Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al

District Court, D. Hawaii·Decided June 26, 2020·No. 1:18-cv-00211·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF HAWAII MARISCO, LTD., a Hawaii ) CIVIL NO. 18-00211 SOM/RT Corporation, ) ) Plaintiff, ) ORDER GRANTING IN PART AND ) DENYING IN PART PLAINTIFF’S vs. ) MOTION FOR JUDGMENT ON THE ) PLEADINGS (ECF NO. 78) AND GL ENGINEERING & CONSTRUCTION ) MOTION FOR SUMMARY JUDGMENT PTE., LTD, a Singapore ) (ECF NO. 76) Corporation; ) ) LIM SING TIAN; and ) ) RAYMOND GAN, ) ) Defendants. ) _____________________________ ) ORDER GRANTING IN PART AND DENYING IN PART PLAINTIFF'S MOTION FOR JUDGMENT ON THE PLEADINGS (ECF NO. 78) AND MOTION FOR SUMMARY JUDGMENT (ECF NO. 76) I. INTRODUCTION. The Complaint in this matter alleges that Plaintiff Marisco, Ltd., hired Defendant GL Engineering & Construction, Pte., Ltd. (“GLEC”), to construct and deliver a floating dry dock. Marisco alleges that the construction company’s principals, Defendants Lim Sing Tian and Raymond Gan, misrepresented their experience and ability with respect to constructing dry docks. Marisco says GLEC delivered the dry dock late, unfinished, and not according to specifications. On February 18, 2020, GLEC filed the Counterclaim at issue on these motions. Tian and Gan are not Counterclaim Plaintiffs. GLEC alleges that Marisco failed to pay the full amount due under their agreement and failed to pay for change orders. See ECF No. 65-1. Before the court are two motions filed by Marisco challenging the Counterclaim. In its first motion, Marisco initially seeks judgment on the pleadings with respect to Count II of the Counterclaim, which alleges a breach of the implied covenant of good faith and fair dealing. At the hearing, the parties agreed that Count II is unnecessary, provided it is read as already part of the breach of contract claim asserted in Count I. Accordingly, to the extent Marisco seeks judgment on the pleadings with respect to Count II, its motion is granted with the understanding that GLEC may proceed with the underlying claim asserted in Count II as part of the breach of contract claim asserted in Count I. The first motion also seeks judgment on the pleadings with respect to Count III of the Counterclaim, which asserts unjust enrichment, arguing that GLEC cannot maintain an equitable claim when there is an adequate remedy at law. This court denies this part of the motion because GLEC may plead alternative claims. At this point, it is not clear that GLEC does have an adequate remedy at law. Of course, GLEC may not recover duplicative damages, and the equitable unjust enrichment claim is viable only if there is no adequate remedy at law. In its second motion, Marisco moves to compel GLEC to arbitrate the matters raised in the Counterclaim. This court

2 agrees that GLEC must arbitrate Count I of the Counterclaim, including the contractual breach of good faith and fair dealing claim that is now subsumed within Count I, to the extent Count I relates to Change Order #s 1, 9, 10, and 11. The court therefore refers that portion of Count I to arbitration. However, because the court does not have before it evidence of an agreement that GLEC must arbitrate its remaining breach of contract claim that Marisco failed to pay $148,400 due on the final progress payment, that portion of Count I remains with this court. The entirety of the unjust enrichment claim in Count III also remains with this court. The court denies Marisco’s request for summary judgment with respect to its failure to pay $148,400 on the final progress payment. Material questions of fact exist. (The motion does not separately seek summary judgment with respect to the unjust enrichment claim.) II. BACKGROUND. On January 20, 2016, Marisco and GLEC entered into a Dry Dock Construction Agreement. See ECF No. 77-2 (copy of Dry Dock Construction Agreement). GLEC agreed to build and perform all the work required by the dry dock plans. Agreement ¶ 1.1, ECF No. 77-2, PageID # 1709. The completed dry dock was supposed

to be delivered by September 30, 2016. See Agreement ¶ 3.1, PageID # 1712. If GLEC failed to deliver the completed dry dock 3 by that date, GLEC was to pay Marisco $700 for every day of delay. See Agreement ¶ 3.6, PageID # 1713. There is no dispute that GLEC failed to deliver the dry dock on time. In fact, GLEC concedes that it did not deliver the dry dock until May 3, 2017. See Decl. of Ping Han Lee ¶ 44, ECF No. 96-1, PageID # 2306. Marisco says that delivery was 212 days late. See Decl. of Fred Anawati ¶ 28, ECF No. 77-1, PageID # 1701. Marisco claims $148,400 in liquidated damages ($700 per day times 212 days). Id. Under the terms of the Agreement, Marisco agreed to pay a total of $9 million for the construction and delivery of the dry dock ($1.8 million due immediately, followed by eight progress payments of $900,000 each). Each progress payment came due when an additional 12.5% of the construction of the dry dock was completed. Agreement ¶ 2.3(a), PageID # 1711. Marisco says that the final progress payment billed by GLEC was for $751,600, which, because of the liquidated damages provision, was $148,400

