Madison County Bd. of Commrs. v. Bell, Unpublished Decision (3-26-2007)

2007 Ohio 1373
CourtOhio Court of Appeals
DecidedMarch 26, 2007
DocketNo. CA2005-09-036.
StatusUnpublished
Cited by16 cases

This text of 2007 Ohio 1373 (Madison County Bd. of Commrs. v. Bell, Unpublished Decision (3-26-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Madison County Bd. of Commrs. v. Bell, Unpublished Decision (3-26-2007), 2007 Ohio 1373 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Defendants-appellants, Greg and Marcia Bell, appeal a decision of the Madison County Court of Common Pleas granting judgment in favor of plaintiff-appellee, the Madison County Board of Commissioners, in an action involving appropriation of real estate.1 We affirm. *Page 2

{¶ 2} Appellants live in the Choctaw Lake Subdivision, north of London, Ohio. This subdivision consists of about 880 homes and surrounds the state-owned Choctaw Lake. Under direction from the Ohio Environmental Protection Agency, appellee resolved to build a centralized wastewater collection and treatment system to handle all of the sewage needs for the subdivision. To successfully connect each property to the new sewer system, appellee needed to obtain a construction easement from each property owner. Once the construction of the sewer system was complete, these easements would convert to maintenance easements. Because the expenses of the project, including easement acquisition costs, were ultimately to be borne by the property owners, the value of the easements was determined to be $1.

{¶ 3} Public meetings were held to discuss issues related to the project, including the easements. Appellant Greg Bell attended one of these meetings. A generic easement was prepared and sent to all of the subdivision property owners. On December 2, 2002, appellee passed a resolution authorizing Madison County Prosecutor Stephen Pronai to file appropriation cases against the 50 property owners (including appellants) who had not signed the easement.

{¶ 4} On February 3, 2003, appellee filed a complaint against appellants which (1) sought to appropriate appellants' property for a construction easement to later be converted to a maintenance easement; (2) sought to appropriate a fee simple interest in appellants' property; (3) alleged disagreement with appellants as to the amount of compensation to be paid to them; and (4) valued the property to be appropriated at $1. In lieu of an answer, appellants defended by filing several motions and moving for admissions, production of documents, and interrogatories.

{¶ 5} On October 20, 2003, appellants filed an answer, a class action counterclaim, and a third-party complaint against third-party defendant, Prosecutor Pronai. That same day, *Page 3 appellants also moved for summary judgment. A week later, on the same day the trial court granted appellee 14 days to respond to appellants' summary judgment motion, appellants filed an amended answer, an amended class action counterclaim, an amended third-party complaint, a counterclaim, and a complaint for declaratory judgment and injunctive relief, which essentially extended appellants' various claims to other third parties.

{¶ 6} Numerous other pleadings by all of the parties involved followed. Most of those pleadings are clearly set forth in the trial court's decisions of July 29, 2004 and October 27, 2004, which the trial court incorporated by reference as though fully set out in its July 6, 2005 decision. It is undisputed that what started as a rather uncomplicated appropriation action by appellee to obtain a temporary construction easement and a permanent maintenance easement on appellants' property turned into a complex "procedural morass" (according to appellee) or "procedural swamp" (according to appellants).

{¶ 7} Over the course of the proceedings, the trial court overruled most of appellants' motions. In addition, appellants' motion for appointment of a special prosecutor, original action for prohibition against the trial court, and affidavit of disqualification against the trial judge were all denied or dismissed. As relevant to this appeal, the trial court held a necessity hearing under R.C. Chapter 163, allowed appellee to amend its complaint to abandon the fee simple interest demand, granted summary judgment in favor of appellee, and granted the motions for dismissal or summary judgment of the third-party defendants.

{¶ 8} On July 11, 2005, a jury found that appellee was entitled to an easement on appellants' property, but found that appellants were not entitled to any compensation for the easement. By judgment entry filed on August 29, 2005, the trial court granted judgment in favor of appellee. This appeal follows in which appellants raise 13 assignments of error.

{¶ 9} We note that the trial court's numerous, well-reasoned decisions rendered throughout the course of this litigation suitably addressed the majority of the arguments raised *Page 4 by appellants on appeal. Where appropriate, we shall adopt those portions of the trial court decisions disposing of the issues raised in appellants' assignments of error.

