McCutcheon v. Philadelphia Electric Co.

788 A.2d 345, 567 Pa. 470, 2002 Pa. LEXIS 107
CourtSupreme Court of Pennsylvania
DecidedJanuary 22, 2002
StatusPublished
Cited by29 cases

This text of 788 A.2d 345 (McCutcheon v. Philadelphia Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCutcheon v. Philadelphia Electric Co., 788 A.2d 345, 567 Pa. 470, 2002 Pa. LEXIS 107 (Pa. 2002).

Opinion

OPINION

CAPPY, Justice.

We granted allocatur in this case to review the Superior Court’s failure to address two issues that the Appellants/Cross Appellees, Robert E. Lamb, Inc. (“Lamb”) and D.N.B. Mechanical Systems, Inc. (“DNB”), raised on appeal, and the Superi- or Court’s decision to overturn the award of delay damages made to the Cross Appellant, Geraldine McCutcheon. We have determined, however, that the trial court’s order which the parties appealed to the Superior Court is not a final order within the meaning of Pa.R.A.P. 341. Therefore, the Superior Court did not have appellate jurisdiction pursuant to 42 Pa.C.S. § 742, and the order it issued is void. As a consequence, this court is also without jurisdiction, there being no final order from the Superior Court, as 42 Pa.C.S. § 724 requires. Accordingly, the ■ Superior Court’s order must be vacated and this appeal must be quashed.

[347]*347The relevant facts and procedural history are as follows. The Appellee, Philadelphia Electric Co. (“PECO”), hired Lamb as a general contractor to build an addition to the Training Center at the Limerick Nuclear Power Plant. PECO and Lamb entered into a contract in which Lamb agreed, inter alia, to indemnify PECO against all claims and liability arising out of Lamb’s acts or omissions and those of its subcontractors, in connection with the addition, irrespective of whether PECO was concurrently negligent. Under the contract’s indemnity provision, Lamb was not obligated to cover claims caused by PECO’s sole negligence or willful misconduct.

A forced main sewer line connecting the addition to the power plant’s existing sewer lines was needed. Lamb subcontracted with DNB to construct needed plumbing and DNB subcontracted with Sutch Construction Co. (“Sutch”) for excavation. On May 21, 1992, James McCutcheon, a heavy equipment operator employed by United Engineers and Catalytic, an independent contractor on a separate project at the power plant, fell on a concrete slab that covered a sewer pipe and suffered bodily injuries.

On July 26, 1998, James McCutcheon and his wife, Geraldine McCutcheon, (collectively, the “McCutcheons”), filed a complaint in negligence against PECO. Later, on July 19, 1995, they filed an amended complaint to include Lamb, DNB and Sutch as defendants. In their amended complaint, the McCutcheons alleged that the defendants were negligent in permitting a dangerous and defective condition to exist on the power plant property.

Lamb, DNB and Sutch raised the statute of limitations as a defense. In an Answer With New Matter To Plaintiffs’ Complaint And Crossclaims Pursuant To Pa.R.Civ.P. 2252(d), PECO asserted cross-claims against its co-defendants, alleging that Lamb, DNB and/or Sutch “are solely liable to the plaintiffs, and/or are jointly or severally liable to the plaintiffs and/or liable to answering defendant [PECO] by way of indemnification and/or contribution.” (R. 1635a).

The parties proceeded to trial before the Honorable Paul J. Ribner.1 At the outset, PECO informed the trial court of its cross-claims for contribution and indemnification, specifically referring to the cross-claim for indemnity it had alleged against Lamb based on the parties’ contract. Viewing PECO’s contractual indemnity cross-claim as a matter of law which raised a question of contract interpretation for the court to decide, the trial court determined that the cross-claim would be argued orally following the jury’s verdict and that the verdict would be molded appropriately.

The jury returned a verdict in favor of James McCutcheon for the injuries he sustained and in favor of Geraldine McCut-cheon for loss of consortium, and against all of the defendants severally and jointly. The jury found PECO 48% negligent, Lamb, 42% negligent, DNB 9% negligent, and Sutch, 1% negligent. The jury also found that James McCutcheon was negligent, but declined to find that his negligence was a contributing cause of his injuries.

After dismissing the jury, Judge Ribner informed the parties that he was about to retire from the bench and that he would not be presiding over post-trial matters. PECO’s counsel reminded the trial court of PECO’s contractual claim for indemnification. When asked whether proceedings on the cross-claim were needed immediate[348]*348ly, PECO’s counsel stated that they were not. The trial court advised the parties to pursue all outstanding issues by filing the appropriate motions.

