Henry Cty. Bd. of Commrs. v. Rettig

2020 Ohio 2787, 154 N.E.3d 449
CourtOhio Court of Appeals
DecidedMay 4, 2020
Docket7-19-11
StatusPublished

This text of 2020 Ohio 2787 (Henry Cty. Bd. of Commrs. v. Rettig) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry Cty. Bd. of Commrs. v. Rettig, 2020 Ohio 2787, 154 N.E.3d 449 (Ohio Ct. App. 2020).

Opinion

[Cite as Henry Cty. Bd. of Commrs. v. Rettig, 2020-Ohio-2787.]

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT HENRY COUNTY

BOARD OF HENRY COUNTY COMMISSIONERS,

PLAINTIFF-APPELLEE, CASE NO. 7-19-11

v.

TODD RETTIG, ET AL., OPINION

DEFENDANTS-APPELLANTS.

Appeal from Henry County Common Pleas Court Trial Court No. 18 CV 0142

Judgment Affirmed

Date of Decision: May 4, 2020

APPEARANCES:

Zachary J. Murry for Appellant

Katie L. Nelson for Appellee Case No. 7-19-11

SHAW, P.J.

{¶1} Defendants-appellants, Todd Rettig1 and Paula Rettig (collectively,

“the Rettigs”), bring this appeal from the September 10, 2019, judgment of the

Henry County Common Pleas Court granting the motion for summary judgment

filed by the Board of Henry County Commissioners (“the Board”) in an eminent

domain action. As a result of granting the Board’s motion for summary judgment,

the trial court dismissed the Rettigs’ counterclaims against the Board.

{¶2} The Rettigs also appeal the September 10, 2019, judgment of the Henry

County Common Pleas Court denying the Rettigs’ motion to dismiss the

appropriation action on the basis that the appropriation petition was “defective.” On

appeal, the Rettigs argue that the trial court erred by granting the Board’s summary

judgment motion and by denying the Rettigs’ motion to dismiss.

Background

{¶3} The City of Napoleon, located in Henry County, is physically divided

into northern and southern portions by the Maumee River. As early as 2001 or 2002,

there were discussions regarding building an additional bridge across the river. In

2003, the City of Napoleon approved a “comprehensive master plan,” which

recommended the creation of a second river crossing via a new bridge as a critical

infrastructure improvement.

1 Todd Rettig is the custodian for Kyle Rettig under the Ohio Transfers to Minors Act.

-2- Case No. 7-19-11

{¶4} A study was commissioned for a potential “New Maumee River

Crossing Project” and a final report was issued on March 11, 2009. The report

identified numerous reasons why a new bridge across the Maumee River was

needed:

First, there is a need to provide a more direct transportation corridor between the two designated industrial development areas that are located on the east side of the city, both north and south of the Maumee River. Secondly, an option is needed to improve emergency response times when traffic is disrupted on the existing bridge that crosses the river on SR 108 in the city. Thirdly, although the majority of Napoleon’s developed areas are located on the north side of the river, the south side of the river contains the largest single employer in Napoleon, the world’s largest Campbell’s Soup plant, which employs an average of 1,200 people. The Henry County fairgrounds, several small businesses, and residential areas also exist on the south side of the Maumee River.

(Def.’s Ex. D at 1-1). The report also stated that having only a single river crossing

at SR 108 caused significant traffic congestion and delays in downtown Napoleon

during peak traffic periods.2 This included heavy truck traffic going through

downtown Napoleon.

{¶5} The report identified four potential sites for a new bridge over the

Maumee River. Early cost estimates for building a bridge were between $14.5-16.5

million. A “no-build” alternative was also considered, which evaluated the potential

of meeting the city’s needs through various measures short of building a new bridge.

2 The record indicates that there were additional river crossings outside of town, but they did not alleviate the problems.

