Neal Electric Corp. v. Clark Construction Group CA4/1

CourtCalifornia Court of Appeal
DecidedOctober 17, 2023
DocketD082217
StatusUnpublished

This text of Neal Electric Corp. v. Clark Construction Group CA4/1 (Neal Electric Corp. v. Clark Construction Group CA4/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neal Electric Corp. v. Clark Construction Group CA4/1, (Cal. Ct. App. 2023).

Opinion

Filed 10/17/23 Neal Electric Corp. v. Clark Construction Group CA4/1 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

NEAL ELECTRIC CORPORATION, D082217

Plaintiff and Appellant,

v. (Super. Ct. No. PSC1805941)

CLARK CONSTRUCTION GROUP - CA, L.P.,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of County of Riverside, Ronald L. Johnson (Retired judge of the San Diego Super. Ct. assigned by the Chief Justice pursuant to art. VI, § 6 of the Cal. Const.) and Randolph Rogers, Judges. Affirmed. Procopio, Cory, Hargreaves & Savitch, Kendra J. Hall and Jeff S. Hood for Plaintiff and Appellant. Pillsbury Winthrop Shaw Pittman, Elaine Y. Lee, John R. Heisse, Daniel H. Bromberg, and Deborah B. Baum for Defendant and Respondent. Neal Electric Corporation, a subcontractor, appeals from a judgment enforcing an arbitration award in its dispute with general contractor Clark Construction Group. Neal petitioned the court to vacate the award on the ground that it exceeded its authority by holding a virtual hearing, unfairly refused to postpone the hearing, and failed to issue a complete and final award. On appeal, Neal again argues that the arbitration panel exceeded its authority in holding a virtual hearing and in refusing to issue a complete and final award. We are unpersuaded by Neal’s claims of error and affirm the judgment. FACTUAL AND PROCEDURAL BACKGROUND A. Background Information 1. Neal and Clark’s Subcontract Agreement This dispute arises out of the construction of the East County Detention Center (Project) located in Indio, California. Clark contracted with the Project owner, County of Riverside (County), to serve as the general contractor for the Project. In May 2015, Clark entered into a Subcontract Agreement (Subcontract) with Neal to perform electrical work on the Project. The Subcontract includes several provisions concerning the settlement of disputes, including an arbitration clause. For any disputes not settled pursuant to the Subcontract’s procedures, the Subcontract provides: To the extent not resolved under Article 11.b above, any dispute between Clark and Subcontractor shall, at Clark’s sole option, be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. If Clark elects to arbitrate, then the arbitration shall be in Riverside, CA.

From the start of the Project, Clark and its subcontractors encountered numerous problems with the plans provided by the Project’s architect, HOK Group, Inc. (HOK). As a result, Clark and its subcontractors submitted thousands of inquiries, which severely delayed their work and increased their costs.

2 2. Termination of Subcontract In 2018, Clark demanded that Neal increase its workforce to complete the existing work. When Neal refused to do so, Clark terminated the Subcontract. Neal sued Clark for wrongful termination and Clark successfully petitioned the court to compel arbitration per the terms of the Subcontract. In November 2018, Clark filed an arbitration demand with the American Arbitration Association to recover the cost of completing and correcting Neal’s work. In response, Neal reasserted its breach of contract claim against Clark. B. Arbitration Proceeding 1. Scheduling Orders In August 2019, the arbitration panel chair issued a scheduling order, which required the parties to file detailed statements of claims and defenses. The order further stated that, after service of these statements, “no party may further amend its claims or defenses (other than changes in monetary amounts allowed by Rule R-6) without leave of the Arbitrator.” It set the evidentiary hearing schedule “at a location to be determined” and further provided that “[t]estimony will be presented in person absent extraordinary circumstances.” In December 2019, the panel chair issued a second scheduling order noting that the parties had served their detailed statements of claims and defenses. The order stated that no amendments beyond those dealing with monetary amounts would be allowed without leave of the panel chair. It confirmed the evidentiary hearing dates and protocol and reiterated that “[t]estimony will be presented in person absent extraordinary circumstances.” It also set an August 2020 deadline for counsel to meet and confer and notify the panel of the proposed location for the evidentiary hearing. 3 2. Virtual Hearing In light of the COVID-19 pandemic, which began in early 2020, the panel advised the parties that they would be required to follow a detailed protocol if the hearings were to proceed in person. During a telephonic status conference in August 2020, the panel advised the parties that “it was now likely to require that the hearings be conducted virtually—i.e., by videoconference—in light of the continuing risks posed by the pandemic.” Neal prepared a written objection to proceeding virtually and requested a six- month continuance. Neal’s objection stated: The Subcontract provides that the arbitration shall be conducted in Riverside, California and the parties have not agreed to change the location of the hearing. The Subcontract does not contemplate, nor does Neal agree to, an entirely virtual arbitration proceeding.

