McDonald Welding & Machine Co. v. Lehman

648 F. Supp. 1338, 1986 U.S. Dist. LEXIS 17203
CourtDistrict Court, N.D. Ohio
DecidedNovember 26, 1986
DocketNo. C86-4486Y
StatusPublished
Cited by2 cases

This text of 648 F. Supp. 1338 (McDonald Welding & Machine Co. v. Lehman) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonald Welding & Machine Co. v. Lehman, 648 F. Supp. 1338, 1986 U.S. Dist. LEXIS 17203 (N.D. Ohio 1986).

Opinion

MEMORANDUM OF OPINION AND ORDER FINDING THE AWARDING OF THE LOT III CONTRACT TO GICH-NER ILLEGAL

KRENZLER, District Judge.

Plaintiffs commenced the above-captioned suit on October 22, 1986. Along with the complaint, plaintiffs filed motions seeking a temporary restraining order and a preliminary injunction. Plaintiffs seek a declaratory judgment that defendant’s activities to date and the exclusion of McDonald Welding & Machine Co., Inc. (“McDonald”) from the bid competition process at issue are invalid, unlawful and contrary to the procurement policy of the United States. Plaintiffs further request this Court to enjoin the defendant and its officers, agents, employees and representatives from allowing continued performance and awarding another contract under N00140-86-R-0987 to anyone other than McDonald.

After a hearing on plaintiffs’ motion for a temporary restraining order, this Court issued an Order, dated October 28, 1986, overruling plaintiffs’ motion and setting an expedited briefing schedule in this matter. Pursuant to this Order, the plaintiffs filed a combined motion for summary judgment, and the defendant filed a motion to dismiss or for summary judgment. At that time, defendant also filed the administrative record in this case under seal. The Court heard full arguments on these motions on November 25, 1986. Because authorities are sparse in this area of the law, the Court concludes that a full discussion is warranted.

I.

A review of the administrative record reveals the following facts. On February 13, 1986, the Naval Regional Contracting Center in Philadelphia, Pennsylvania, issued solicitation N00140-86-R-0987 to procure 1,024 mobile facility units (“MFV”). These MFV units are eight foot by eight foot by twenty foot vans, which function as containerized aviation maintenance facilities for the United States Navy, Marine [1340]*1340Corps, and Air Force weapons systems. The MFV units are an integral support element for the Rapid Deployment Force and are used primarily as maintenance facilities for aircraft electronic and mechanical systems.

As originally structured, the solicitation was divided into two “lots.” Lot I called for the production of 1,024 MFV units and contained a First Article Testing (“FAT”) requirement. Lot II sought the production of the same 1,024 units, but waived the FAT requirements for those contractors who had already undergone and passed FAT. Thus, both offerors who had passed FAT, in addition to those contractors who had not previously passed FAT, were eligible to submit offers for the production of the 1,024 MFV units. The solicitation closed on April 12, 1986 with twelve offers received.

After the solicitation had closed, the Navy determined that it was necessary to obtain delivery of 337 MFV units in the shortest time period possible. The Navy further concluded that the total requirement should be reduced from a total of 1,024 MFV units to a total of 824 MFV units (the 337 MFV units plus an additional 487 MFV units). Since production lead time with FAT is seven months longer than production lead time without FAT, the contracting officer determined that acquisition of the urgently required 337 units would be restricted to those contractors which had already passed FAT. A “Justification and Approval,” as required by 10 U.S.C. § 2304(f), was prepared by the contracting officer and approved at the required level to limit competition on the urgently needed 337 MFV units by requiring prior FAT passage.

The solicitation was revised to reduce the quantity to be procured from 1,024 MFV units to 824 MFV units. The amendment to the solicitation also established three lots. Lots I and II represented the unrestricted requirement for 487 MFV units. As before, Lots I and II could be bid upon by those firms which had passed FAT, as well as those firms which had not passed FAT. Lot III was for the urgently needed 337 MFV units, and was restricted to those offerors who had previously passed FAT. The closing date for this revised solicitation was established as August 25, 1986.

Nine offers were submitted for the revised solicitation. Four firms submitted offers on Lot III, claiming eligibility for FAT waiver:

FIRM OFFER

Gichner Mobile Systems $ 6,972,085.40

Craig Systems Corporation 10,155,807.43

McDonald 6,227,824.20

McDonald 5.560.513.40

McDonald 5.360.725.40

Allied Materials & Equipment Co., Inc. 5.827.373.40

The Navy rejected the offers of Allied Materials & Equipment Co., Inc. (“Allied”) and McDonald as not meeting the solicitation requirements, since neither McDonald nor Allied had yet passed FAT. After determining that Gichner Mobile Systems (“Gichner”) and Craig Systems Corporation had each previously passed FAT, the Navy awarded the Lot III contract to Gichner as the low acceptable offeror on September 11, 1986. The award of Lot I/Lot II has not yet been made by the Navy. McDonald protested the Lot III award by filing protests with the General Accounting Office on September 17 and 18, 1986.

II.

Plaintiffs assert that the Court is vested with jurisdiction over this matter pursuant to the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 701, et seq. See Scanwell Laboratories, Inc. v. Shaffer, 424 F.2d 859 (D.C.Cir.1970) (unsuccessful bidder has standing to bring suit in district court under the APA). Section 702 contains a limited waiver of the sovereign immunity enjoyed by the United States and its agencies: “A person suffering legal wrong because of agency action ... is entitled to judicial review thereof.”

Review under the APA is a review of the administrative record; the Competition in Contracting Act (“CICA”), 31 U.S.C. §§ 3551, et seq., defines the composition of the record upon review. 31 U.S.C. § 3556. [1341]*1341The standard the Court must employ in reviewing the contracting officer’s action is set forth in the APA, which provides that a reviewing court may hold unlawful and may set aside any agency action found to be “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A).

In their motion for summary judgment, plaintiffs contend that the actions undertaken by the defendant with regard to the award of Lot III to Gichner failed to conform to several statutory and regulatory requirements, and that judicial action to allow relief from those procurement defects is essential. Defendant raises a variety of other issues in its motion to dismiss or for summary judgment, but the Court finds that the statutory and regulatory issues addressed below are the only relevant issues.

A.

First, plaintiff alleges defendant violated the competition requirements of CICA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
648 F. Supp. 1338, 1986 U.S. Dist. LEXIS 17203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonald-welding-machine-co-v-lehman-ohnd-1986.