Mayor of Savannah v. Batson-Cook Co.

714 S.E.2d 242, 310 Ga. App. 878, 2011 Fulton County D. Rep. 2504, 2011 Ga. App. LEXIS 395
CourtCourt of Appeals of Georgia
DecidedMay 11, 2011
DocketA11A0768
StatusPublished
Cited by4 cases

This text of 714 S.E.2d 242 (Mayor of Savannah v. Batson-Cook Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayor of Savannah v. Batson-Cook Co., 714 S.E.2d 242, 310 Ga. App. 878, 2011 Fulton County D. Rep. 2504, 2011 Ga. App. LEXIS 395 (Ga. Ct. App. 2011).

Opinion

McFadden, Judge.

The City of Savannah appeals the judgment entered in this action arising from the construction of an underground parking garage. The dispute arose out of the discovery of “materially different site conditions,” as defined under the parties’ contract. Raito, Inc., a subcontractor on the project, filed the action against Batson-Cook Company, the firm the city hired to design and build the garage. Batson-Cook then filed a third-party complaint against the city.

The city argues that the trial court erred in denying its motion to recuse the trial court judge, contending that, at a minimum, he should have assigned the motion to another judge for resolution. But the city’s factual assertions are legally insufficient to warrant recusal. The city argues that the trial court erred in its ordering of the trial, but the trial court did not abuse its broad discretion in this regard. The city argues that it was entitled to a directed verdict on Batson-Cook’s claim for final payment because Batson-Cook did not fulfill the contract conditions for final payment, but at least some of the conditions with which Batson-Cook did not comply depended on resolution of the issues of this lawsuit. The city argues that the trial court should have granted its motion for directed verdict because Batson-Cook did not give it notice of the alleged materially differing *879 site conditions within the contractual deadline, but there was evidence that the city received timely notice. The city argues that the trial court should have granted its motion for directed verdict on Batson-Cook’s bad faith claim. But there was evidence that the city arbitrarily denied Batson-Cook’s claim for an adjustment in price despite knowing that conditions were very different from what the parties had believed when they entered the contract. The city argues that the trial court erred by charging the jury on quantum meruit and promissory estoppel. We disagree because, contrary to the city’s assertion, not all of the claims for payment arose from the parties’ contractual relationship. The city argues that Raito’s action was barred by its failure to comply with the Nonresident Contractors Act. But Raito’s late registration constituted substantial compliance with the Act. Finding that no enumeration requires the reversal of the judgment, we affirm.

The city hired Batson-Cook to design and build an underground parking garage at Ellis Square. The September 1, 2005 contract included a guaranteed maximum price of $29,592,416 and a completion date of August 28, 2007. The contract also included a “materially differing site conditions” clause, which provided that should Batson-Cook encounter site conditions that differed materially from the conditions indicated in the contract documents or from conditions ordinarily found to exist, the price of the contract would be adjusted. The contract required the party observing the materially different condition to notify the other party within 21 days.

In December 2004, prior to the execution of the contract, WPC, Inc., a local engineering firm the city had hired, prepared a preliminary soils report that analyzed four soil borings so that interested bidders could prepare cost proposals. The borings indicated that the northeast corner of the site contained soft clay. The contract entered between the city and Batson-Cook contemplated a second, more detailed soils report. At the city’s direction, Batson-Cook hired WPC to prepare the second report. On September 26, 2005, about two weeks after Batson-Cook and the city had entered their contract, WPC provided the second report. The second report showed no additional soft clay.

Batson-Cook hired Raito, Inc. to design and install an excavation support system for the project. After Raito began its work, it learned of additional soft clay at the site. Accordingly, it had to revise its design. Raito considered this to be a materially differing site condition, and so notified Batson-Cook on June 1, 2006.

Initially Batson-Cook denied that this was a materially differing site condition, but eventually it changed its opinion. When it did, Batson-Cook sought from the city an adjustment in the contract price based on differing site conditions. Because WPC’s engineer *880 disagreed that materially different site conditions existed, since both of its soil reports had identified soft clay at the site, the city denied Batson-Cook’s claim.

On March 6, 2008, before the project was completed, Raito sued Batson-Cook in Troup County, Batson-Cook’s corporate home, for $5.8 million. Raito sought reimbursement for the extra costs it incurred in redesigning and constructing the support system because of the differing soil conditions.

Batson-Cook answered Raito’s complaint and filed a third-party complaint against the city. Batson-Cook sought to pass through Raito’s damages, agreeing that if conditions at the site were materially different, then Raito was entitled to reimbursement but that the city should pay. Batson-Cook also sought damages of its own.

The city answered Batson-Cook’s complaint and filed a counterclaim against Batson-Cook. It alleged that Batson-Cook breached the contract and performance bond in unspecified ways.

The case was tried, and a jury returned a verdict in favor of Raito against Batson-Cook for $2,766,330 and for Batson-Cook against the city for $15,162,592 plus $2,009,620 in attorney fees and expenses. The jury also found Batson-Cook owed the city $594,000 for project delay. The city then filed this appeal.

1. The city challenges the denial of its motion to disqualify Judge William F. Lee, contending that at a minimum, Judge Lee should have assigned its motion to another judge for disposition. We review the denial of a motion to recuse for abuse of discretion. Vaughn v. State, 247 Ga. App. 368, 370 (2) (543 SE2d 429) (2000). Under Uniform Superior Court Rule (USCR) 25.3,

[w]hen a judge is presented with a motion to recuse, or disqualify, accompanied by an affidavit, the judge shall temporarily cease to act upon the merits of the matter and shall immediately determine the timeliness of the motion and the legal sufficiency of the affidavit, and make a determination, assuming any of the facts alleged in the affidavit to be true, whether recusal would be warranted. If it is found that the motion is timely, the affidavit sufficient and that recusal would be authorized if some or all of the facts set forth in the affidavit are true, another judge shall be assigned to hear the motion to recuse.

“[T]he court’s duty [is] limited to determining the legal sufficiency of the affidavit required under USCR 25.2.” Studenic v. Birk, 260 Ga. App. 364, 368 (2) (579 SE2d 788) (2003). “The focus here is not on bias in fact but whether the judge’s impartiality might reasonably be questioned, keeping in mind the reality that any judge will have *881 come to the bench after having had extensive contacts with the community and the legal profession.” (Punctuation omitted.) Sears v. State, 262 Ga. 805 (1) (b) (426 SE2d 553) (1993), overruled on other grounds, Brogdon v. State, 287 Ga. 528 (697 SE2d 211) (2010).

The city attached three affidavits to its motion to recuse. The first was the affidavit of Gregory K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caradigm USA LLC v. Pruithealth, Inc.
964 F.3d 1259 (Eleventh Circuit, 2020)
The Mayor and Alderman of the City of Savannah V.
Court of Appeals of Georgia, 2012
Mayor of Savannah v. Batson-Cook Co.
734 S.E.2d 743 (Court of Appeals of Georgia, 2012)
Mayor of Savannah v. Batson-Cook Co.
728 S.E.2d 189 (Supreme Court of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
714 S.E.2d 242, 310 Ga. App. 878, 2011 Fulton County D. Rep. 2504, 2011 Ga. App. LEXIS 395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayor-of-savannah-v-batson-cook-co-gactapp-2011.