Henry Cty. Bd. of Commrs. v. Rettig

2020 Ohio 2787, 154 N.E.3d 449
Ohio Court of Appeals·Decided May 4, 2020·No. 7-19-11·Published

Opinion

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT

HENRY COUNTY

BOARD OF HENRY COUNTY COMMISSIONERS,

PLAINTIFF-APPELLEE, CASE NO. 7-19-11 v.

TODD RETTIG, ET AL., OPINION DEFENDANTS-APPELLANTS.

Appeal from Henry County Common Pleas Court Trial Court No. 18 CV 0142

Judgment Affirmed

Date of Decision: May 4, 2020

APPEARANCES:

Zachary J. Murry for Appellant Katie L. Nelson for Appellee

SHAW, P.J.

{¶1} Defendants-appellants, Todd Rettig1 and Paula Rettig (collectively, “the Rettigs”), bring this appeal from the September 10, 2019, judgment of the Henry County Common Pleas Court granting the motion for summary judgment filed by the Board of Henry County Commissioners (“the Board”) in an eminent domain action. As a result of granting the Board’s motion for summary judgment, the trial court dismissed the Rettigs’ counterclaims against the Board.

{¶2} The Rettigs also appeal the September 10, 2019, judgment of the Henry County Common Pleas Court denying the Rettigs’ motion to dismiss the appropriation action on the basis that the appropriation petition was “defective.” On appeal, the Rettigs argue that the trial court erred by granting the Board’s summary judgment motion and by denying the Rettigs’ motion to dismiss.

Background

{¶3} The City of Napoleon, located in Henry County, is physically divided into northern and southern portions by the Maumee River. As early as 2001 or 2002, there were discussions regarding building an additional bridge across the river. In 2003, the City of Napoleon approved a “comprehensive master plan,” which recommended the creation of a second river crossing via a new bridge as a critical infrastructure improvement.

1 Todd Rettig is the custodian for Kyle Rettig under the Ohio Transfers to Minors Act.

{¶4} A study was commissioned for a potential “New Maumee River Crossing Project” and a final report was issued on March 11, 2009. The report identified numerous reasons why a new bridge across the Maumee River was needed:

First, there is a need to provide a more direct transportation corridor between the two designated industrial development areas that are located on the east side of the city, both north and south of the Maumee River. Secondly, an option is needed to improve emergency response times when traffic is disrupted on the existing bridge that crosses the river on SR 108 in the city.

Thirdly, although the majority of Napoleon’s developed areas are located on the north side of the river, the south side of the river contains the largest single employer in Napoleon, the world’s largest Campbell’s Soup plant, which employs an average of 1,200 people. The Henry County fairgrounds, several small businesses, and residential areas also exist on the south side of the Maumee River.

(Def.’s Ex. D at 1-1). The report also stated that having only a single river crossing at SR 108 caused significant traffic congestion and delays in downtown Napoleon during peak traffic periods.2 This included heavy truck traffic going through downtown Napoleon.

{¶5} The report identified four potential sites for a new bridge over the Maumee River. Early cost estimates for building a bridge were between $14.5-16.5 million. A “no-build” alternative was also considered, which evaluated the potential of meeting the city’s needs through various measures short of building a new bridge.

2 The record indicates that there were additional river crossings outside of town, but they did not alleviate the problems.

{¶6} After the report was complete on the project, a “feasibility” study was undertaken, which analyzed traffic and crashes in the area in order to determine the necessity of the bridge project and, if the bridge project was necessary, which of the potential build sites would be the best. The feasibility study was completed in 2013.

{¶7} The completed feasibility study determined that a “no-build” option would not address the traffic and access concerns. (Schumm Depo at 48). The four initial build sites were narrowed to two options, and the final recommendation from the feasibility study was that the new bridge be an extension of “Industrial Drive.” The extension of Industrial Drive would connect Riverview Avenue on the south side of the Maumee River via a new bridge to State Route 110 on the north side of the Maumee River.

{¶8} During the time that the feasibility study was being conducted, there were attempts by the Henry County Engineer to secure funding for the bridge through means separate from the City of Napoleon and Henry County such as through state and federal grants and private donations. Applications were made to the Transportation Review Advisory Committee (“TRAC”), a funding agency from the State of Ohio, which accepted applications approximately once per year. Initial applications to TRAC were denied, and TRAC provided feedback that securing some private funding would make the application more attractive. (Dahl Depo. at 28); (Schumm Depo at 59, 119). Financial assistance for the bridge was then sought

from the area’s largest employer, Campbell’s, first in the amount of $1.5 million. Although Campbell’s never agreed to contribute $1.5 million, Campbell’s did eventually agree to contribute over $400,000. Then, on the sixth attempt at applying for a TRAC grant, the application was approved and additional funding was received for the bridge project.3 (Schumm Depo. at 22). However, applications through a federal grant program called “TIGER” were rejected on the three occasions that they were submitted.

{¶9} Over the next several years bridge and road plans were submitted and completed. In the meantime, additional funding was still sought through various sources. Once plans for the road and bridge had essentially been finalized, initial work proceeded on the bridge such as clearing trees and acquiring property. A deal was made with one property owner, but a deal could not be made with the Rettigs, who owned property along the river.

{¶10} On November 6, 2018, the Board met in regular session and passed a resolution indicating that the “New River Bridge Project” was proceeding and that construction would require the acquisition of .7857 acres of property from the Rettigs. The resolution indicated that the acquisition of the Rettigs’ property was necessary, and that they had been unable to negotiate a fair price.

3 Regarding the difficulty of acquiring a grant through TRAC, a Henry County Commissioner testified that TRAC had something like “$25 billion worth of good projects and $12 billion to spend.” (Hastedt Depo at 31).

{¶11} An appraisal of the property was conducted by Martin & Wood Appraisal Group, LTD. The appraisal valued the .7857 acres of riverfront property proposed to be taken at $27,500. In addition, the appraisal valued damage to the remaining parcel the Rettigs would still own at $6,900, for a total compensation award of $34,400.

{¶12} Subsequently the Board filed a Petition for Appropriation of the Rettigs’ property on November 16, 2018. The petition attached numerous exhibits including, inter alia, the legal description of the property, a copy of the Board’s resolution, a title report, and the appraisal report of the Rettigs’ property.

{¶13} On December 18, 2018, the Rettigs filed an answer containing affirmative defenses and counterclaims. The Rettigs’ first counterclaim requested that the trial court make a declaratory judgment that the Board had abused its eminent domain power and that the Board’s actions were in violation of R.C.163.021 because the appropriation in this case was not for “public use.”

Free access — add to your briefcase to read the full text and ask questions with AI

Henry Cty. Bd. of Commrs. v. Rettig, 2020 Ohio 2787, 154 N.E.3d 449 (Ohio Ct. App. 2020).

2020 Ohio 2787 (Henry Cty. Bd. of Commrs. v. Rettig) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kelo v. City of New London
545 U.S. 469 (Supreme Court, 2005)
Lundeen v. Graff
2015 Ohio 4462 (Ohio Court of Appeals, 2015)
Tracey v. Preston, Dir.
181 N.E.2d 479 (Ohio Court of Appeals, 1960)
Brown v. Scioto Cty. Bd. of Commrs.
622 N.E.2d 1153 (Ohio Court of Appeals, 1993)
Cirino v. Bur. of Workers' Comp. (Slip Opinion)
2018 Ohio 2665 (Ohio Supreme Court, 2018)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
State ex rel. Bush v. Spurlock
537 N.E.2d 641 (Ohio Supreme Court, 1989)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)