Main Line Paving Co. v. Board of Education

725 F. Supp. 1349, 1989 U.S. Dist. LEXIS 14187, 1989 WL 143266
CourtDistrict Court, E.D. Pennsylvania
DecidedNovember 29, 1989
DocketCiv. A. 89-0821
StatusPublished
Cited by10 cases

This text of 725 F. Supp. 1349 (Main Line Paving Co. v. Board of Education) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Main Line Paving Co. v. Board of Education, 725 F. Supp. 1349, 1989 U.S. Dist. LEXIS 14187, 1989 WL 143266 (E.D. Pa. 1989).

Opinion

MEMORANDUM OPINION AND ORDER

WEINER, District Judge.

I. Introduction.

Main Line Paving Co., Inc. and its only stockholder Bernard A. Faggioli (collective *1351 ly “Main Line”) have brought this suit against the Board of Education of the School District of Philadelphia (the “Board”), to raise a facial challenge to the Board’s minority business enterprise set aside requirements for construction contracts. Main Line was an unsuccessful bidder on a School District contract to demolish an abandoned school building. The matter was originally filed in the Court of Common Pleas for Philadelphia County and removed to this court by the Board. Main Line’s amended complaint, brought pursuant to 42 U.S.C. § 1983, avers that the Board’s bidding and contracting policies violate the Equal Protection Clause of the Fourteenth Amendment. Before the court are the parties’ cross motions for summary judgment, based upon a joint stipulation of facts. For the reasons which follow, we find the Board’s minority set aside program to be a violation of the Equal Protection Clause. We therefore grant the motion of the plaintiff.

In its complaint Main Line alleges that the Board’s affirmative action requirements and the so called Addendum No. 1 attached to the subject contract, together with the Board’s standard operating procedure, are violative of the Equal Protection Clause because they create race and gender conscious classifications, assigning favored status to minorities and women in the award of construction contracts. As such, Main Line argues the set aside program fails to pass the strict scrutiny requirement for these types of benign classifications recently announced by the United States Supreme Court in City of Richmond v. J.A. Croson Co., — U.S. -, 109 S.Ct. 706, 102 L.Ed.2d 854 (1989). The Board responds that Main Line, as a mere unsuccessful bidder, has no cause of action; that since the contract has already been rebid and let, the question is moot; and that the plaintiffs have no standing to bring this action. We will first recount the stipulated facts, set out the standard for deciding motions for summary judgment, then address the arguments regarding standing and mootness, each of which are threshold issues.

II. Stipulated Facts.

The parties have submitted the issue on the following joint stipulation of facts:

1. This is an action by plaintiffs, Main Line Paving Co., Inc. and Bernard A. Fag-gioli, against the Board of Education, School District of Philadelphia, for injunc-tive relief, a declaratory Judgment [sic] and damages, pursuant to the Fourteenth Amendment to the United States Constitution and 42 U.S.C. § 1983, arising out of the failure of the Board ... to award Main Line ... a contract for Specification B-91 of 1988/1989 for the demolition and related work on the former R.L. Wright School.

2. Plaintiffs’ prayers for temporary and permanent injunctive relief in the form of an order prohibiting the Board from opening the bids and from awarding the contract to any one other than Main Line are moot.

3. Bernard A. Faggioli is a citizen and taxpayer of the Commonwealth of Pennsylvania, and is President of Main Line.

4. Main Line ... is a Pennsylvania corporation ...

5. The School District ... is a political subdivision under 53 P.S. section 1-101 et seq. [sic] and 351 Pa.Code section 12.12.100 et seq. ... The Board ... is its policy-making body.

6. At all relevant times, the Board was acting under color of state law.

7. 1

8. Main Line is a construction contractor qualified to bid on construction contracts let by the Board.

9. On or about November 22, 1988, the Board advertised for bids on Specification No. B-91 of 1988/1989 (the “contract”) for the demolition and asbestos removal at the former R.L. Wright School.

*1352 10. Asbestos removal and demolition of the school, hauling away debris, and back-filling, all together, made up all the work called for in the contract sought by plaintiffs, except restoration of the site to grade.

11. There exist in the construction industry reports known as “Dodge Reports”, which are published showing public entities that are advertising for bids on construction projects, the bid opening date and other information relevant to a contractor preparing and submitting bids on public contracts.

12. Main Line obtained a Dodge Report dated November 22, 1988 on the Board’s Specification ... which showed a bid opening date of December 6, 1988.

13. Main Line subsequently obtained a Dodge Report dated November 30, 1988 ... which showed a bid opening date of December 13, 1988.

14. Main Line obtained from the Board the necessary specifications to submit a bid for the Contract, prior to December 6, 1988.

15. Prospective bidders were advised of the Board's affirmative action policy by way of a document entitled Addendum No. 1 (Revised) of the General Conditions, which was attached to and made part of the contract’s specifications.

16. Addendum No. 1 had as its subject matter “School District’s Policy on Subcontracting Opportunities for Minority/Women-Owned Businesses.” Its provisions included the following:

NOTICE
This is to advise you of a change in the School District of Philadelphia bidding conditions as stated below. The following paragraph is [sic] 2 hereby a requirement of this bid specification and you are cautioned THAT FAILURE TO COMPLY AT THE TIME OF BID SUBMISSION WILL LEAD TO REJECTION OF YOUR BID.
* *< * * * *
Bids over $200,000
Bids for construction, reconstruction, repairs, maintenance of work of any nature, including the installation of plumbing, heating and ventilation, or lighting systems in excess of $200,000 must include a minority and women-owned business subcontracting plan guaranteeing:
(a) No less than fifteen percent (15%) of the value of the award to minority-owned businesses; and
(b) No less than ten percent (10%) of the value of the award to women-owned businesses.
* * * * * *
For bids over $200,000, the following may also apply:
(a) Bidders which are certified minority-owned businesses may satisfy the fifteen percent (15%) MBE participation by listing themselves on the subcontracting plan. Ten percent (10%) women-owned participation is still required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
725 F. Supp. 1349, 1989 U.S. Dist. LEXIS 14187, 1989 WL 143266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/main-line-paving-co-v-board-of-education-paed-1989.