David J. Tierney, Jr., Inc. v. T. Wellington Carpets, Inc.

392 N.E.2d 1066, 8 Mass. App. Ct. 237, 1979 Mass. App. LEXIS 919
CourtMassachusetts Appeals Court
DecidedAugust 13, 1979
StatusPublished
Cited by35 cases

This text of 392 N.E.2d 1066 (David J. Tierney, Jr., Inc. v. T. Wellington Carpets, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David J. Tierney, Jr., Inc. v. T. Wellington Carpets, Inc., 392 N.E.2d 1066, 8 Mass. App. Ct. 237, 1979 Mass. App. LEXIS 919 (Mass. Ct. App. 1979).

Opinion

Brown, J.

The plaintiff, David J. Tierney, Jr., Inc. (Tierney), commenced this action in the Superior Court to recover damages resulting from the defendant’s (T. Wellington) alleged failure to perform under a contract for the installation of carpeting. The case was tried before a judge and jury and a verdict was returned in Tierney’s favor in the amount of $12,131 plus interest. T. Wellington appealed, claiming that the judge erred in denying its motion for a directed verdict. 1 In support of its motion, T. *238 Wellington argued that there had been no binding agreement because Tierney’s purported acceptance of the contract terms had been ineffective. We affirm.

The pertinent evidence is summarized. In the summer of 1975 Tierney was preparing to submit a bid for the job of general contractor in the renovation of the Pittsfield High School. Tierney solicited subbids and received from T. Wellington on the morning of September 11, 1975, a subbid for the installation of carpeting at a cost of $22,869. This subbid was substantially lower than any other subbid received by Tierney. 2 David J. Tierney, Jr., the plaintiff’s president, testified that on September 11 he received a telephone call from a person at T. Wellington’s office to whom he mentioned that T. Wellington’s bid appeared to be unusually low. David Tierney also testified that the person with whom he spoke at T. Wellington’s office said he would check to see if the bid was correct and that "he would get back to me by twelve [noon] o’clock” that day. He further testified that he did not hear from T. Wellington prior to 2 p.m. on September 11, 1975, the time designated for submitting bids on the general contract. Tierney submitted its bid which included T. Wellington’s subbid of $22,869 and the general contract was awarded to it later on that same day.

This testimony was contradicted by Ralph A. DeMarco, T. Wellington’s estimator and job coordinator in September, 1975. DeMarco testified that he talked with David Tierney the day before the bidding closed and when informed that T. Wellington’s bid was substantially lower than that of any of the other subbidders, he told Tierney not to use the bid until he heard from him (DeMarco). He further testified that he spoke to a receptionist at Tierney’s the next day and submitted a revised bid.

*239 On September 13,1975, after submitting its bid on the general contract, Tierney received a second subbid from T. Wellington, dated September 12,1975, which listed the cost of the carpeting job at $37,869. On September 19, 1975, Tierney mailed an unexecuted subcontract to T. Wellington in the amount of $22,869. T. Wellington refused to sign the contract of to install the carpeting. Tierney then contracted with Raleigh Carpets for the installation of the carpeting at a cost of $35,000. Tierney brought this action to recover the difference between the amount stated in T. Wellington’s first subbid and the amount paid to Raleigh Carpets.

1. The judge properly submitted to the jury the question whether a contract existed between the parties. "Ordinarily the question whether a contract has been made is one of fact. If the evidence consists only of writings, or is uncontradicted, the question is for the court; otherwise it is for the jury.” Bresky v. Rosenberg, 256 Mass. 66, 75 (1926). See Boston Box Co. v. Shapiro, 249 Mass. 373, 377 (1924). Here there was conflicting testimony on the question whether T. Wellington had withdrawn its first offer prior to any acceptance of it by Tierney. T. Wellington offered testimony which tended to prove that it had with-' drawn its first offer prior to acceptance by Tierney. Testimony favorable to Tierney, on the other hand, tended to prove that the offer had not been withdrawn but remained open when Tierney relied upon it in submitting its bid. Where there is conflicting evidence on the question whether a contract has been created, the question is one for the jury. Beach & Claridge Co. v. American Steam Gauge & Valve Mfg. Co., 202 Mass. 177, 183 (1909). See also Loranger Constr. Corp. v. E.F. Hauserman Co., 376 Mass. 757, 760 (1978) (decided after the briefs were filed in this case but prior to oral argument). The jury could have found that T. Wellington’s offer had not been revoked, that Tierney relied upon it in submitting its bid for the general contract, and that T. Wellington was thereby bound. Id. at 760-761 & n.l. See Restatement (Sec *240 ond) of Contracts § 89B (2) & Illustration 6 (Tent. Drafts Nos. 1-7, 1973).

