Mass. Hous. Fin. Agency v. WHITNEY HOUSE ASSOC

638 N.E.2d 1378, 37 Mass. App. Ct. 238
CourtMassachusetts Appeals Court
DecidedSeptember 2, 1994
Docket93-P-1123
StatusPublished
Cited by9 cases

This text of 638 N.E.2d 1378 (Mass. Hous. Fin. Agency v. WHITNEY HOUSE ASSOC) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Hous. Fin. Agency v. WHITNEY HOUSE ASSOC, 638 N.E.2d 1378, 37 Mass. App. Ct. 238 (Mass. Ct. App. 1994).

Opinion

37 Mass. App. Ct. 238 (1994)
638 N.E.2d 1378

MASSACHUSETTS HOUSING FINANCE AGENCY
vs.
WHITNEY HOUSE ASSOCIATES & others.[1]

No. 93-P-1123.

Appeals Court of Massachusetts, Suffolk.

May 13, 1994.
September 2, 1994.

Present: DREBEN, KASS, & FINE, JJ.

Paul W. Shaw for the plaintiff.

Thomas P. Callaghan, Jr., for the defendants.

KASS, J.

We are to decide whether a condition placed by the Massachusetts Housing Finance Agency (MHFA) on the extension of a loan commitment, that the borrower reimburse the MHFA for arbitrage losses, was enforceable. The question was submitted on the MHFA's motion for summary judgment, which a judge of the Superior Court resolved — *239 we think mistakenly — against the MHFA. We are of opinion that the MHFA is entitled to judgment in its favor.[2]

These are the material facts, based on the summary judgment materials. MHFA first issued a commitment for a permanent loan (i.e., a "take out" loan to be disbursed only when construction had been substantially completed) of $2,194,243 to Whitney House Associates (Whitney) in 1981. Whitney is a limited partnership. To fund its commitment obligations to Whitney as well as to other entities, MHFA issued bonds on December 1, 1981, and earmarked $2,194,243 for the Whitney loan.[3] Whitney experienced a variety of difficulties (including a fire in 1982 in the historic building to be made over into fifty dwelling units) such that it neither lined up construction financing nor started construction. On February 23, 1984, MHFA issued a new commitment for the Whitney loan, containing a condition that construction be completed by November 1, 1985.

Delay continued to bedevil Whitney's project. It passed the November 1, 1985, deadline by a wide margin, but MHFA stayed with the undertaking and, on December 18, 1987, "recommitted" to it when Whitney obtained a construction loan commitment from the BayBank/Middlesex (BayBank). That renewed obligation on the part of MHFA was memorialized by a "tri-party agreement" among Whitney, BayBank, and MHFA, which established December 18, 1988, as the new deadline for completion of construction; i.e., the commitment expired on that date if the contemplated improvements were not substantially finished. Once again, Whitney could not make the deadline date and required an extension of the commitment.

*240 By letter dated December 15, 1988, MHFA offered what was roughly a six-month extension (it ran to June 1, 1989). The extension was subject to three conditions, the third of which provided that the "[d]eveloper will be responsible for reimbursing the Agency for any arbitrage losses it incurs from and after January 1, 1989." By arbitrage losses, the MHFA meant the difference between the interest it was paying the bondholders on the $2,194,243 it had set aside for the Whitney project and the amount it could earn on that money on the then current short term market. Prior to the extension of December 15, 1988, MHFA had already sustained arbitrage losses of $488,430. The MHFA letter granting the extension, by its terms, was valid only if signed and returned by Whitney. Salvy J. Sacro, the managing general partner of Whitney, signed his name on the line marked "Accepted by" and added to the right of his signature the typewritten message: "See Attached Letter Dated 12/30/88." In that letter Sacro wrote that his acceptance of the extension had been "signed by me under protest and reserving all my legal rights with respect thereto." He added: "I ask also that since I am being assessed with the arbitrage deficit, that the Agency immediately provide me with a detailed description of how the daily charges are calculated, the plan of investment for the Whitney School bond proceeds, and any other data that would enable me to calculate the arbitrage deficit."

