Richard L. Wulsin v. Mark F. Murphy.

CourtMassachusetts Appeals Court
DecidedApril 1, 2026
Docket25-P-0402
StatusUnpublished

This text of Richard L. Wulsin v. Mark F. Murphy. (Richard L. Wulsin v. Mark F. Murphy.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richard L. Wulsin v. Mark F. Murphy., (Mass. Ct. App. 2026).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

25-P-402

RICHARD L. WULSIN

vs.

MARK F. MURPHY.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiff, Richard L. Wulsin, and the defendant, Mark

F. Murphy, were partners in the law firm of Wulsin & Murphy LLP

from 2005 to 2015. Following Murphy's formal termination of the

partnership, Richard1 filed a single-count complaint against

Murphy for breach of contract to recover a debt Murphy had

incurred during the first few years of the firm's operation.

Murphy denied owing Richard any obligation under the contract

and asserted twenty-two counterclaims and third-party claims

against Richard, Richard's daughter Rachel Wulsin, and a new law

firm that Richard and Rachel had formed, Wulsin Law LLP. A

1Because the case involves several members of the Wulsin family, for clarity we refer to them by their first names. Superior Court judge allowed summary judgment in favor of

Richard on his contract claim and on all but two of Murphy's

counterclaims. Following a bench trial on those two

counterclaims, for breach of fiduciary duty and civil

conspiracy, the judge found for Richard on both. Murphy appeals

from parts of the summary judgment order and from the judgment

after trial. We affirm.

Discussion. 1. Claims resolved on summary judgment. In

2005, Richard and Murphy executed a one-page partnership

agreement, setting forth the basic financial structure of the

firm. The agreement permitted termination of the partnership by

either partner at will with thirty days' written notice to the

other. A side agreement executed simultaneously with the

partnership agreement guaranteed Murphy a minimum income during

the firm's first two years of operation; if Murphy's earned fees

were less than the guaranteed minimum, Murphy was required to

repay the difference to Richard, without interest, "no later

than December 31, 2015." The side agreement referred to this

debt as the "guaranteed payment amount." Although Murphy

disclaims any obligation under the side agreement, the parties

agree that the guaranteed payment amount that accrued under the

side agreement was $308,824.16.

2 The judge granted summary judgment for Richard on his claim

against Murphy under the side agreement, as well as on Murphy's

counterclaims that Richard committed breaches of the partnership

agreement and the side agreement and violated the implied

covenant of good faith and fair dealing.2

"To prevail on a motion for summary judgment, the moving

party bears the burden of 'show[ing] that there is no genuine

issue as to any material fact and that the moving party is

entitled to a judgment as a matter of law' based on the

undisputed facts." Premier Capital, LLC v. KMZ, Inc., 464 Mass.

467, 474 (2013), quoting Mass. R. Civ. P. 56 (c), as amended,

436 Mass. 1404 (2002). "We review a grant of summary judgment

de novo to determine whether, viewing the facts most favorably

to the nonmoving party, the moving party is entitled to judgment

as a matter of law." Huang v. RE/MAX Leading Edge, 101 Mass.

App. Ct. 150, 153 (2022).

a. Side agreement. In response to Richard's claim that

Murphy committed a breach of the side agreement by failing to

repay the guaranteed payment amount on or before December 31,

2015, Murphy countered that the parties had amended the side

2 The judge also allowed Richard's and Rachel and Wulsin LLP's motions for summary judgment as to Murphy's tort, quasicontract, and third-party claims that had survived previous motions to dismiss. Murphy does not challenge the dismissal or allowance of summary judgment on those claims.

3 agreement to extend the repayment date for five to ten years and

that Richard committed a breach of the amended agreement by

demanding payment in January 2016. Whether the side agreement

had been amended hinges on a series of e-mail messages (e-mails)

that Richard and Murphy exchanged between June 19 and July 1,

2014, with the subject line "RE: THE FUTURE" ("future" e-mails).

Although we must view the record in the light most favorable to

Murphy, see Gutierrez v. Board of Managers of Flagship Wharf

Condominium, 100 Mass. App. Ct. 678, 682 (2022), we are not

bound to accept Murphy's interpretation of the "future" e-mails.

"Ordinarily the question whether a contract has been made is one

of fact. If the evidence consists only of writings, or is

uncontradicted, the question is for the court . . . ." David J.

Tierney, Jr., Inc. v. T. Wellington Carpets, Inc., 8 Mass. App.

Ct. 237, 239 (1979), quoting Bresky v. Rosenberg, 256 Mass. 66,

75 (1926).

