Maycumber v. Wolfe

10 Misc. 2d 464, 171 N.Y.S.2d 44, 1958 N.Y. Misc. LEXIS 3985
CourtNew York Supreme Court
DecidedJanuary 27, 1958
StatusPublished
Cited by3 cases

This text of 10 Misc. 2d 464 (Maycumber v. Wolfe) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maycumber v. Wolfe, 10 Misc. 2d 464, 171 N.Y.S.2d 44, 1958 N.Y. Misc. LEXIS 3985 (N.Y. Super. Ct. 1958).

Opinion

Frank Del Vecchio, J.

This is a motion pursuant to rule 113 of the Rules of Civil Practice for summary judgment dismissing a complaint to foreclose a mechanic’s lien, canceling the lien and discharging a notice of lis pendens filed in connection with the action.

It appears from the pleadings and affidavits submitted on the motion that the defendant Robert W. Wolfe entered into a contract with the defendant Robin Construction Corporation whereby the latter was to build a residence for an agreed price of $21,588, part of which was to be financed by the owner’s procuring an $18,000 mortgage. The sum of $1,000 was paid at the execution of the contract and a part of the balance was to be paid as follows: 10% of the mortgage loan when foundation is in and cellar walls erected, 20% of the mortgage loan when roof boards are on and shingled, 25% of the mortgage loan when the windows, exterior door frames, rough wiring, rough plumbing and heat risers are in, 25% of the mortgage loan when Sheetrock installed, plumbing fixtures and heating installed. It was further provided that: ‘ ‘ The above payments shall be made within 3 days after inspection and approval of work done by the architect Owner and proposed Mort-”.

The contract also provided: “ 6. I. Should the Contractor neglect to execute the work properly or fail to perform any provision of the contract, or fail to continue with the work for a period of ten days, the Owner after seven days’ written notice to the Contractor may without prejudice to any other remedy he may have, make good the deficiencies and may deduct the cost thereof from the final payment due the Contractor, or, at his option, may terminate the contract, holding the Contractor liable for payments made to that time, take possession of all materials, and finish the work by such means as he sees fit, and if the unpaid balance of the contract price exceeds the expense of finishing the work, such excess shall be adjusted between Owner and Contractor, but if such expense exceeds [467]*467such unpaid balance, the Contractor shall be liable for the difference to the Owner. ’ ’

Plaintiffs are subcontractors of the defendant Robin Construction Corporation. Defendant Home Life Insurance Company is the holder of an $18,000 mortgage upon the property in question and defendant Rearwin is a second mortgagee.

Plaintiffs allege that they furnished goods and services at the express request of the general contractor and that defendants Wolfe expressly and impliedly agreed to pay therefor; that the value of the items for which no payment has been made is $1,531.38; that this amount is due from defendants Wolfe; that in accordance with the provisions of the Lien Law they filed a lien for this amount within the time provided therefor which is prior to any interest of the defendants Home Life and Rearwin; that in consideration of the mortgage loan granted by Home Life defendants Wolfe agreed to apply the proceeds therefrom to the cost of the improvement and to hold the same as a trust fund for the payment thereof.

The answer denies that any labor or materials for which payment has not been made were furnished by plaintiffs at the request of defendant owners. As an affirmative defense defendants set up paragraph 6. I. of the construction contract, quoted above, and allege that prior to March 14, 1956 they made payments to the contractor totaling $10,400 which exceeded the value of materials and labor furnished in the construction of the house to that date, that as a result of the general contractor’s failure expeditiously to continue construction of the building as required by the contract the owners exercised their option under paragraph 6.1. of the agreement and notified Robin Construction on March 14, 1956 of their election to terminate the contract in seven days; that defendants thereafter were compelled to and did undertake to complete the house; that defendants ordered labor and materials from plaintiffs for which they agreed to be personally liable and for which payment has been made in full; that plaintiffs were advised that the owners assumed responsibility only for items thereafter furnished at their request or at the request of their new contractor; that in order to complete the residence which Robin Construction had agreed to erect by the contract hereinbefore referred to defendants were compelled to and did expend sums in excess of the contract price of $21,588; that any items for which plaintiffs seek to foreclose a lien were furnished to Robin Construction as contractor under the building contract and that at the time the lien was filed there was no money due or to become due [468]*468on the contract. As a second defense it is alleged that the complaint fails to state a cause of action.

In support of the present motion for summary judgment dismissing the complaint is an affidavit by the defendant Robert Wolfe repeating in substance the allegations of the answer, setting forth the dates and amounts of payments made to the general contractor and stating that after making the last payment on December 11, 1955 the deponent discovered that the moneys which he had paid exceeded the work done on the premises, that he thereafter communicated with the contractor on several occasions and received assurances that the work would proceed but that it became necessary as a result of the contractor’s default to give notice of termination of the contract on March 14, 1956, that in order to complete the residence which Robin Construction had agreed to construct, the deponent was required to and did spend the sum of $1,044.43 in excess of the original contract price of $21,588. Attached to the affidavit are photostatic copies of the building contract, the checks issued to Robin Construction Corporation by defendant Robert Wolfe, letters addressed to the general contractor demanding performance and letters from defendant Robert Wolfe accompanying payments made to plaintiffs for labor and materials furnished after March 22, 1956 identifying the payments and disclaiming liability for the charge of $1,531.58, representing items furnished to Robin Construction Corporation.

This court is of the opinion that the pleadings together with the affidavit and documentary proof submitted by defendants have established a complete defense to the action and the motion should be granted unless plaintiffs by affidavit or other proof show such facts as may be deemed sufficient to raise an issue with respect to the verity or conclusiveness of the proof submitted. (Rules Civ. Prac., rule 113; Schoenfeld v. Modern Silver Linen Supply Co., 279 App. Div. 49.)

Plaintiffs’ affidavits fail to show the existence of any factual issue with regard thereto.

Section 4 of the Lien Law defines the extent of liens and provides in part: “If labor is performed for, or materials furnished to, a contractor or subcontractor for an improvement, the lien shall not be for a sum greater than the sum earned and unpaid on the contract at the time of filing the notice of lien, and any sum subsequently earned thereon. In no case shall the owner be liable to pay by reason of all liens created pursuant to this article a sum greater than the value or agreed [469]*469price of the labor and materials remaining unpaid, at the time of filing notices of such liens ”.

In construing this section, the Court of Appeals said in Van Clief v. Van Vechten (130 N. Y. 571) at page 577:

“ the following rules determine the extent to which a mechanics’ lien, filed by a sub-contractor or a material-man, attaches to the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abe Schild Stone Corp. v. Apostle
41 Misc. 2d 732 (New York Supreme Court, 1964)
Rochester Smelting & Refining Co. v. Republic Chemical Corp.
36 Misc. 2d 194 (New York Supreme Court, 1962)
Lorber v. Eskof Real Estate, Inc.
21 Misc. 2d 308 (New York Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
10 Misc. 2d 464, 171 N.Y.S.2d 44, 1958 N.Y. Misc. LEXIS 3985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maycumber-v-wolfe-nysupct-1958.