Marsch v. Williams

23 Cal. App. 4th 238, 28 Cal. Rptr. 2d 402, 94 Daily Journal DAR 3399, 94 Cal. Daily Op. Serv. 1875, 1994 Cal. App. LEXIS 222
California Court of Appeal·Decided March 15, 1994·No. D017954·Published·Cited by 51 cases

Opinion

Opinion

BENKE, J.

In this appeal, plaintiff Nicolas Marsch III 1 appeals a judgment confirming an arbitration award. The award was made by an arbitration panel (Panel) at the conclusion of an arbitration proceeding between Marsch and defendant Ronald Williams, 2 both of whom are partners in the Horizon Properties general partnership. The award appointed one of the Panel members as receiver to oversee the dissolution of the partnership and the sale of the partnership property. Marsch contends: (1) the award should be vacated because the Panel exceeded its powers by failing to apply California law to the dispute; and (2) the award should be corrected to require that the receiver be sworn and bonded as mandated by Code of Civil Procedure section 567. For the reasons set forth below, we affirm the judgment in part, reverse in part and remand with instructions.

Factual Background

Horizon

In January 1985 Marsch formed a California corporation called New Horizon Group, Inc. (New Horizon), and purchased a 400-acre parcel of land *241 in Rancho Santa Fe California for $11.4 million. Additional purchases by New Horizon and its successor increased the size of the parcel to 541 acres. Marsch planned to build a golf course and develop approximately 240 luxury home sites on the land.

Later in 1985 Marsch realized the New Horizon project needed a financial partner with substantial assets. Marsch was introduced to Williams, a wealthy man with many years’ experience in real estate and golf course development. After discussing the project with Williams, Marsch agreed to sell Williams 50 percent of New Horizon’s stock for $25,000. According to Marsch, Williams also promised to arrange all further financing for the project.

In December 1986 Marsch and Williams agreed to reorganize the New Horizon project. They created the Horizon Properties general partnership (Horizon) by way of a December 18, 1986, partnership agreement. This agreement, which became effective January 1, 1987, contained a binding arbitration clause. 3 In February 1987 Marsch and Williams dissolved New Horizon and transferred its assets to Horizon. Marsch and Williams were the only partners of Horizon and each owned a 50 percent share in the partnership.

Marsch/Williams Dispute

The early years of Marsch and Williams’s association were marked by good faith and cooperation. However, in 1988 Marsch and Williams began to have disagreements about how to best proceed with the Horizon project. Marsch alleges it was during this time that Williams conceived a scheme to steal Marsch’s interest in Horizon. The essence of this alleged scheme was for Williams to place such financial pressure on Marsch that he would sell his interest to Williams at Williams’s price. Marsch claims Williams pursued this objective on two fronts: (1) Williams delayed funding and otherwise obstructed the Horizon project so as to make timely completion impossible, *242 and (2) Williams undermined two other partnerships he and Marsch controlled by refusing to cooperate in the sale or refinancing of buildings in La Jolla the partnerships owned. 4

Throughout 1988 and 1989 the relationship between Marsch and Williams continued to deteriorate. The Horizon project was delayed as the partners disagreed on, among other matters, the development schedule, the sale and pricing of lots, the amount of funding necessary for the project and the use of partnership funds by Marsch. Work on Horizon stopped in February 1990.

Procedural Background

On July 17, 1990, Marsch filed a complaint against Williams, alleging fraud, breach of fiduciary duty, intentional infliction of emotional distress and other causes of action based upon Williams’s conduct in Horizon. On September 19, 1990, Williams petitioned the trial court for an order to compel arbitration and stay litigation based upon section 6.04 of the Horizon partnership agreement. The trial court granted Williams’s petition and entered an order compelling arbitration on November 27, 1990. The arbitration proceeding took place in Palo Alto, California, before a 3-member panel, took 10 months to complete and consumed 88 trial days.

