Lane Supply, Inc. v. W. H. Ferguson & Sons, Inc.

649 S.E.2d 614, 286 Ga. App. 512, 2007 Fulton County D. Rep. 2346, 2007 Ga. App. LEXIS 820
CourtCourt of Appeals of Georgia
DecidedJuly 11, 2007
DocketA07A0701
StatusPublished
Cited by5 cases

This text of 649 S.E.2d 614 (Lane Supply, Inc. v. W. H. Ferguson & Sons, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane Supply, Inc. v. W. H. Ferguson & Sons, Inc., 649 S.E.2d 614, 286 Ga. App. 512, 2007 Fulton County D. Rep. 2346, 2007 Ga. App. LEXIS 820 (Ga. Ct. App. 2007).

Opinion

Bernes, Judge.

Lane Supply, Inc. sued W. H. Ferguson & Sons, Inc. and Premier Petroleum, Inc. asserting claims arising out of Lane’s work in supplying materials and labor in a project to “rebrand” 25 gasoline retail *513 outlets. The trial court granted summary judgment in favor of Ferguson and Premier. On appeal, Lane argues that the trial court erred in granting summary judgment to Ferguson and Premier on its quantum meruit and promissory estoppel claims. We disagree and affirm.

Summary judgment is proper where the movant shows no genuine issue of material fact exists and entitlement to summary judgment as a matter of law. A defendant carries this burden by demonstrating the absence of evidence as to one essential element of plaintiffs case. Should the defendant do so, the plaintiff cannot rest on [its] pleadings, but rather must point to specific evidence giving rise to a triable issue.

(Citations and punctuation omitted.) Jackson v. K-Mart Corp., 242 Ga. App. 274, 275 (529 SE2d 404) (2000). See OCGA § 9-11-56 (c). Our review of the grant of summary judgment is de novo, and “we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant.” (Citation omitted.) Ledford v. Smith, 274 Ga. App. 714, 715 (618 SE2d 627) (2005).

So viewed, the evidence shows that appellee Ferguson is a wholesale fuel supplier. In that capacity, Ferguson buys gasoline from Motiva Enterprises, LLC, which owns the Shell brand, and sells the fuel to independent service stations.

In November 2002, Ferguson entered into a “Fast Fusion Enrollment Agreement” with Motiva to convert 25 retail service stations to the Shell brand. Ferguson owned one of the stations to be converted, whereas the other stations were owned by independent third parties.

Ferguson contracted with SEF Construction Company, Inc. to perform construction work associated with the rebranding of the service stations. SEF then subcontracted with appellant Lane to supply materials and labor for the rebranding. Notably, Ferguson, SEF, and Lane never contracted with the service station owners themselves in connection with the rebranding of the stations, although the station owners were aware that the rebranding work was being performed.

During the course of the rebranding, Ferguson sold the gasoline supply rights to some of the stations that were being rebranded to appellee Premier, another wholesale fuel supplier. Premier took over responsibility for rebranding these stations, and Motiva paid Premier for the rebranding.

Apart from a de minimus amount, SEF did not pay Lane for its rebranding work. In August and September 2003, Lane filed materialman’s liens against the 25 stations involved in the rebranding, *514 although Lane had not installed any materials on some of the stations. Station owners began demanding that Ferguson and Premier have the liens removed.

On December 1, 2003, Premier’s president, Aziz Dhanani, telephoned Lane’s CFO, Steve Golovich. Dhanani told Golovich that he was with Ferguson’s vice president, Sherry Ferguson, and they were calling because they “wanted to get this matter settled.” Dhanani then explained that Premier and Ferguson had divided up responsibilities, with Premier taking the role with respect to the sites for which Lane claimed that it was owed for uninstalled materials, while Ferguson was to be responsible for finalizing the “installed jobs.” Golovich told Dhanani that Lane needed to be paid all of the money it was owed for its work, and that Lane’s foreclosure on its lien rights was its most viable tool for being made whole. Dhanani responded to Golovich, “You will be paid a hundred percent on all of the material-only jobs and all the installed jobs.” Dhanani estimated that Lane would have full payment by the end of December because “it was very close for funds flowing.” Dhanani did not, however, specify who would pay Lane. In light of Dhanani’s statements, Golovich told Dhanani that Lane would not foreclose on the liens.

Thereafter, Ferguson’s president sent Lane a letter proposing a settlement with regard to the liens. Under the proposed settlement, Ferguson would pay Lane an as-yet undetermined sum of money in return for Lane’s release of the liens. Ferguson also proposed that Lane be given a lien against a service station owned by Ferguson to secure the payments.

The parties subsequently began negotiations over the terms of a potential settlement, but Ferguson ultimately discontinued negotiations with Lane. In a letter sent to Lane, Ferguson explained that it was ceasing negotiations because it had come to the conclusion that Lane’s liens were invalid. This lawsuit followed.

1. Lane claims that the trial court erred in granting summary judgment to Ferguson and Premier on its quantum meruit claim. We disagree.

In order to recover under a quantum meruit theory, claimant must show (1) his performance as agent of services valuable to the defendants; (2) either at the request of the defendants or knowingly accepted by the defendants; (3) the defendants’ receipt of which without compensating claimant would be unjust; (4) and claimant’s expectation of compensation at the time of the rendition of the services.

(Citations and punctuation omitted.) Artrac Corp. v. Austin Kelley Advertising, 197 Ga. App. 772, 777 (5) (399 SE2d 529) (1990).

*515 Here, the uncontroverted evidence reflects that Lane had no expectation of payment from Ferguson and Premier at the time it performed work on the rebranding project, and so its quantum meruit claim necessarily fails as a matter of law. See Scott v. Mamari Corp., 242 Ga. App. 455, 458 (2) (530 SE2d 208) (2000); Artrac Corp., 197 Ga. App. at 777 (5). Lane contracted with SEF to provide labor and materials for the rebranding project, not with Ferguson or Premier. Thus, at the time it performed the rebranding work, Lane expected payment from SEF based on the express contract, rather than from some third party. As Golovich’s deposition testimony makes clear, Lane began looking to Ferguson and Premier for payment only after Lane had performed the work and SEF had failed to fulfill its promise to pay under the express contract. “There can be no recovery for services rendered... with no expectation at the time of the rendition that they will be compensated” by the defendant. (Emphasis omitted.) Smith Dev., Inc. v. Flood, 198 Ga. App. 817, 820-821 (3) (b) (403 SE2d 249) (1991). Consequently, Lane cannot establish an essential element of its quantum meruit claim, namely, expectation of compensation from Ferguson and Premier at the time services were rendered.

Nonetheless, Lane argues that Ferguson’s and Premier’s alleged actions in inducing Lane to forbear from enforcing its lien rights creates a genuine issue of fact over whether Lane can recover under the quantum meruit theory of equitable lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farm Credit of Northwest Florida v. Easom Peanut Co.
718 S.E.2d 590 (Court of Appeals of Georgia, 2011)
Harris Ventures, Inc. v. Mallory and Evans, Inc.
662 S.E.2d 874 (Court of Appeals of Georgia, 2008)
Kennesaw Flooring, Inc. v. Rector
662 S.E.2d 808 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
649 S.E.2d 614, 286 Ga. App. 512, 2007 Fulton County D. Rep. 2346, 2007 Ga. App. LEXIS 820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-supply-inc-v-w-h-ferguson-sons-inc-gactapp-2007.