{¶ 10} Assignment of Error No. 1:

{¶ 11} "THE TRIAL COURT ERRED TO THE PREJUDICE OF DEFENDANT-APPELLANTS [SIC] BY ENTERING INTO AN A PRIORI, EX PARTE AGREEMENT WITH THE MADISON COUNTY PROSECUTOR TO DELAY SUBSTANTIVE ACTION FOR SIX MONTHS AFTER THE COMPLAINT WAS FILED."

{¶ 12} Appellants allege that the trial court and Prosecutor Pronai entered into an ex parte agreement to delay the litigation for six months subsequent to the filing of the complaint. In support, appellants cite the trial court's July 29, 2004 decision, in which the court stated:

{¶ 13} "Prosecutor Pronai immediately began systematically to negotiate with landowners in an attempt to secure easements. A decision was made to review the cases at 6 months, consider the status of pending cases and begin trial assignments to be integrated into the trial docket."

{¶ 14} According to appellants, this constitutes an admission that the prosecution and the court entered into an ex parte agreement to delay the case, in violation of both the Code of Judicial Conduct and the Code of Professional Responsibility.

{¶ 15} Initially, we note that the Ohio Supreme Court has exclusive jurisdiction to determine violations of attorney disciplinary rules. See Section 2(B)(1)(g), Article IV, Ohio Constitution. See, also, FredSiegel Co. v. Arter Hadden, 85 Ohio St.3d 171, 178, 1999- Ohio-260. All grievances involving alleged misconduct by attorneys and judges are to be brought and disposed of in accordance with the provisions of Rule 5 of the Supreme Court Rules for the Government of the Bar of Ohio. Gov.Bar R. 5(2)(A). Thus, the proper method by which to raise such allegations is by a grievance filed before the Board of Commissioners on Grievances and Discipline of the Supreme Court, not by a brief filed before this appeals *Page 5 court. See, generally, Gov.Bar R. 5.

{¶ 16} Even were the issue properly before this court, nothing in the July 29, 2004 trial court decision states that the court and Prosecutor Pronai engaged in an ex parte communication regarding how the case was to proceed. Appellants simply made an assumption that is not supported by the record. Further, in light of the large number of appropriation cases filed by the prosecutor, we find no prejudicial error in the trial court's decision to review the cases at six months or in the delay to the case.

{¶ 17}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry Cty. Bd. of Commrs. v. Rettig
2020 Ohio 2787 (Ohio Court of Appeals, 2020)
Nationwide Agribusiness Ins. Co. v. Heidler
2019 Ohio 4311 (Ohio Court of Appeals, 2019)
Highfield v. Pietrykowski
2016 Ohio 5695 (Ohio Court of Appeals, 2016)
State v. Cline
2014 Ohio 4503 (Ohio Court of Appeals, 2014)
State Ex Rel. Bell v. Madison County Board of Commissioners
2014 Ohio 1564 (Ohio Supreme Court, 2014)
State ex rel. Bell v. Pfeiffer
2012 Ohio 54 (Ohio Supreme Court, 2012)
Dublin v. Wirchanski
2011 Ohio 2461 (Ohio Court of Appeals, 2011)
State v. Gaines
951 N.E.2d 814 (Ohio Court of Appeals, 2011)
Battelle Memorial Institute v. Big Darby Creek Shooting Range
948 N.E.2d 1019 (Ohio Court of Appeals, 2011)
Paulsen v. Dennis
2010 Ohio 4579 (Ohio Court of Appeals, 2010)
Roberts v. Clinton Cty. Aud., Ca2007-03-012 (2-11-2008)
2008 Ohio 535 (Ohio Court of Appeals, 2008)
Smith v. Village of Waynesville, Ca2007-03-039 (2-11-2008)
2008 Ohio 522 (Ohio Court of Appeals, 2008)
Smith v. Village of Waynesville, Ca2007-03-039 (12-28-2007)
2007 Ohio 7069 (Ohio Court of Appeals, 2007)
Simmons v. Trumbull County Engineer, 2007-T-0049 (12-14-2007)
2007 Ohio 6735 (Ohio Court of Appeals, 2007)
In Matter of Estate of Romero, Ca2006-06-015 (5-7-2007)
2007 Ohio 2157 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 1373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/madison-county-bd-of-commrs-v-bell-unpublished-decision-3-26-2007-ohioctapp-2007.