Glens Falls Portland Cement Co. v. Schenectady County Coal Co.

163 A.D. 757, 149 N.Y.S. 189, 1914 N.Y. App. Div. LEXIS 7662
CourtAppellate Division of the Supreme Court of the State of New York
DecidedSeptember 9, 1914
StatusPublished
Cited by7 cases

This text of 163 A.D. 757 (Glens Falls Portland Cement Co. v. Schenectady County Coal Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glens Falls Portland Cement Co. v. Schenectady County Coal Co., 163 A.D. 757, 149 N.Y.S. 189, 1914 N.Y. App. Div. LEXIS 7662 (N.Y. Ct. App. 1914).

Opinions

Lyon, J.:

The important question involved in this litigation, which was instituted to foreclose a mechanic’s lien, is whether the final payment by the owner to the contractor was made for the purpose of avoiding the provisions of section 7 of the Lien Law (Consol. Laws, chap. 33; Laws of 1909, chap. 38), which provided that Any payment by the owner to a contractor upon a contract for the improvement of real property, made prior to the time when, by the terms of the contract, such payment becomes due, for the purpose of avoiding the provisions of this article, shall he of no effect as against the lien of a subcontractor, laborer or material man under such contract, created before such payment actually becomes due.” The contract in question was made in September, 1911, and provided for furnishing the materials and performing the labor necessary for the construction by the contractor, Booth, for the Schenectady County Coal Company, the appellant, of five rein[759]*759forced concrete coal pockets, for the sum of $75,500, payments to be made monthly to the extent of eighty-five per cent of the architect’s estimates, the final payment to be made thirty-one days after the completion of the contract, which as to the large pocket was to be February 1, 1912, and as the four small pockets June 1, 1912. The contract provided that the owner might retain out of any payments due or to become due sufficient moneys to indemnify it against any liens chargeable to the contractor; also, that before final payment should be made the contractor should furnish to the owner a bond in the penal sum of $18,750, conditioned that the contractor should keep all the buildings in repair for the period of one year from the time of their completion. Upon undertaking the construction of the large pocket it was found that the laying of a concrete mat as a foundation to the pocket was necessary. This was done at an expense of $7,209.36, which was paid for as extra work, and accounts for the delay in the completion of the contract, but has no bearing upon the issues herein. On March 8, 1912, the appellant had paid Booth on account of the contract, and exclusive of the payment for the extra work of constructing the mat, $55,505, leaving unpaid upon the contract $19,995. The appel lant then proposed to Booth that if he would furnish it a surety bond in the penalty of $20,000 conditioned for the performance by him of the contract, it would pay him in advance of the time specified in the contract the said balance remaining unpaid thereon. March 15, 1912, Booth in acceptance of such proposition furnished said bond, and on March nineteenth the appellant paid him $15,000, and on March twenty-sixth the balance of $4,995 in full of the contract price, and also of the extra work in constructing the concrete mat. Booth continued work upon the pockets until June 13, 1912, when he abandoned the contract, and on June 17, 1912, became a bankrupt, having then expended upon the contract, exclusive of the construction of the mat, $79,960.64. The surety company thereupon -undertook the work of completing the contract and expended $8,000 thereon. Thereafter the appellant, claiming that the surety company had not fully completed the contract, which claim the surety company disputed, expended $2,000 upon the pockets. Commencing June 18, 1912, plaintiff and many [760]*760of the defendants1 filed hens against the coal pocket properties, and in July, 1912, this action was brought to foreclose the hen of the respondent cement company. The court in its decision, which is amply supported by the evidence, excepting in respect of the claim of the respondent cement company, as hereinafter stated, found the facts practically as above stated, and also that during the month of March, 1912, the appellant acquired knowledge that contractor Booth, who was repeatedly asking the appellant for advance payments, was embarrassed financially and in need of money to meet his payrolls; that there were unpaid claims against him for material and labor, and that he had misrepresented to the appellant the amount of the same, stating that the claim of the respondent cement company on account amounted to $579.40, whereas in fact it amounted to $1,358.40; that having constructive notice that he was owing other large sums of money to various other persons who had furnished materials for said contract, and having concluded that the appellant had mistakenly neglected to require of Booth before entering upon the contract the bond required by the contract to be given, although in fact the contract did not require such bond to be given until the time of making the final payment, and knowing that although about $63,000 had been expended by Booth upon the work, it was but about two-thirds completed, and that Booth was liable to lose a very substantial sum in completing the contract, the appellant proposed to Booth to pay him the balance unpaid upon the contract upon his furnishing a bond as before stated. The court also found that the said final payment was made for the purpose of avoiding the provisions of article (sic section) 7 of the Lien Law, and not in good faith, and that the respondent lienors were entitled to be paid for materials furnished and labor performed prior to March 26, 1912, but not subsequent to that date, and that as to such portions of their claims the said payment was not made in bad faith, and that the amounts included in the liens for labor. and materials subsequent to March twenty-sixth were invalid. The court also found that the claim of the respondent cement company was valid to the extent of $1,584.80 and that the claims of defendant lienors were valid to the extent in the aggregate of about $1,800, and [761]*761decreed foreclosure and sale of the properties, and the application of the proceeds to the payment of the liens and costs. From this decision the coal company alone has appealed, and the issue presented is whether the evidence satisfactorily establishes the conclusion arrived at by the trial court that the final payment was made by the appellant to contractor Booth prior to the time when it became due for the purpose of avoiding the provisions of the Lien Law.