less than the $900,000 set forth in the Agreement. See Anawati Decl. ¶ 27, ECF No. 77-1, PageID # 1701; ECF No. 77-15, PageID # 1866 (April 24, 2017, Final Progress Claim of $751,600). GLEC says that immediately before it sent the $751,600 invoice, it had sent a $900,000 final progress payment invoice to Marisco. See Lee Decl. ¶ 46, ECF No. 96-1, PageID # 2306; ECF No. 96-22, PageID # 2445 (April 24, 2017, Final Progress Claim of 4 $900,000). GLEC says Marisco rejected this invoice and forced GLEC to issue a new invoice for $751,600 if GLEC wanted any portion of the final payment. See Lee Decl. ¶ 47, PageID # 2307. On May 15, 2020, GLEC’s attorney sent Marisco’s attorney a letter stating that acceptance of the $751,600 payment was not a waiver of GLEC’s right to collect the remaining $148,400 allegedly owed on the final progress payment. See ECF No. 96-24, PageID # 2450. GLEC attached a bill for the remaining $148,400. ECF No. 96-24, PageID # 2454. On April 24, 2017, GLEC billed Marisco $201,768.99 in connection with Change Order # 1, which Marisco has refused to pay. See ECF No. 77-18; Counterclaim ¶ 44, ECF No. 65-1, PageID # 1431. Marisco says that GLEC agreed in section 6.2 of the Agreement to charge Marisco $2847 per ton for the first 700 tons of steel, and to charge the same price for any steel exceeding 700 tons. See Anawati Decl. ¶ 31, ECF No. 77-1, PageID # 1702. Marisco says Change Order # 1 improperly included an increase of

$170.82 per ton in the cost of steel, bringing the cost to $3017.82 per ton for both the first 700 tons used and the extra 483.01 tons used. Marisco says it paid for all of the steel at the original agreed-upon price of $2847 per ton, meaning that what is in dispute is the increase in price. Id. ¶ 32. The numbers are close, but they do not add up exactly (1,183.01 tons x $170.82 per ton = $202,081.77). The bill for $201,768.99 is 5 $312.78 less than the mathematical total of $202,081.77. At the hearing, the parties indicated that the amounts were close enough that they had not bothered making any correction to the amount in controversy. GLEC says that Fred Anawati, on behalf of Marisco, approved an invoice for $1,577,211.24 relating to Change Order # 1, which included the increased price of $3017.82 per ton of steel. See Lee Decl. ¶ 28, ECF No. 96-1, PageID # 2302 (“Marisco agreed to the increased rate for all steel acquired, including the initial 700 tons”); ECF No. 96-12, PageID # 2428 (copy of invoice for Change Order # 1 dated April 10, 2017, with a signature that may be Anawati’s on it after the word “Approved”). While the signature on the “Approved” Change Order # 1 appears to be on behalf of Marisco, the record does not clearly establish that it is Anawati’s signature. Compare signature on ECF No. 96- 12, PageID # 2428 with signatures on Agreement, ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al, (D. Haw. 2020).

Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al (Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mastrobuono v. Shearson Lehman Hutton, Inc.
514 U.S. 52 (Supreme Court, 1995)
Cafasso v. General Dynamics C4 Systems, Inc.
637 F.3d 1047 (Ninth Circuit, 2011)
Dan Beraha, M.D. v. Baxter Health Care Corporation
956 F.2d 1436 (Seventh Circuit, 1992)
Jose Chavez v. James Ziglar
683 F.3d 1102 (Ninth Circuit, 2012)
Ikeoka v. Kong
386 P.2d 855 (Hawaii Supreme Court, 1963)
Hawaii Leasing v. Klein
698 P.2d 309 (Hawaii Intermediate Court of Appeals, 1985)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)
Best Place, Inc. v. Penn America Insurance Co.
920 P.2d 334 (Hawaii Supreme Court, 1996)
Small v. Badenhop
701 P.2d 647 (Hawaii Supreme Court, 1985)
Cox v. Ocean View Hotel Corp.
533 F.3d 1114 (Ninth Circuit, 2008)
Fleming v. Pickard
581 F.3d 922 (Ninth Circuit, 2009)
Kahili, Inc. v. Yamamoto
506 P.2d 9 (Hawaii Supreme Court, 1973)
Francis v. Lee Enterprises, Inc.
971 P.2d 707 (Hawaii Supreme Court, 1999)
Lowden v. T-MOBILE USA, INC.
512 F.3d 1213 (Ninth Circuit, 2008)