Neal argued that an in-person hearing was “imperative” due to “the scope and complexity of the dispute and amount of evidence that will be presented.” Neal asserted that “[a] virtual proceeding introduces a host of issues that will substantially impact the proceeding and result in prejudice,” including “internet connectivity issues,” distractions, and difficulties presenting exhibits and examining witnesses. It also argued that a continuance was needed because “critical authorized discovery remains pending,” as two-thirds of the parties had not produced subpoenaed documents, and Neal was facing objections from third parties regarding three deposition subpoenas. Neal acknowledged that it was “not possible to secure a facility that can guarantee accommodations that would meet the needs of the hearing due to governmental restrictions currently being imposed as a result of the COVID-

4 19 pandemic.” Neal’s objection stated that it would consider a virtual hearing if a continuance was granted: If, after a reasonable continuance and after obtaining the necessary discovery at issue, it remains infeasible to proceed in- person, Neal will re-evaluate proceeding virtually. Neal simply wants a reasonable opportunity to proceed in person as contemplated by the parties. Neal proposes the scheduling of a new hearing date be deferred to January 2021 and, based upon the level of restriction at such time, and status of the discovery disputes, a reasonable hearing date can be scheduled.

Clark opposed Neal’s request, arguing that the panel had authority to order a virtual hearing. Clark also argued that any prejudice caused by a virtual hearing would be borne equally by both parties. Clark also acknowledged that “no one expected that we would be in the middle of a pandemic, and that everyone would prefer an in-person hearing where witnesses could testify at a normal distance, without masks, and all attendees could come and go as they please.” The panel denied Neal’s request for a continuance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moncharsh v. Heily & Blase
832 P.2d 899 (California Supreme Court, 1992)
Ulene v. Murray Millman of California, Inc.
346 P.2d 494 (California Court of Appeal, 1959)
Safeway Stores, Inc. v. Brotherhood of Teamsters
83 Cal. App. 3d 430 (California Court of Appeal, 1978)
East San Bernardino County Water District v. City of San Bernardino
33 Cal. App. 3d 942 (California Court of Appeal, 1973)
Rodrigues v. Keller
113 Cal. App. 3d 838 (California Court of Appeal, 1980)
M. B. Zaninovich, Inc. v. Teamster Farmworker Local Union 946
86 Cal. App. 3d 410 (California Court of Appeal, 1978)
Banks v. Milwaukee Ins. Co.
247 Cal. App. 2d 34 (California Court of Appeal, 1966)
Jones v. Humanscale Corp.
29 Cal. Rptr. 3d 881 (California Court of Appeal, 2005)
County of San Diego v. State of California
164 Cal. App. 4th 580 (California Court of Appeal, 2008)
Marsch v. Williams
23 Cal. App. 4th 238 (California Court of Appeal, 1994)
Boghos v. Certain Underwriters at Lloyd's of London
115 P.3d 68 (California Supreme Court, 2005)
Mangini v. R. J. Reynolds Tobacco Co.
875 P.2d 73 (California Supreme Court, 1994)
Advanced Micro Devices, Inc. v. Intel Corp.
885 P.2d 994 (California Supreme Court, 1994)
Gueyffier v. Ann Summers, Ltd.
184 P.3d 739 (California Supreme Court, 2008)
Cooper v. Lavely & Singer Professional Corp.
230 Cal. App. 4th 1 (California Court of Appeal, 2014)
Emerald Aero, LLC v. Kaplan
9 Cal. App. 5th 1125 (California Court of Appeal, 2017)
Heimlich v. Shivji
441 P.3d 857 (California Supreme Court, 2019)
Morris v. Zuckerman
446 P.2d 1000 (California Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
Neal Electric Corp. v. Clark Construction Group CA4/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neal-electric-corp-v-clark-construction-group-ca41-calctapp-2023.