2. T. Wellington makes the further argument that notwithstanding the conflicting testimony with respect to the oral negotiations (discussed above) Tierney never accepted its offer because its subbid required a particular mode of acceptance which Tierney failed to comply with, and any other form of attempted acceptance was ineffective. 3 T. Wellington thus asserts that Tierney could accept only by delivering to T. Wellington an executed contract on "the standard form provided by Northeast Flooring Contractor’s Association [NEFCA].” There was no reversible error.

The offeror has full control over his offer and may prescribe a particular and exclusive mode of acceptance. To be effective the acceptance must be made in the manner required by the offer. Lewis v. Browning, 130 Mass. 173 (1881). Horne v. Niver, 168 Mass. 4,5 (1897). Lawrence v. Rosenberg, 238 Mass. 138, 141 (1921). See 1 Williston, Contracts § 76 (3d ed. 1957). And if a purported acceptance substantially varies from the terms of the offer it is ineffective, creating no binding agreement. Bank of the United States v. Thomson & Kelly Co., 290 Mass. 224, 228 (1935). See Peretz v. Watson, 3 Mass. App. Ct. 727, 728 (1975). In our view there was sufficient evidence from which the jury could conclude that Tierney accepted the offer of T. Wellington, thereby creating a binding agreement.

Although an offeror, as the creator of a power of acceptance, may demand an exclusive mode of acceptance, we think that other forms of acceptance are ineffective only "if the offeror clearly expresses, in the terms of the com *241 municated offer itself, his intention to exclude all other modes of acceptance.” 1 Corbin, Contracts § 88, at 373 (1963). The language in the bid here is, at best, ambiguous as to whether it required an offeree to respond by tendering an executed contract on an NEFCA form. The bid provides that "the undersigned [T. Wellington’s president] agrees to execute said contract within five working days thereafter on the standard form provided by Northeast Flooring Contractor’s Association.” The bid does not state that the offeree has an obligation to use the NEFCA form.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard L. Wulsin v. Mark F. Murphy.
Massachusetts Appeals Court, 2026
Ritter v. Johnson
D. Massachusetts, 2022
Kagan v. Another
89 N.E.3d 1205 (Massachusetts Appeals Court, 2017)
Burns v. Taylor
34 Mass. L. Rptr. 89 (Massachusetts Superior Court, Suffolk County, 2017)
Olsen v. Johnston
2013 MT 25 (Montana Supreme Court, 2013)
Ghassemi-Tary v. Hami
30 Mass. L. Rptr. 522 (Massachusetts Superior Court, 2012)
Dennis v. Kaskel
950 N.E.2d 68 (Massachusetts Appeals Court, 2011)
Doctor Franklin Perkins School v. King Philip Regional School District
25 Mass. L. Rptr. 549 (Massachusetts Superior Court, 2009)
Cannon v. Cannon
868 N.E.2d 636 (Massachusetts Appeals Court, 2007)
Donahue v. Heritage Property Investment Trust, Inc.
21 Mass. L. Rptr. 488 (Massachusetts Superior Court, 2006)
Twin Fires Investment, LLC v. Morgan Stanley Dean Witter & Co.
445 Mass. 411 (Massachusetts Supreme Judicial Court, 2005)
Gurley v. King
183 S.W.3d 30 (Court of Appeals of Tennessee, 2005)
Casavant v. Norwegian Cruise Line, Ltd.
829 N.E.2d 1171 (Massachusetts Appeals Court, 2005)
Coldwell Banker/Hunneman v. Shostack
818 N.E.2d 1079 (Massachusetts Appeals Court, 2004)
Hunneman Real Estate Corp. v. Norwood Realty, Inc.
765 N.E.2d 800 (Massachusetts Appeals Court, 2002)
Agri-Mark, Inc. v. Niro, Inc.
214 F. Supp. 2d 33 (D. Massachusetts, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
392 N.E.2d 1066, 8 Mass. App. Ct. 237, 1979 Mass. App. LEXIS 919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-j-tierney-jr-inc-v-t-wellington-carpets-inc-massappct-1979.