Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al

District Court, D. Hawaii·Decided June 25, 2020·No. 1:18-cv-00211·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF HAWAII MARISCO, LTD., a Hawaii ) CIVIL NO. 18-00211 SOM/RT Corporation, ) ) Plaintiff, ) ORDER DENYING GLEC’S MOTION ) FOR PARTIAL SUMMARY JUDGMENT vs. ) WITH RESPECT TO SECTION 4.4 ) OF THE AGREEMENT GL ENGINEERING & CONSTRUCTION ) PTE., LTD, a Singapore ) Corporation; ) ) LIM SING TIAN; and ) ) RAYMOND GAN, ) ) Defendants. ) _____________________________ ) ORDER DENYING GLEC'S MOTION FOR PARTIAL SUMMARY JUDGMENT WITH RESPECT TO SECTION 4.4 OF THE AGREEMENT I. INTRODUCTION. This case concerns the construction and sale of a dry dock by Defendant GL Engineering & Construction, Pte., Ltd., and its representatives Defendants Lim Sing Tian and Raymond Gan (collectively, “GLEC”), to Plaintiff Marisco, Ltd. GLEC seeks partial summary judgment in the form of a ruling that section 4.4 of the Dry Dock Construction Agreement imposes a limitation on any damages that Marisco might seek for alleged breach of warranty or breach of contract. There is no dispute as to the validity of section 4.4. Nor do the parties dispute that section 4.4, if enforced, might limit Marisco’s remedies with respect to breach of warranty and breach of contract claims against GLEC. What is in dispute is whether the limitation contained in section 4.4 has been triggered. This court, finding that there are factual disputes that cannot be resolved on this motion, denies GLEC’s motion. II. FACTUAL BACKGROUND. On January 20, 2016, Marisco and GLEC entered into the “Dry Dock Construction Agreement.” See ECF No. 95-3 (copy of Dry Dock Construction Agreement). The Agreement designated Marisco as the “Owner” and GLEC as the “Contractor.” ECF No. 95-3, PageID # 2132. GLEC agreed to construct the dry dock in Batam, Indonesia, and to deliver the dry dock to Marisco’s towing agent in Indonesia by September 20, 2016, so it could then be towed to Hawaii. Id. ¶¶ 1.5, 3.1, 4.3 PageID #s 2133, 2135, 2137. GLEC warranted that, when the dry dock was delivered to the towing agent in Indonesia, it would be free from defects in workmanship, would conform to specifications, would be in a finished condition, and would be fit for its intended purpose. Agreement ¶ 4.1, ECF No. 95-3, PageID #S 2136-37. Section 4.3 agreement, which bears the heading “Warranty Period,” provides:

(a) the Dry Dock will be delivered to Owner’s towing agent in Indonesia and the Dry Dock will be towed to Owner’s facility in the State of Hawaii; and (b) once the Dry Dock arrives at the Owner’s facility [in Hawaii] Owner will complete construction of the Dry Dock. Within 100 days after Contractor receives notice from Owner that the construction of the Dry Dock is completed, Contractor must travel to the Owner’s 2 facility in Hawaii, for the final inspection of the Dry Dock. . . . At the final inspection, the Parties will inspect and test the Dry Dock, including the assessment of the water tightness and integrity of the Dry Dock’s wing walls and Dry Dock’s compartments. Contractor has no responsibility for any claim by Owner under Sections 4.1 and 4.2 that Contractor does not receive in writing from Owner within 30 days of that final inspection. ECF No. 95-3, PageID # 2137. Section 4.4 of the Agreement required GLEC to promptly correct nonconforming work after being notified of any defect and after GLEC had inspected the work to confirm the defect: If Owner notifies Contractor in accordance with Section 4.3 of any claim covered under Sections 4.1 and 4.2 (which notice must set forth with specificity the Dry Dock affected and the nature and location of the defect), and upon inspection thereafter by Contractor at which time Contractor confirms that the warranted defect set out in the notice in fact exists, then Contractor promptly must correct the nonconforming work by making repairs or replacements, without expense to Owner; or, if it is not practical to have Contractor make the repairs or replacements, then Owner may have the repairs or replacements made by a third party, and, in that event, Contractor must reimburse Owner an amount equivalent to the lesser of (a) the amount Contractor would have expended at its own yard at Contractor’s then-prevailing rates or (b) the amount actually expended by Owner; provided, however, that in no event is Contractor to be liable to Owner for any amount in excess of the cost of repairs or replacements as specified above. Id., PageID # 2137. 3 According to Ping An Lee, finance manager for GLEC, Marisco’s representatives, including Alfred Anawati, inspected the dry dock on May 3, 2017, at the Batam Yard in Indonesia. See Decl. of Ping An Lee ¶ 2, ECF No. 74-1, PageID # 1501. Later that same day, the dry dock began a 26-day dry tow from Indonesia to Hawaii that cost approximately $2 million and that involved placing the dry dock on top of a larger vessel. Id. ¶¶ 3-8, PageID #s 1501-02. Under section 4.3, once the dry dock was in Hawaii, Marisco was to complete construction. ECF No. 95-3, PageID # 2137. There is no dispute that GLEC lacked the facilities, personnel, and necessary license to conduct dry dock repair work in the United States. Id. ¶¶ 9-10, PageID #s 1502. The dry dock arrived in Hawaii on June 3, 2017. Several days later, on June 9, 2017, Marisco sent a letter to GLEC, indicating that Marisco had begun inspecting the dry dock and had found many defective items. While the letter did not purport to identify all the defects, it detailed some of them and included photographs and other records that Marisco said showed certain defects. The same letter asked GLEC to immediately send

