Behrer v. McMillan

114 A.D. 450, 100 N.Y.S. 35, 1906 N.Y. App. Div. LEXIS 2123
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 12, 1906
StatusPublished
Cited by9 cases

This text of 114 A.D. 450 (Behrer v. McMillan) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Behrer v. McMillan, 114 A.D. 450, 100 N.Y.S. 35, 1906 N.Y. App. Div. LEXIS 2123 (N.Y. Ct. App. 1906).

Opinion

Laughlin, J.:

Tliis is an action to foreclose a mechanic’s lien. The defendant City and Suburban Homes Company is the only respondent.

The respondent company was the owner of premises at the northeasterly corner of Avenue A and Seventy-eighth street, and it was erecting a tenement building thereon. The contract for the plumbing and gasfitting was let to the defendant McMillan, by whom the plaintiffs were employed as sub-contractors. The plaintiffs sold and delivered to McMillan materials and supplies of the value of $12,224.95, which were used in the performance of his contract with the owner, and were paid on account the sum of $6,278.99. Within ninety days after furnishing the material, and on the 18th day of June, 1903, the plaintiffs duly filed a notice of lien for the balance of $5,945.96 owing to them. This action is brought to foreclose that lien. The entire contract price of the work to be performed by McMillan was $26,190, and it is admitted that he performed extra work of the value of $180, making his aggregate claim $26,370.

The contract provided that the respondent should pay McMillan “ in monthly payments as the work progresses, reserving 15 per cent, until final completion and acceptance of the work by Sturgis & Hill Co.,” and that Sturgis & Hill Company, who were the superintendents, should certify in writing “in each case that the contractor is entitled to such payment.” The contract further provided “that at the time of making the last two payments satisfactory proof shall be furnished to the owner that the land and building upon or for which the work is done are free from all liens or claims on account of said work.”

On the 1st day of June, 1903, the superintendents recommended a partial payment to McMillan of $1,275 under the contract; but this was not ¡3aid nor was any payment made on the contract thereafter. At that time, but for the advance payments, which will be considered presently, there would have been a balance of $7,049.15 unpaid on the contract. A few days after the superintendents recommended the payment of $1,275, the contractor abandoned the work and the owner completed it at a cost of $1,498.94. The contract contained the usual provision that in the event of the failure of the contractor to proceed with due diligence, the owner might [452]*452take possession of the work and complete the same at the expense of the contractor. In these circumstances, if no payment had been made in advance of its being earned under the contract, the owner would have owed the contractor the difference between the said balance of $7,049.15, which would have been unpaid, and $1,498.94, the cost of completion, or $5,730.21, consisting of $3,928.50, the fifteen per cent reserved, $180 for extra work, and $1,621.71, a surplus of work done over the monthly estimates of the superintendents. The owner, however, with a view to expediting the work of McMillan, who was hard pressed for money and seemed to be falling behind in his work which delayed other work, had made further payments from time to time between the monthly payments and before the plaintiffs filed their lien, leaving only $819.34 unpaid at at that time, which was less than the amount necessarily expended by the owner in completing the work.

The plaintiffs were familiar with the provisions of the contract between the owner and McMillan and they relied upon fifteen per cent of the contract being reserved by the owner until final completion. They had discussed the matter with the superintendents who had notice of their claim and promised to protect them and advise them from time to time of the certificates issued for partial payments. The appellants claim that the superintendents were the authorized agents of the owner, as they were supervising the work and no other architect was employed. The plaintiffs, however, Were informed by the superintendents that they had no authority to represent the owner with respect to agreeing that they would be protected in the payments to be made on the contract, and they were advised by the superintendents to communicate directly with the owner on that point, which they failed to do.

The plaintiffs claim that the advance payments wrere made for the purpose of avoiding the provisions of the Mechanics’ Lien Law, and that in determining what amount, if any, was due. and owing by the owner to the contractor at the time the lien was filed or at any time thereafter, such advance payments should be left out of the account. This claim is based on section 7 of the Lien Law (Laws of 1897, chap. 418), wrhich provides as follows: “ Any jiayment by the owner to a contractor upon a contract for the improvement of real property, made prior to the time when, by the [453]*453terms of the contract, such payment becomes due, for the purpose of avoiding the provisions of this article,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maycumber v. Wolfe
10 Misc. 2d 464 (New York Supreme Court, 1958)
Thomas F. Reilly & Co. v. Scheer
125 Misc. 832 (Appellate Terms of the Supreme Court of New York, 1925)
Horton v. Queens County Machinery Corp.
101 Misc. 31 (New York Supreme Court, 1917)
Glens Falls Portland Cement Co. v. Schenectady County Coal Co.
163 A.D. 757 (Appellate Division of the Supreme Court of New York, 1914)
Glens Falls Portland Cement Co. v. Schenectady County Coal Co.
83 Misc. 552 (New York Supreme Court, 1914)
Glen Falls Portland Cement Co. v. Schenectady County Coal Co.
144 N.Y.S. 519 (New York Supreme Court, 1913)
Wagner v. Butler
155 A.D. 425 (Appellate Division of the Supreme Court of New York, 1913)
Parsons v. Curran
149 A.D. 762 (Appellate Division of the Supreme Court of New York, 1912)
Hudson River Blue Stone Co. v. Huntington
143 A.D. 99 (Appellate Division of the Supreme Court of New York, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
114 A.D. 450, 100 N.Y.S. 35, 1906 N.Y. App. Div. LEXIS 2123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/behrer-v-mcmillan-nyappdiv-1906.