Martin K. Eby Construction Co. v. LAN/STV

350 S.W.3d 675, 2011 Tex. App. LEXIS 6910, 2011 WL 3795695
CourtCourt of Appeals of Texas
DecidedAugust 29, 2011
Docket05-09-00946-CV
StatusPublished
Cited by8 cases

This text of 350 S.W.3d 675 (Martin K. Eby Construction Co. v. LAN/STV) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin K. Eby Construction Co. v. LAN/STV, 350 S.W.3d 675, 2011 Tex. App. LEXIS 6910, 2011 WL 3795695 (Tex. Ct. App. 2011).

Opinion

OPINION

Opinion By

Justice LANG.

Martin K. Eby Construction Co. (Eby) appeals from a trial court’s judgment following a jury trial. In the trial court, Eby sought damages for delays and increased costs it alleged were caused by LAN/STV, a Joint Venture of Lockwood, Andrews & Newnam, Inc. and STV, Incorporated’s (LAN/STV) negligent misrepresentations regarding construction plans prepared for a light rail line project by LAN/STV and others. Eby raises three issues contending the trial court erred by: (1) failing to disregard the findings that Eby was negligent and responsible for fifteen percent of the damages; (2) failing to disregard the findings that Dallas Area Rapid Transit (DART) was negligent and responsible for forty percent of the damages; and (3) failing to disregard the finding that LAN/ STV was responsible for forty-five percent of the damages. We decide against Eby on its issues.

LAN/STV filed a cross-appeal. It asserts five issues contending: (1) it enjoys derivative sovereign immunity as a contractor for DART and cannot be held ha-ble for tort claims; (2) the evidence is legally insufficient to support the damages award; (3) the trial court erred in not applying the economic loss rule to bar Eby from recovering damages; (4) the trial court erred in not allowing a settlement credit; and (5) the evidence is legally insufficient to support the jury finding of negligent misrepresentation. We decide against LAN/STV on its issues. The trial court’s judgment is affirmed.

I. Factual and Procedural Background

DART awarded Eby a contract to construct a portion of the DART rail line in Dallas known as the NW-1A project. Eby *679 based its bid upon documents submitted by DART. LAN/STV was primarily responsible for the preparation of the plans and specifications in the bid documents. After construction began, Eby encountered numerous delays and increased costs. Eby attributed those problems to inaccuracies in the bid documents.

Eby sued DART in United States District Court for breach of contract and misrepresentation. They settled for $4,700,000. Eby then sued LAN/STV in the trial court below alleging claims for negligence and negligent misrepresentation. The terms of the settlement between Eby and DART were presented as evidence by both Eby and LAN/STV at trial. The jury found LAN/STV made negligent misrepresentations and awarded damages in the amount of $5,000,000. The jury also found negligence and percentages of responsibility for the damages as follows: Eby — fifteen percent; DART — forty percent; and LAN/STV — forty-five percent. The trial court awarded Eby forty-five percent of the $5,000,000 or $2,250,000. This appeal timely followed.

A. Eby’s Appeal

Eby contends the trial court erred in failing to disregard the jury findings that both it and DART were negligent and responsible for a portion of the damages and that LAN/STV was responsible for only a portion of the damages. 1

*680 1. Eby’s Negligence

In its first issue, Eby contends the trial court erred by failing to disregard the findings that Eby was negligent and responsible for fifteen percent of the damages. It asserts these findings are legally immaterial to the controlling findings in jury questions one and two that LAN/STV made negligent misrepresentations that proximately caused damages, there is no evidence to support a negligence finding as to Eby, and any negligence on Eby’s part could not have been a proximate cause of the original incident. 2

A trial court may disregard a jury finding only if it is not supported by evidence or if the issue is immaterial. See Spencer v. Eagle Star. Ins. Co. of Am., 876 S.W.2d 154,- 157 (Tex.1994). A jury question that is mandated by law cannot be immaterial. See Se. Pipe Line Co. v. Tichacek, 997 S.W.2d 166, 172 (Tex.1999). A finding may be rendered immaterial by other findings if there is a fatal conflict. See Beltran v. Brookshire Grocery Co., — S.W.3d—,—, 2011 WL 1797629 (Tex.App.-Dallas, 2011, no pet. h.). For example, a finding that a party’s negligence was the sole cause of an accident renders the comparative fault finding of the other party immaterial. Am. Jet, Inc. v. Leyendecker, 683 S.W.2d 121, 127 (Tex.App.-San Antonio 1984, no writ).

Section 33.003 requires the trier of fact to determine the percentage of responsibility for each claimant, defendant, settling person, and responsible third party who “caus[ed] or eontribut[ed] to cause in any way the harm for which recovery of damages is sought....” See Tex. Civ. Prac. & Rem.Code Ann. § 33.003(a)(1) (West 2008). This statutory mandate is not discretionary. F.F.P. Operating Partners, L.P. v. Duenez, 237 S.W.3d 680, 694 (Tex.2007).

Eby contends the jury’s findings that Eby was negligent and responsible for fifteen percent of the damages are immaterial because of the “unique” way its negligent misrepresentation theory was submitted to the jury in question two. The jury was asked specifically to find the amount of damages, if any, that were proximately caused by the negligent misrepresentation of LAN/STV. Eby argues that because of the requirement of a spe *681 cific causal link between the $5,000,000 damages award and LAN/STV’s negligent misrepresentation, it is immaterial that any negligence on its part “caused or contributed to cause those damages.” (emphasis in original). According to Eby, the term “damages in question” used in question three, refers to the part of the total damages it claimed of approximately $13,800,000 that was not proximately caused by LAN/STV’s negligent misrepresentation. However, we cannot agree with Eby that these findings are immaterial and should have been disregarded by the trial court.

The term “damages in question” is not defined in the charge and no other damages are addressed in the charge other than in question three. The charge does not direct the jury to somehow distinguish between the negligent misrepresentation of LAN/STV and the negligence of Eby, DART, and Parsons inquired about in questions three, four, and five. Nor do we find any submission of a suggested charge by Eby to instruct the jury on how to make such differentiation. Certainly, the reference in questions three, four, and five about the “damages in question” gives no hint there is a difference to be assigned to damages proximately caused by LAN/ STV’s negligent misrepresentation, i.e., $5,000,000, and the “damages in question,” if any, caused by Eby’s negligence. Further, the definition of proximate cause provided to the jury instructed that there could be more than one proximate cause. Eby did not object to that instruction nor did it offer any variation to it. Indeed, the jury found more than one proximate cause in its responses to questions three and four.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
350 S.W.3d 675, 2011 Tex. App. LEXIS 6910, 2011 WL 3795695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-k-eby-construction-co-v-lanstv-texapp-2011.