The Panel issued its award and reasoned opinion of award on June 18, 1992. It found that “[Williams] decided that he wanted to buy out [Marsch] on [Williams’s] terms, that the way to accomplish this was to keep [Marsch] in a financially strapped situation, and therefore [Williams] determined to delay completion in order to avoid selling lots and memberships. Such conduct is a breach of [Williams’s] fiduciary duty.” The Panel found this breach of fiduciary duty inflicted nearly $48.5 million worth of damage on Horizon and ordered Williams to pay Horizon that amount. However the Panel permitted Williams to offset this judgment against the $70 million Horizon owed Williams and the Williams Trust. The Panel also appointed one of its members as receiver to supervise the sale of the Horizon property and the dissolution of the partnership.

Over Marsch’s objection, the trial court confirmed the arbitration award. Following the trial court’s ruling, Marsch submitted a proposed judgment which required the receiver be sworn and bonded. The trial court rejected Marsch’s proposed judgment and entered an alternative proposed by Williams. Williams’s alternative did not require an oath or bond from the receiver.

*243 Marsch filed a timely notice of appeal from the order confirming the arbitration.

Issue on Appeal

On appeal Marsch contends the arbitration award should be set aside because he believes he, rather than the receiver, should have been given possession of the corporation’s assets.

Discussion

I

California has a well-established policy favoring arbitration as a speedy and relatively inexpensive means of settling disputes. (Ericksen, Arbuthnot, McCarthy, Kearney & Walsh, Inc. v. 100 Oak Street (1983) 35 Cal.3d 312, 322 [197 Cal.Rptr. 581, 673 P.2d 251].) To support this policy and encourage parties to settle their disputes through arbitration, it is essential arbitration judgments be both binding and final. Thus, as a general rule courts will indulge every reasonable intendment to give effect to arbitration proceedings. (Knass v. Blue Cross of California (1991) 228 Cal.App.3d 390, 393 [279 Cal.Rptr. 124]; Pacific Inv. Co. v. Townsend (1976) 58 Cal.App.3d 1, 9 [129 Cal.Rptr. 489].) This rule conforms with the parties’ expectations when agreeing to submit to arbitration: “This expectation of finality strongly informs the parties’ choice of an arbitral forum over a judicial one. The arbitrator’s decision should be the end, not the beginning, of the dispute.” (Moncharsh v. Hetty & Blase

Free access — add to your briefcase to read the full text and ask questions with AI

Marsch v. Williams, 23 Cal. App. 4th 238, 28 Cal. Rptr. 2d 402, 94 Daily Journal DAR 3399, 94 Cal. Daily Op. Serv. 1875, 1994 Cal. App. LEXIS 222 (Cal. Ct. App. 1994).

23 Cal. App. 4th 238 (Marsch v. Williams) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Linderoth v. Relola, Inc. CA1/1
California Court of Appeal, 2026
Koenig v. Centralia Limited Investors
California Court of Appeal, 2025
Rivas v. Dynamic Nursing Services CA2/1
California Court of Appeal, 2025
Liberty Law Office v. The Bloom Firm CA1/1
California Court of Appeal, 2024
Espinoza v. Super. Ct.
California Court of Appeal, 2022
Jiang v. Ferreira CA2/7
California Court of Appeal, 2022
Estate of Boldon CA2/2
California Court of Appeal, 2021
Razuki v. Malan CA4/1
California Court of Appeal, 2021
SingerLewak LLP v. Gantman
California Court of Appeal, 2015
Singerlewak, LLP v. Gantman CA2/8
241 Cal. App. 4th 610 (California Court of Appeal, 2015)
Amkor Technology v. Tessera CA1/3
California Court of Appeal, 2014
O'Rourke v. Lunde and The Housing Group Limited Partnership
2014 VT 88 (Supreme Court of Vermont, 2014)
Gardyn v. Sangha CA1/3
California Court of Appeal, 2014
Hoso Foods, Inc. v. Columbus Club, Inc.
190 Cal. App. 4th 881 (California Court of Appeal, 2010)
Toal v. Tardif
178 Cal. App. 4th 1208 (California Court of Appeal, 2009)
Cable Connection, Inc. v. DirecTV, Inc.
190 P.3d 586 (California Supreme Court, 2008)
Luce, Forward, Hamilton, & Scripps v. Koch
75 Cal. Rptr. 3d 869 (California Court of Appeal, 2008)