Clover Cable of Ohio, Inc. v. Heywood

392 S.E.2d 855, 260 Ga. 341, 1990 Ga. LEXIS 266
CourtSupreme Court of Georgia
DecidedJuly 5, 1990
DocketS90A0011, S90A0013
StatusPublished
Cited by15 cases

This text of 392 S.E.2d 855 (Clover Cable of Ohio, Inc. v. Heywood) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clover Cable of Ohio, Inc. v. Heywood, 392 S.E.2d 855, 260 Ga. 341, 1990 Ga. LEXIS 266 (Ga. 1990).

Opinion

Fletcher, Justice.

Clover Cable of Ohio, Inc., a foreign corporation, is asserting contractual, quasi-contractual, tort, and equitable claims against other foreign corporations and a nonresident individual. Plaintiff predicates its claims on the allegation that under an oral agreement, plaintiff acted as a sub-subcontractor on a construction project. The trial court ruled that plaintiff’s complaint is subject to dismissal under a forum-barring clause in the Nonresident Contractors Act, Ga. L. 1978, p. 309, § 2 at 738 (codified at OCGA § 48-13-37), in that plaintiff did not comply with the registration and bonding requirements of the Act and granted summary judgment to defendants. OCGA § 48-13-37 provides:

No contractor who fails to register with the [State Revenue] [Cjommissioner as required by this article or who fails to comply with any provision of this article shall be entitled to maintain an action to recover payment for performance on the contract in the courts of this state.

The primary question for decision is whether a dismissal under OCGA § 48-13-37 is with or without prejudice. In a trilogy of decisions, Taco Bell Corp. v. Calson Corp., 190 Ga. App. 481 (379 SE2d 6) (1989); Adams v. PPT, Inc., 191 Ga. App. 729 (2) (382 SE2d 732) (1989); Rehco Corp. v. California Pizza Kitchen, 192 Ga. App. 92 (383 SE2d 643) (1989), the Court of Appeals has held that such a dismissal is without prejudice. For reasons which follow, we agree.

In March of 1986, U. S. Telcom, Inc., a long distance telephone carrier, entered into a contract with Burnup & Sims Telcom, Inc., under which Burnup became U. S. Telcom’s general contractor for the construction of a fiber-optic telecommunications line. On March 18, 1986, Burnup in turn entered into a unit-price subcontract with Heywood Associates under which Heywood Associates became the subcontractor responsible for excavation work and the installation of an underground conduit through which the telecommunications line runs. Clover alleges that it entered into an oral joint-venture agreement with Heywood Associates under which Clover and Heywood Associates were to split any net profits under the subcontract. Pursuant to this alleged agreement Clover provided construction equipment, employees, and capital for the subcontracting work.

Clover alleges that, with the knowledge of supervisory personnel of Burnup, Clover’s identity as a sub-subcontractor was camouflaged *342 because of a provision in the Burnup/Heywood subcontract prohibiting the employment of sub-subcontractors, and that A1 Rodgers, who is president of Clover, signed the subcontract as vice-president of Heywood so as to note Clover’s participation. At the time Clover and Heywood Associates entered into the oral agreement, controversies existed between Clover and John Heywood with regard to the receipt of funds under another joint-venture agreement. Clover contends that John Heywood, never intending to split profits with Clover, fraudulently induced Clover to enter into the present joint venture as a vehicle to procure cash and equipment from Clover in satisfaction of the other monies Clover allegedly owed Heywood.

By letter dated May 13, 1986, Clover sought to inform Burnup that Clover was a partner with Heywood Associates and to request that all payments under the subcontract be jointly payable to Clover and Heywood Associates. One week later Clover provided Burnup with documentary evidence tending to show that Clover had provided capital, equipment, and employees to Heywood Associates for Heywood’s performance of its subcontract with Burnup. After Burnup received these letters, John Heywood, at Burnup’s request, executed a sworn affidavit stating that Clover was not a party to the Burnup/ Heywood subcontract and that there were no unsatisfied mechanic’s or materialmen’s liens on the project.