The mere fact that the March payments were made to Booth in advance of the time required by the contract, or that the appellant had knowledge of the indebtedness of Booth to the lienors, is not of itself sufficient, under the present Lien Law, to charge the appellant with liability on account of such payments, but in addition thereto it must be shown, in order to avoid the effect of a payment as against a lien,- that the advance payments were made for the purpose of avoiding the provisions of the Lien Law, and the burden of so proving is upon the person asserting it. (Behrer v. McMillan, 114 App. Div. 450; Tommasi v. Archibald, Id. 838; Hudson River Blue Stone Co. v. Huntington, 143 id. 99; Wagner v. Butler, 155 id. 425.)

We think the finding of the trial judge that the payments made March nineteenth and twenty-sixth were made for such purpose was not warranted by the evidence as to the respondent cement company. Prior to making the payment of $15,000 on March nineteenth Ashton, the secretary and manager of the appellant, called Bayle, the president of the cement company, by telephone and asked him about Booth’s indebtedness to the cement company, and said that the appellant was going to pay Booth in full the next day or two. Bayle stated in the conversation that he thought that so far as the indebtedness to the cement company was concerned Booth was all right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

3-G Servs. Ltd. v. SAP V/Atlas 845 WEA Assoc. NF L.L.C.
2018 NY Slip Op 4292 (Appellate Division of the Supreme Court of New York, 2018)
Abe Schild Stone Corp. v. Apostle
41 Misc. 2d 732 (New York Supreme Court, 1964)
Maycumber v. Wolfe
10 Misc. 2d 464 (New York Supreme Court, 1958)
J. W. Van Cott & Son v. Gallon
163 Misc. 914 (Delaware County Court, 1937)
Thomas F. Reilly & Co. v. Scheer
125 Misc. 832 (Appellate Terms of the Supreme Court of New York, 1925)
Rukeyser v. Fountain & Choate, Inc.
185 A.D. 263 (Appellate Division of the Supreme Court of New York, 1918)
Streever Lumber Co. v. Mitchell & Congregation of Sharra Tfille
183 A.D. 129 (Appellate Division of the Supreme Court of New York, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
163 A.D. 757, 149 N.Y.S. 189, 1914 N.Y. App. Div. LEXIS 7662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glens-falls-portland-cement-co-v-schenectady-county-coal-co-nyappdiv-1914.