The "future" e-mails do not amend the side agreement.

Richard began the exchange by expressing his plan to gradually

wind down his practice and his desire to turn over the firm to

Murphy, Rachel, and Richard's son Seth. He then stated, "Over

the next five to ten years, as I slow down, I will draw less,"

and discussed Seth's, Rachel's, and Murphy's anticipated

earnings. After this Richard added, "We need to discuss the

4 guaranteed amount." Murphy responded by expressing his "hope"

that if the firm generated a bonus pool, a "healthy chunk" of

Murphy's bonus could be used to repay Richard, and his further

"hope" that "we can start that this year" -- that is, 2014.

Murphy asked if that "approach" was "ok" with Richard, and

Richard responded, "Yes." While the parties discussed a

possible mechanism for Murphy to pay his debt under the side

agreement, the parties did not discuss the repayment date for

the guaranteed amount, nor did they link the repayment timeline

to Richard's plan for retirement. Indeed, under Murphy's

suggested approach, the guaranteed amount could have been paid

by December 31, 2015, if the bonus pool was sufficient. To the

extent Murphy claims that the "future" e-mails are ambiguous,

"[c]laims of ambiguity . . . do not hold the line against

summary judgment if the documents do not reflect ambiguity on

the point in question, and the party resisting summary judgment

adduces no evidence of ambiguity . . . ." USTrust v. Henley &

Warren Mgt., Inc., 40 Mass. App. Ct. 337, 343 (1996). In the

"future" e-mails, Richard and Murphy began a series of

negotiations about the future structure of the firm, but did not

"reach a 'meeting of the minds' as to the material terms of a

modification." Sea Breeze Estates, LLC v. Jarema, 94 Mass. App.

Ct. 210, 216 (2018).

5 b. Partnership agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
Uproar Co. v. National Broadcasting Co.
81 F.2d 373 (First Circuit, 1936)
Druker v. Roland Wm. Jutras Associates, Inc.
348 N.E.2d 763 (Massachusetts Supreme Judicial Court, 1976)
Gallagher v. Taylor
534 N.E.2d 14 (Massachusetts Appeals Court, 1989)
Tri-City Concrete Co. Inc. v. ALA Construction Co.
179 N.E.2d 319 (Massachusetts Supreme Judicial Court, 1962)
David J. Tierney, Jr., Inc. v. T. Wellington Carpets, Inc.
392 N.E.2d 1066 (Massachusetts Appeals Court, 1979)
Buffalo-Water 1, LLC v. Fidelity Real Estate Company, LLC
111 N.E.3d 266 (Massachusetts Supreme Judicial Court, 2018)
Bresky v. Rosenberg
152 N.E. 347 (Massachusetts Supreme Judicial Court, 1926)
Starr v. Fordham
648 N.E.2d 1261 (Massachusetts Supreme Judicial Court, 1995)
Demoulas v. Demoulas Super Markets, Inc.
677 N.E.2d 159 (Massachusetts Supreme Judicial Court, 1997)
Uno Restaurants, Inc. v. Boston Kenmore Realty Corp.
805 N.E.2d 957 (Massachusetts Supreme Judicial Court, 2004)
Makrigiannis v. Nintendo of America, Inc.
442 Mass. 675 (Massachusetts Supreme Judicial Court, 2004)
Ayash v. Dana-Farber Cancer Institute
822 N.E.2d 667 (Massachusetts Supreme Judicial Court, 2005)
Eigerman v. Putnam Investments, Inc.
877 N.E.2d 1258 (Massachusetts Supreme Judicial Court, 2007)
North American Expositions Co. v. Corcoran
452 Mass. 852 (Massachusetts Supreme Judicial Court, 2009)
Premier Capital, LLC v. KMZ, Inc.
984 N.E.2d 286 (Massachusetts Supreme Judicial Court, 2013)
Merriam v. Demoulas Super Markets, Inc.
464 Mass. 721 (Massachusetts Supreme Judicial Court, 2013)
USTrust v. Henley & Warren Management, Inc.
663 N.E.2d 1238 (Massachusetts Appeals Court, 1996)
Thurlow v. Shaw's Supermarkets, Inc.
727 N.E.2d 532 (Massachusetts Appeals Court, 2000)
Greenberg v. Greenberg
861 N.E.2d 801 (Massachusetts Appeals Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Richard L. Wulsin v. Mark F. Murphy., Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-l-wulsin-v-mark-f-murphy-massappct-2026.