representatives to Hawaii “to inspect the Dry Dock subject to GLEC’s agreement with Marisco Ltd., and to decide with Marisco on how best and quickest to bring the Dry Dock into compliance with

4 GLEC’s Warranties under Section 4.1.” See ECF No. 74-5, PageID #s 1606. Marisco sent similar letters to GLEC on June 16 and June 23, 2017. See ECF No. 95-5, PageID # 2183. On June 28, 2017, GLEC responded that it was sending its project manager, Thet Lwin, and engineer, Han Lin Kyaw (whose surname appears to be “Han”), to Hawaii to inspect the dry dock. Lwin and Han needed visas to travel to Hawaii, see ECF No. 95-6, PageID # 2186, which they did in July 2017. See Decl. of Fred Anawati ¶ 20, ECF No. 95-1, PageID # 2116. Han attested to defects in the dry dock in front of a notary public. Id.; ECF No. 95-7. Ping Han Lee of GLEC says that Han was threatened and

coerced into attesting to defects. See Decl. of Ping Han Lee ¶ 21, ECF No. 103-1, PageID # 2869. On August 11, 2017, Marisco wrote a letter to GLEC in which Marisco noted that GLEC had not communicated with Marisco since the July 2017 inspection. Marisco told GLEC that Marisco needed to have the dry dock operational by August 27, 2017, given Marisco’s contractual obligations with third parties. Marisco stated that it had not yet completed its own work on the dry dock and would soon give GLEC a written notice of completion that would trigger GLEC’s obligation under section 4.3 of the Agreement to travel to Hawaii for a final inspection. ECF No. 103-6, PageID #s 2889-92. 5 In its letter of August 11, 2017, Marisco listed $1,977,747.90 in expenses incurred for repairs and because of delay. ECF No. 103-6, PageID #s 2889-93. On August 16, 2017, Marisco sent GLEC an email detailing some of the work it had done to address its warranty claims. See ECF No. 103-7, PagID # 2895. It is not clear that Marisco was entitled to fix any alleged defect before GLEC had inspected the dry dock with respect to such a defect and had had a chance to address it. Of course, according to Marisco, GLEC had failed to respond to Marisco’s requests to inspect and fix the defects identified by Marisco. On August 27, 2017, GLEC wrote to Marisco, acknowledging Marisco’s desire for a fully operational dry dock by that date.

Free access — add to your briefcase to read the full text and ask questions with AI

Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al, (D. Haw. 2020).

Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al (Marisco, Ltd. v. GL Engineering & Construction Pte. Ltd,et al) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Kutkowski v. Princeville Prince Golf Course, LLC.
300 P.3d 1009 (Hawaii Supreme Court, 2013)
Brown v. KFC National Management Co.
921 P.2d 146 (Hawaii Supreme Court, 1996)
Ikeoka v. Kong
386 P.2d 855 (Hawaii Supreme Court, 1963)
Earl M. Jorgensen Co. v. Mark Construction, Inc.
540 P.2d 978 (Hawaii Supreme Court, 1975)
Kahili, Inc. v. Yamamoto
506 P.2d 9 (Hawaii Supreme Court, 1973)
Kalinowski v. Yeh
847 P.2d 673 (Hawaii Intermediate Court of Appeals, 1993)
Joshua Munroe v. Continental Western Insurance
735 F.3d 783 (Eighth Circuit, 2013)