In its complaint Clover has sought a recovery against Heywood Associates for breach of contract, or, in the alternative, quantum meruit. Clover has asserted claims against John Heywood for fraud in the inducement of the oral agreement, as well as fraud and misrepresentation in statements made in the sworn affidavit. Clover contends that after it gave Burnup notice of its participation in the subcontract, Clover became entitled to a recovery in quantum meruit against Burnup. Clover also asserts that an equitable lien in Clover’s favor was impressed upon contract balances in Burnup’s hands, that Burnup became contractually bound to Clover as an obligor of the Heywood/Clover partnership, and that Burnup’s refusal to remit contract balances to Clover and Heywood jointly was tortious.

The trial court dismissed the tort and equitable-lien claims asserted by Clover against Burnup, and, based upon the fact that Clover failed to comply with the registration and bonding requirements of the Nonresident Contractors Act, the trial court granted summary judgment in favor of each of the defendants as to all of Clover’s other claims. In Case No. S90A0011, Clover appeals, arguing that its claims are neither barred by the Act nor subject to dismissal by the trial court. In Case No. S90A0013, Burnup cross-appeals the trial court’s failure to dismiss all of Clover’s claims against Burnup, and Burnup argues that portions of an affidavit relied upon by Clover were inadmissible. Held:

*343 1. Under the broad language contained in OCGA § 48-13-30, construction of a telecommunications line fits within the definition of contracting activities under the Act. See Mullis v. Southern Co. Services, 250 Ga. 90 (4) (296 SE2d 579) (1982).

Furthermore, under what Clover refers to as the undisputed factual allegations in its complaint, Clover is a contractor under the Act and not merely a supplier of equipment. Cf. American &c. Supply Corp. v. Starline Mfg. Corp., 171 Ga. App. 790 (2) (320 SE2d 857) (1984).

2. (a) A nonresident contractor desiring to engage in the business of contracting in this State must register with the State Revenue Commissioner “for each contract when the total contract price or compensation to be received amounts to more than $10,000.00. . . .” OCGA § 48-13-31. The failure of the parties to reduce such a contract to writing does not exempt the contract from these requirements.

(b) Before entering into the performance of the contract, a contractor must execute a bond in an amount equal to 10% of the contract price or compensation to be received, OCGA § 48-13-32 (c) (1); when this is impracticable, a blanket or master bond is to be executed. OCGA § 48-13-32 (c) (2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of Darryl J. Ferguson
Supreme Court of Georgia, 2026
Mayor of Savannah v. Batson-Cook Co.
714 S.E.2d 242 (Court of Appeals of Georgia, 2011)
Lane Supply, Inc. v. W. H. Ferguson & Sons, Inc.
649 S.E.2d 614 (Court of Appeals of Georgia, 2007)
Mitsubishi Motors Credit of America, Inc. v. Sheridan
650 S.E.2d 357 (Court of Appeals of Georgia, 2007)
Le v. SHEPHERD'S POND HOMEOWNERS ASS'N
633 S.E.2d 363 (Court of Appeals of Georgia, 2006)
Gateway Bank & Trust v. Timms
577 S.E.2d 15 (Court of Appeals of Georgia, 2003)
Kline v. Atlanta Gas Light Co.
538 S.E.2d 93 (Court of Appeals of Georgia, 2000)
Transportation Insurance v. El Chico Restaurants, Inc.
524 S.E.2d 486 (Supreme Court of Georgia, 1999)
Health Horizons, Inc. v. State Farm Mutual Automobile Insurance
521 S.E.2d 383 (Court of Appeals of Georgia, 1999)
Underground Festival, Inc. v. McAfee Engineering Co.
447 S.E.2d 683 (Court of Appeals of Georgia, 1994)
Mayor of Savannah v. Norman J. Bass Construction Co.
441 S.E.2d 63 (Supreme Court of Georgia, 1994)
Fuller Enterprises, Inc. v. Hardin Construction Group, Inc.
424 S.E.2d 311 (Court of Appeals of Georgia, 1992)
Department of Transportation v. Moseman Construction Co.
393 S.E.2d 258 (Supreme Court of Georgia, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
392 S.E.2d 855, 260 Ga. 341, 1990 Ga. LEXIS 266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clover-cable-of-ohio-inc-v-heywood-ga-1990.