-3- Case No. 7-19-11

{¶6} After the report was complete on the project, a “feasibility” study was

undertaken, which analyzed traffic and crashes in the area in order to determine the

necessity of the bridge project and, if the bridge project was necessary, which of the

potential build sites would be the best. The feasibility study was completed in 2013.

{¶7} The completed feasibility study determined that a “no-build” option

would not address the traffic and access concerns. (Schumm Depo at 48). The four

initial build sites were narrowed to two options, and the final recommendation from

the feasibility study was that the new bridge be an extension of “Industrial Drive.”

The extension of Industrial Drive would connect Riverview Avenue on the south

side of the Maumee River via a new bridge to State Route 110 on the north side of

the Maumee River.

{¶8} During the time that the feasibility study was being conducted, there

were attempts by the Henry County Engineer to secure funding for the bridge

through means separate from the City of Napoleon and Henry County such as

through state and federal grants and private donations. Applications were made to

the Transportation Review Advisory Committee (“TRAC”), a funding agency from

the State of Ohio, which accepted applications approximately once per year. Initial

applications to TRAC were denied, and TRAC provided feedback that securing

some private funding would make the application more attractive. (Dahl Depo. at

28); (Schumm Depo at 59, 119). Financial assistance for the bridge was then sought

-4- Case No. 7-19-11

from the area’s largest employer, Campbell’s, first in the amount of $1.5 million.

Although Campbell’s never agreed to contribute $1.5 million, Campbell’s did

eventually agree to contribute over $400,000. Then, on the sixth attempt at applying

for a TRAC grant, the application was approved and additional funding was

received for the bridge project.3 (Schumm Depo. at 22). However, applications

through a federal grant program called “TIGER” were rejected on the three

occasions that they were submitted.

{¶9} Over the next several years bridge and road plans were submitted and

completed. In the meantime, additional funding was still sought through various

sources. Once plans for the road and bridge had essentially been finalized, initial

work proceeded on the bridge such as clearing trees and acquiring property. A deal

was made with one property owner, but a deal could not be made with the Rettigs,

who owned property along the river.

{¶10} On November 6, 2018, the Board met in regular session and passed a

resolution indicating that the “New River Bridge Project” was proceeding and that

construction would require the acquisition of .7857 acres of property from the

Rettigs. The resolution indicated that the acquisition of the Rettigs’ property was

necessary, and that they had been unable to negotiate a fair price.

3 Regarding the difficulty of acquiring a grant through TRAC, a Henry County Commissioner testified that TRAC had something like “$25 billion worth of good projects and $12 billion to spend.” (Hastedt Depo at 31).

-5- Case No. 7-19-11

{¶11} An appraisal of the property was conducted by Martin & Wood

Appraisal Group, LTD. The appraisal valued the .7857 acres of riverfront property

proposed to be taken at $27,500. In addition, the appraisal valued damage to the

remaining parcel the Rettigs would still own at $6,900, for a total compensation

award of $34,400.

{¶12} Subsequently the Board filed a Petition for Appropriation of the

Rettigs’ property on November 16, 2018. The petition attached numerous exhibits

including, inter alia, the legal description of the property, a copy of the Board’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelo v. City of New London
545 U.S. 469 (Supreme Court, 2005)
Lundeen v. Graff
2015 Ohio 4462 (Ohio Court of Appeals, 2015)
Tracey v. Preston, Dir.
181 N.E.2d 479 (Ohio Court of Appeals, 1960)
Brown v. Scioto Cty. Bd. of Commrs.
622 N.E.2d 1153 (Ohio Court of Appeals, 1993)
Cirino v. Bur. of Workers' Comp. (Slip Opinion)
2018 Ohio 2665 (Ohio Supreme Court, 2018)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
State ex rel. Bush v. Spurlock
537 N.E.2d 641 (Ohio Supreme Court, 1989)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 2787, 154 N.E.3d 449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-cty-bd-of-commrs-v-rettig-ohioctapp-2020.