The McCutcheons filed a motion for delay damages. PECO, Lamb and DNB filed post-trial motions and responses opposing the McCutcheons’ delay damages request. Based on its contract with Lamb, PECO filed a Motion for Summary Judgment on Crossclaim for Indemnification.2

By order dated March 9, 1999, the trial court denied PECO’s, Lamb’s and DNB’s motions for post trial relief; awarded delay damages to both the McCutcheons; and denied PECO’s Motion for Summary Judgment on Crossclaim for Indemnification. As to the latter, the trial court concluded that summary judgment was improper because there exist genuine issues of material fact regarding the interpretation of the indemnity provision in the parties’ contract. On March 11, 1999, judgment was entered on the verdict.

PECO, Lamb, and DNB appealed to the Superior Court from the trial court’s March 9,1999 order.

In their respective appeals, Lamb and DNB contended that the trial court erred in denying them post-trial relief based on the statute of limitations. In an unpublished memorandum opinion, the Superior Court agreed, concluding that the trial court mistakenly applied the concealment doctrine to toll the statute. Accordingly, the court ruled that the McCutcheons’ claims against Lamb and DNB were time-barred, and held that the trial court erred in not dismissing Lamb and DNB from the McCutcheons’ action.

At the same time the Superior Court determined that the McCutcheons’ claims against Lamb and DNB were time-barred, the court observed that the bar had no effect on PECO’s right to enforce claims for contribution and indemnification against its co-defendants. In this regard, the Superior Court discussed the “separate proceedings” it believed PECO had already initiated to collect for contribution and/or indemnification from Lamb and DNB and announced its intention to quash as interlocutory that portion of PECO’s appeal which raised the trial court’s denial of its motion for summary judgment on the claim for indemnity it had asserted against Lamb in the “separate action”. (Superior Court’s Memorandum Opinion at p. 6 n. 2.)3

Based on its statute of limitations ruling, the Superior Court declined to address the other issues Lamb and DNB had raised, [349]*349which included whether they owed a duty of care to James McCutcheon because they did not control the area where he fell, and whether the evidence was sufficient to support the jury’s verdict apportioning fault against them.

Last, the Superior Court turned to the matter of delay damages. The court concluded that since the statute of limitations prevented the McCutcheons from directly suing Lamb and DNB, delay damages could not be levied against them. The court also stated that if PECO continued to maintain its action for contribution and indemnity against Lamb and DNB, PECO may seek compensation for having paid their portion of the delay damages award. The court then applied our decision in Anchorstar v. Mack Trucks, 533 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com. v. Flanders, D.
2026 Pa. Super. 60 (Superior Court of Pennsylvania, 2026)
D.L. Smith v. Ivy League Real Estate, LLC
Commonwealth Court of Pennsylvania, 2024
Com. v. Lukehart, T.
Superior Court of Pennsylvania, 2023
Bennett Williams Reality Inc. v. Four Brothers LLC
Superior Court of Pennsylvania, 2023
Jay Fulkroad & Sons v. Bor. of Northumberland
Superior Court of Pennsylvania, 2023
In the Matter of: Mergl, R. Appeal of: Mergl, R.
Superior Court of Pennsylvania, 2022
Com. v. Snyder, B.
Superior Court of Pennsylvania, 2022
PFCU v. Bass, R.
Superior Court of Pennsylvania, 2022
Haverford Hill Condo Assoc. v. M.K. Lekoma
Commonwealth Court of Pennsylvania, 2021
Com. v. Vazquez, J.
Superior Court of Pennsylvania, 2021
Com. v. Mickell, J., Jr.
Superior Court of Pennsylvania, 2020
Manidis, T. v. Manidis, R.
Superior Court of Pennsylvania, 2020
Kurach, K. v. Truck Insurance Exchange
Superior Court of Pennsylvania, 2018
Commonwealth v. Horn
172 A.3d 1133 (Superior Court of Pennsylvania, 2017)
Brace, C. v. Lyons, D.
Superior Court of Pennsylvania, 2016
McCarthy, G. v. Armstrong, J.
Superior Court of Pennsylvania, 2016
Conestoga Bank v. Tioga Invs. II, LLC
138 A.3d 652 (Superior Court of Pennsylvania, 2016)
Turner Construction v. Plumbers Local 690
130 A.3d 47 (Superior Court of Pennsylvania, 2015)
Gleeson, M. v. B. Zipay Contractors, Inc.
Superior Court of Pennsylvania, 2015

Cite This Page — Counsel Stack

Bluebook (online)
788 A.2d 345, 567 Pa. 470, 2002 Pa. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccutcheon-v-philadelphia-electric-co-pa-2002.