There were four more extensions, for varying periods, the last extending the MHFA commitment to June 12, 1990. On each of these, Sacro placed his signature on the line marked "Accepted by" and added in handwriting or typewriting, "But Accepted With Prejudice." Ultimately, Whitney obtained permanent financing from Everett Savings Bank and MHFA, on April 1, 1991, redeemed the bonds through which it had obtained the funds held for the Whitney project. MHFA demanded reimbursement from Whitney for its arbitrage losses, which came to $188,293. That amount is not in contention; Whitney's position is that it owes nothing at all because: first, it did not accept the arbitrage loss condition in the extension; and, second, the introduction of that *241 condition violated § 4 of the tri-party agreement, which provided: "The Borrower and MHFA agree that the Commitment shall not be amended or modified in any respect whatsoever without the express prior written consent of the Bank."

1. The effect of Sacro's hedged acceptance of the commitment extension. Whitney argues that the "see attached letter" and "but accepted with prejudice" notations over and beside Sacro's signatures denoting Whitney's acceptance of the extension conditions sufficiently varied the terms of MHFA's offer so that Whitney's "acceptance" was not a binding one. A substantial variation in contract terms incident to a purported acceptance is not a binding acceptance but a counter offer. Bank of United States v. Thomson & Kelly Co., 290 Mass. 224, 228 (1935). David J. Tierney, Jr., Inc. v. T. Wellington Carpets, Inc., 8 Mass. App. Ct. 237, 240 (1979). A comment, purported clarification, or expression of dissatisfaction appended to an endorsement of acceptance, however, does not have the same effect. Those are in the category of "grumbling acceptances," acceptances made without enthusiasm but acceptances nonetheless. See Nelson v. Hamlin, 258 Mass. 331, 340 (1927); Costello v. Pet Inc., 17 Mass. App. Ct. 382, 386-387 (1984); Brangier v. Rosenthal, 337 F.2d 952, 954 (9th Cir.1964); Panhandle Eastern Pipeline Co. v. Smith, 637 P.2d 1020, 1023 (Wyo. 1981); 1 Corbin, Contracts § 3.30 (Perillo rev. ed. 1993). The idea is expressed with more formality in the Restatement (Second) of Contracts § 61 (1979): "An acceptance which requests a change or addition to the terms of the offer is not thereby invalidated unless the acceptance is made to depend on an assent to the changed or added terms."[4]

What Sacro wrote on behalf of Whitney was not a counter offer. The first of Whitney's reservations was expressed in a side letter which merely expressed distress about the imposition of the arbitrage condition, not rejection of it, and requested numbers so that Whitney might better know what *242 the cost would be. The "accepted with prejudice," communicated no more, i.e., that Whitney did not like the arbitrage condition, expected to talk more about it, but, grudgingly accepted it in preference to having the MHFA commitment expire. For its part, Whitney accepted the benefit of the extension documents, namely, the extension of the permanent loan commitment, without which the project would have been in dire jeopardy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cp 200 State LLC v. Ciee, Inc.
Massachusetts Appeals Court, 2024
Sea Breeze Estates, LLC v. Jarema
113 N.E.3d 355 (Massachusetts Appeals Court, 2018)
Dennis v. Kaskel
950 N.E.2d 68 (Massachusetts Appeals Court, 2011)
20 Atlantic Avenue Corp. v. Allied Waste Industries, Inc.
482 F. Supp. 2d 60 (D. Massachusetts, 2007)
Haufler v. Zotos
446 Mass. 489 (Massachusetts Supreme Judicial Court, 2006)
Opinion No.
Texas Attorney General Reports, 1999
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1999
Charles v. Kender
646 N.E.2d 411 (Massachusetts Appeals Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
638 N.E.2d 1378, 37 Mass. App. Ct. 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mass-hous-fin-agency-v-whitney-house-assoc-massappct-1994.