McDonald Welding and MacHine Company, Inc. v. James H. Webb, Jr., Secretary of the Navy

829 F.2d 593
CourtCourt of Appeals for the Sixth Circuit
DecidedOctober 30, 1987
Docket87-3068
StatusPublished
Cited by16 cases

This text of 829 F.2d 593 (McDonald Welding and MacHine Company, Inc. v. James H. Webb, Jr., Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonald Welding and MacHine Company, Inc. v. James H. Webb, Jr., Secretary of the Navy, 829 F.2d 593 (6th Cir. 1987).

Opinion

CORNELIA G. KENNEDY, Circuit Judge.

Defendant-appellant James H. Webb, Jr., Secretary of the Navy, (“defendant” or *594 “Navy”) appeals the District Court’s judgment granting partial summary judgment for the plaintiff. The District Court found that the defendant violated 10 U.S.C. § 2305 by awarding a procurement contract to Gichner Mobile Systems (“Gichner”), and also violated the mandatory stay provision of 31 U.S.C. § 3553(d)(1). The defendant raises two issues on appeal: 1) whether the District Court erred in finding that Gichner Mobile Systems (“Gichner”) was ineligible to receive the Lot III MFV contract; and 2) whether the District Court erred in determining that the defendant violated the post-award stay provisions of 31 U.S.C. § 3553(d)(1). For the reasons set forth below, we reverse.

In 1986 the Navy solicited bids for 824 mobile facility units (“MFV units”). MFV units are vans, measuring eight feet by eight feet by twenty feet, which contain aircraft repair shops. The Navy subsequently decided that it urgently needed 337 MFV units. Consequently the contracting officer, in accordance with 10 U.S.C. § 2304(f), prepared a “Justification and Approval” which limited competition on the urgently needed 337 MFV units to those firms which had previously passed First Article Testing (“FAT”). The final solicitation was divided into three lots. Lots I and II were unrestricted solicitations for 487 MFV units; bidders who had previously passed FAT as well as those who had not could bid on these lots. Lot III was for the urgently needed 337 MFV units, and was restricted to those bidders who had previously passed FAT.

McDonald Welding & Machine Company (“plaintiff”) and Gichner were among the bidders on Lot III. Although the plaintiff’s bid was lower than Gichner’s, the Navy rejected it because the plaintiff had not previously passed FAT. Finding Gichner’s bid was the lowest bid by a contractor who had previously passed FAT, the defendant awarded the Lot III contract to Gichner on September 11, 1986.

The plaintiff filed protests of the Lot III award with the General Accounting Office (“GAO” or “Comptroller General”) in September of 1986, which the GAO dismissed. The plaintiff 1 then brought suit against the defendant in the U.S. District Court for the Northern District of Ohio, seeking a declaratory judgment that the defendant illegally awarded the Lot III contract to Gichner 2 and illegally excluded the plaintiff from the Lot III bidding process. The District Court granted in part the plaintiff’s motion for summary judgment, finding that Gichner was not eligible to bid on the Lot III contract and that therefore the award was illegal under 10 U.S.C. § 2305(b)(1), which requires the head of an agency to evaluate bids solely on the basis of the factors specified in the solicitation. The District Court denied the motion as to the plaintiff's claim that it was entitled to the award of the Lot III contract, finding that the plaintiff was not eligible to bid on the contract. 3 Defendant appealed. 4

I.

The defendant’s first issue is whether the District Court erred in finding that Gichner had not passed FAT and consequently was not eligible to bid on the Lot III solicitation. Under the Administrative Procedure Act, 5 U.S.C. §§ 701-706, a reviewing court may overturn an agency’s *595 actions, findings and conclusions if the court finds that they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). Case law has interpreted this section as requiring the party challenging the agency’s action to show that the action had no rational basis or that it involved a clear and prejudicial violation of applicable statutes or regulations. See, e.g., Saco Defense Sys. Div. v. Weinberger, 806 F.2d 308, 310-11 (1st Cir.1986); Sea-Land, Serv., Inc. v. Brown, 600 F.2d 429, 430 (3d Cir. 1979).

The Navy limited the solicitation for the Lot III MFV units to those bidders who had previously “passed” FAT. The defendant attempted to show that Gichner had passed FAT by introducing a December 1, 1975 letter from the Navy to Gichner which stated that “[t]he First Article Test Report [of the MFV unit] is hereby accepted.” Joint Appendix at 71 (emphasis added). The District Court, finding that “accepted” is not synonymous with “passed”, ruled that the letter was not evidence that Gichner had passed FAT and that therefore Gichner was ineligible to receive the Lot III contract. Id. at 23.

The defendant argues that this determination by the District Court was wrong for two reasons. He claims first, the court wrongly decided that the Navy’s determination that “accepted” meant “passed” was arbitrary and capricious, and second, the court should have admitted the affidavit of the engineer in charge of the MFV program, which states that “Gichner had previously passed first article test qualifications.” Joint Appendix at 63-64.

The District Court erred in holding that the Navy’s determination that “accepted” meant “passed” was arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law. In Norwich Eaton Pharmaceuticals, Inc. v. Bowen, 808 F.2d 486 (6th Cir.), petition for cert, filed, 55 U.S.L.W. 3714 (U.S. Apr. 9, 1987) (86-1633) this Court stated that “ ‘[a]n agency’s construction of a statute it is charged with enforcing is entitled to deference if it is reasonable and not in conflict with the expressed intent of Congress.’ ” Id. at 491 (quoting United States v. Riverside Bayview Homes, Inc., 474 U.S. 121, 131, 106 S.Ct. 455, 461, 88 L.Ed.2d 419 (1985)). An agency’s construction of a word in its own solicitation document should be entitled to at least that much deference. The Navy’s determination that its acceptance of Gichner’s FAT meant that Gichner had passed FAT is very reasonable and has a rational basis. See Sea-Land,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoedt v. Vanderbilt University
M.D. Tennessee, 2025
Chamber of Com. Of the United States v. SEC
115 F.4th 740 (Sixth Circuit, 2024)
David Hous. v. U.S. Dep't of Labor
318 F. Supp. 3d 1028 (W.D. Kentucky, 2018)
Lanier v. U.S. Dep't of Labor
296 F. Supp. 3d 834 (W.D. Kentucky, 2017)
Lahndorff v. U.S. Dep't of Labor
289 F. Supp. 3d 826 (W.D. Kentucky, 2017)
Favor Techconsulting, LLC v. United States
132 Fed. Cl. 292 (Federal Claims, 2017)
MERIDIETH v. Chao
723 F. Supp. 2d 1044 (E.D. Tennessee, 2010)
TACO ESPECIAL v. Napolitano
696 F. Supp. 2d 873 (E.D. Michigan, 2010)
Trego v. United States Department of Labor
681 F. Supp. 2d 894 (E.D. Tennessee, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
829 F.2d 593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonald-welding-and-machine-company-inc-v-james-h-webb-jr-secretary-ca6-1987.