositional nature of its mistake and requesting permission to correct the mistake. Counsel included with the June 24, 1994, letter copies of Mr. McKnight’s original bid working papers and his sworn affidavit. The various notations and computations shown in Mr. McKnight’s bid work papers do not identify bid items or individual buildings; it is virtually impossible to determine the intended allocation of bid line items from McKnight’s bid work papers. McKnight’s affidavit explains that he simply transposed bid line items one and two with four and five.4 On June 28, 1994, McKnight [1181]*1181Construction’s lawyer again wrote the Corps regarding the mistake and tendered McKnight’s “post-bid opening” worksheets wherein he purports to “reconstruct” his thought processes relative to the allocation of bid line items.

The Corps’ contracting officer, Defendant Robert C. Hoffman, determined that McKnight Construction’s request to correct its bid should be denied. On June 28, 1994, the Corps, through its Division Commander, denied Plaintiffs request to correct. The Coips found that while there was clear and convincing evidence of a mistake in the bid, there was not clear and convincing evidence of Plaintiffs intended allocation among bid line items. (See Admin.Rec. Exh 3, Tab D.)

On June 29, 1994, McKnight Construction received notice that its request for correction had been denied. On July 1,1994, McKnight Construction filed with the General Accounting Office its protest of the Corps’ decision to reject its bid. On November 7, 1994, the Comptroller General denied McKnight’s protest. Matter of McKnight Construction Company, Inc., B-257782 (C.G.1994).

McKnight Construction filed this lawsuit on December 2, 1994, seeking judicial review of the Corps’ decision to reject its bid. The Court’s subject matter jurisdiction is unchallenged. See 28 U.S.C. § 1331, 31 U.S.C. § 3556. Section 702, 5 U.S.C., confers standing on McKnight Construction to challenge the Corps’ interpretation and application of the Federal Acquisition Regulations in connection with this procurement. Notice to proceed with performance of the contract has been withheld from Conner Brothers pending final resolution of Plaintiffs protest.

The Federal Acquisition Regulations require that contracts be awarded to the lowest responsible bidder.5 See 48 C.F.R. § 14.103-2. A bid may be rejected by the contracting officer, however, if “the prices for any line items ... are materially unbalanced.” Id., § 14.404-2(g). That McKnight Construction’s submitted bid was materially unbalanced due to the erroneous allocation of bid line items is undisputed. See id., § 15.814. At issue in this declaratory judgment action is whether correction of the bid should have been allowed. See id., § 14.406-3.

A preliminary injunction is drastic equitable relief. To prevail on its Motion, McKnight Construction must clearly demonstrate: (1) a substantial likelihood of success on the merits; (2) that it will be irreparably injured if the injunction does not issue; (3) that the threatened injury to the movant outweighs whatever damage the proposed injunction may cause an opposing party; and (4) that an injunction would be in the public interest.

Likelihood of Success

Plaintiffs assertions are not evaluated as if made to this Court in the first instance. The District Court is not the agency vested with authority under the Federal Acquisition Regulations to make determinations concerning alleged bidding errors, see 48 C.F.R. § 14.406-3(e); that authority was delegated in this ease to the Division Commander of the Corps. The judicial review to which Plaintiff is entitled is of the Corps’ decision making process. Under the Admin[1182]*1182istrative Procedure Act, 5 U.S.C. §§ 701, et seq., an executive agency’s action may be set aside if “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law[.]” Id., § 706(2)(A). See Choctaw Mfg. Co., Inc. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKnight Construction Co. v. Perry
888 F. Supp. 1186 (S.D. Georgia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
888 F. Supp. 1178, 1994 U.S. Dist. LEXIS 20388, 1994 WL 808564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcknight-construction-co-v-perry-gasd-1994.