Glens Falls Portland Cement Co. v. Schenectady County Coal Co.

83 Misc. 552
CourtNew York Supreme Court
DecidedJanuary 15, 1914
StatusPublished

This text of 83 Misc. 552 (Glens Falls Portland Cement Co. v. Schenectady County Coal Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glens Falls Portland Cement Co. v. Schenectady County Coal Co., 83 Misc. 552 (N.Y. Super. Ct. 1914).

Opinion

Borst, J.

The plaintiff brings this action to foreclose a mechanic’s lien against the defendant Schenectady Coal Company.

On the 16th day of September, 1911, the defendant Booth entered into a contract with the defendant coal company to construct, at different places in the city of Schenectady, N. Y., five reenforced concrete coal pockets according to certain specifications. There was one large pocket, which was to be- completed ready for installation of machinery January 1, 1912, and ready for occupancy a month later; the others are called small pockets and were to be ready for machinery May 1, 1912, and fully completed June 1, 1912. The contract price for the work, $75,000, was to be paid, eighty-five per cent, of the estimated amount of work done and materials purchased during a given month and approved by the architect. The final payment of fifteen per cent, was to be made within thirty-one days after the completion of the work. Before final payment, the contractor was to furnish to the coal company a bond, in the penal sum of $18,750, conditioned that the contractor Booth would keep all the coal pockets in repair for a period of one year from the date of their completion.

Shortly after the making of the contract defendant Booth entered upon the performance of the contract, when it was found that the large coal pocket would require a concrete mat under it. This he constructed at a cost of $7,209.36, which was allowed him as extra work. The construction of this mat delayed the contractor in his work and was treated by the parties as an extension of his time for its completion.

A large part of the work was uncompleted in March, 1912. The coal company had paid to Booth on and prior to March 8,1912, $62,714.36, the cost of the extra work in putting in the concrete mat and on account of [556]*556work clone under the contract. About the latter date, the parties agreed that the coal company should pay to Booth immediately the sum of $19,995, the balance of the contract price, and that Booth should give a bond in the sum of $20,000, conditioned that if he should in all respects comply with and perform the terms and conditions of their contract, except that the time for its performance was extended to June 1,1912, then such bond to be void, otherwise to remain in full force and effect. Booth executed the bond and on March 18, 1912, it was delivered to the coal company. On March 19, 1912, the coal company paid to Booth $15,000 and on March twenty-sixth the further sum of $4,995, the balance of the contract price. Booth continued the work until June 13, 1912, when he filed a petition in bankruptcy. At the time Booth quit work on June 13,1912, the work done under the contract had cost him about $87,000.

The surety company claims to have completed the work at an expense of $8,000, while the coal company contends there was left about $2,000 of work undone.

Prior to the giving of the bond and the advance payments being made, Booth furnished the officers of the coal company at their request a statement purporting to contain the names of those who had furnished labor or materials, with the amounts unpaid incurred on account of the contract, the total of which aggregated $3,959. In this list appear the names of Knapp & Hotchkiss, Collins Bros., Miller Bros., Holland Sand Company, defendants in this action and the Glens Falls Portland Cement Company, the plaintiff, who have filed liens. The plaintiff’s claim in the list, however, appears to be $579.40. The secretary and general manager of the coal company on receiving this list advised with the plaintiff and was informed that the latter’s claim was $1,358.40 against [557]*557Booth. At the same time, he advised the president of the plaintiff company that “ we [coal company] were going to pay him [Booth] in full the next day or two.” In the list Booth furnished the coal company also appears the name of the defendant Frank Anker, who has filed a lien for material furnished after March 26, 1912.

At or prior to the time of the advance payments being made to Booth he advised the officers of the coal company that he would pay the claims included in the list which he had presented.

The coal company had notice at the time of the advance payments that the David Mahoney Company, a defendant lienor in this action, had been furnishing Booth materials for work to be done under the contract and for which that company had not been paid in full.

I am of the opinion that the plaintiff is entitled to enforce its lien by a foreclosure to the amount due on it on the 26th of March, 1912, and that the defendant lienors are entitled to the payment of the amount due on each of their liens on that date.

The defendant coal company had knowledge of the claims of these lienors at that date and made the advance payments with such knowledge. Such payments cannot be said under the circumstances to have been made in good faith. The situation required that the coal company should see that the amounts due and of which it had knowledge when it made the advance payments were paid and not trust to the uncertainty of Booth’s promise to pay them. The fact that some of these liens include claims which occurred after March 26, 1912, and hence in excess of the amounts allowed, does not prevent their enforcement for the amounts due on that date, as it does not appear that any of the liens were filed with fraudulent intent for [558]*558larger amounts than is allowed under this decision. Donovan v. Frazier, 15 App. Div. 521; Gaskell v. Beard, 58 Hun, 101.

Amounts included in the liens, however, which occurred for labor or materials after the 26th of March, 1912, cannot be allowed, nor liens which were filed for labor and materials furnished wholly after that date. Payments by an owner upon- a contract made prior to the time when by the terms of such contract such payment becomes due, for the purpose of avoiding the provisions of the Lien Law, are of no effect as against the lien of a laborer or material-man under such contract created before such payment actually becomes due. Lien Law, § 7. Advance payments, therefore, must have been made for the purpose of avoiding the provisions of the Lien Law to prevent their allowance to the owner as against a lien. It is only when the advance payments have been made with the purpose of avoiding the statute that they are held to be invalid, and the burden of proving that such payments were made in bad faith is on the lienor who asserts it. Hudson River Blue Stone Co. v. Huntington, 143 App. Div. 99, 102.

The provisions of the Lien Law, it has been held, were not intended to prevent an owner from modifying or terminating his contract or facilitating his work by a payment earlier than the contract stipulated. Wagner v. Butler, 155 App. Div. 425.

In the instant case there is no evidence which warrants a finding of bad faith or collusion on the part of the coal company as to the claims for labor and material furnished after March 26,1912. The lienors had the right under the provisions of the Lien Law to see the contract, but so far as the evidence discloses none of them exercised that right. They also had the right to be advised of the amount, if any, unpaid Booth on [559]*559the contract and to he advised as to the condition of the account between the contracting parties. None of them exercised this right, however.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Behrer v. . City and Suburban Homes Company
84 N.E. 1108 (New York Court of Appeals, 1908)
Donovan v. Frazier
15 A.D. 521 (Appellate Division of the Supreme Court of New York, 1897)
Behrer v. McMillan
114 A.D. 450 (Appellate Division of the Supreme Court of New York, 1906)
Hudson River Blue Stone Co. v. Huntington
143 A.D. 99 (Appellate Division of the Supreme Court of New York, 1911)
Wagner v. Butler
155 A.D. 425 (Appellate Division of the Supreme Court of New York, 1913)
Gaskell v. Beard
11 N.Y.S. 399 (New York Supreme Court, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
83 Misc. 552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glens-falls-portland-cement-co-v-schenectady-county-coal-co-nysupct-1914.