M. O'Connor Contracting, Inc. v. City of Brockton

809 N.E.2d 1062, 61 Mass. App. Ct. 278, 2004 Mass. App. LEXIS 634
CourtMassachusetts Appeals Court
DecidedJune 7, 2004
DocketNo. 02-P-1017
StatusPublished
Cited by13 cases

This text of 809 N.E.2d 1062 (M. O'Connor Contracting, Inc. v. City of Brockton) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. O'Connor Contracting, Inc. v. City of Brockton, 809 N.E.2d 1062, 61 Mass. App. Ct. 278, 2004 Mass. App. LEXIS 634 (Mass. Ct. App. 2004).

Opinion

Cohen, J.

At issue in this appeal is whether the city of Brock-ton must pay an award of double damages under G. L. c. 93A in a construction contract case that was decided, over the city’s objection, by an arbitrator. Although we reject the city’s contention that the arbitration agreement cannot be read to authorize arbitration of a c. 93A claim, we nevertheless conclude that the award must be vacated as beyond the arbitrator’s authority because it is contrary to principles of sovereign immunity and, hence, against public policy.

[279]*279Background. Undertaking to build a new municipal building to house its council on aging,1 the city entered into a written construction contract with the plaintiff, M. O’Connor Contracting, Inc., whereby the plaintiff would receive $1,344,500 for its work on the project. The contract included the following “Supplementary General Condition” relating to arbitration:

“U. Damages
Should either party to the Contract suffer damages because of any wrongful act or neglect of the other party . . . claim shall be made in writing to the party liable within a reasonable time of the first observance of such damage and no later than the final payment. . . and shall be adjusted by agreement or arbitration.”

Another Supplementary General Condition, paragraph Q, provided that such claims would be heard by the American Arbitration Association.

As the project neared completion, a dispute arose between the parties. The plaintiff claimed that it was owed a balance of $101,685.95 for work performed under the contract. The city refused to pay, citing deficiencies in the work. Viewing the city’s refusal to pay as unjustified and, hence, giving rise to a “claim” for “damages because of any wrongful act” within the meaning of the above arbitration clause, the plaintiff filed a demand for arbitration with the American Arbitration Association. After preliminary skirmishes before the arbitrator as to whether arbitration was the appropriate forum for the dispute,2 the city refused to participate. On October 5, 2001, the plaintiff therefore went to court, pursuant to G. L. c. 251, § 2(a), [280]*280and moved to compel arbitration of (1) its claim for the balance allegedly owed under the contract, and (2) a claim for double or treble damages under G. L. c. 93A.

In response, the city opposed the arbitration generally, contending that the parties had not agreed to arbitrate any aspect of the controversy. It also requested that, at a minimum, the court strike the plaintiffs c. 93 A claim.3 A judge of the Superior Court rejected the city’s position, concluding that the arbitration clause was broad enough to include a claim for payments improperly withheld. He did not distinguish between the breach of contract and c. 93A claims and allowed the plaintiffs motion to compel arbitration as to both.

The arbitration proceeded (over the city’s protest) with the following results: the arbitrator issued an award on December 14, 2001, in favor of the plaintiff on the contract claim, which, with interest, amounted to $107,479.35; then, finding that the city “chose to ignore its obligations established under the terms of the contract” and that its “actions during the subsequent period regarding payments . . . and . . . concerning this Arbitration process” were “unfair and purposely deceptive,” the arbitrator also rendered an award of double damages on the plaintiff’s c. 93A claim. Although the award was fairly detailed in other respects (it was six pages in length), it did not address the legal sufficiency of the c. 93A claim and contained no discussion of whether the transaction arose from the city’s engagement in trade or commerce.

After the arbitration was concluded, the parties returned to the Superior Court. The plaintiff moved, pursuant to G. L. c. 251, § 11, to confirm the arbitration award and, for the first time, requested an award of costs and attorney’s fees in conjunction with its c. 93A claim. The city countered with a motion, pursuant to G. L. c. 251, § 12, to reconsider the court order compelling arbitration and to vacate the award.4 A judge differ[281]*281ent from the one who allowed the plaintiff’s motion to compel arbitration denied the city’s motion and confirmed the award in its entirety.

The judge rejected the city’s contention that the arbitrator lacked the authority to consider and award relief on the c. 93A claim, concluding that the issue was governed by Drywall Sys., Inc. v. ZW Constr. Co., 435 Mass. 664, 666-671 (2002), which held that a statutory claim under G. L. c. 93A, § 11, including a claim for multiple damages, was within the scope of a broadly worded arbitration clause agreed to by two private construction businesses. The judge then observed that while “[t]he court might venture to agree that the city was not engaged in trade or commerce and thus not subject to G. L. c. 93A liability,” he was constrained to leave the results of the arbitration undisturbed because even a grossly erroneous arbitration decision is binding in the absence of fraud.

Discussion. The city takes the position that the arbitration clause cannot be read as an agreement to arbitrate the plaintiff’s c. 93A claim and that it therefore was error for the first judge to order that the c. 93A claim be submitted to arbitration, and for the second judge to refuse to vacate the double damages award as exceeding the arbitrator’s authority. The city’s rationale, briefly stated, is that the parties’ agreement requires that, to be arbitrable, the plaintiff’s claim must be one for damages because of a “wrongful act”5; that this language can only refer to a grievance that is capable of legal redress; and that, given the public motivation for the project, the plaintiff’s c. 93A claim against the city was not legally cognizable,6 and hence not arbitrable. In effect, the city invites us to consider the legal [282]*282merits of the plaintiff’s c. 93A claim and to conclude that, because it fails to state a valid cause of action on the facts of this case, the parties could not have intended to arbitrate it. This we cannot do.

“[WJhere the contract contains an arbitration clause, there is a presumption of arbitrability in the sense that ‘[a]n order to arbitrate the particular grievance should not be denied unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage ....’” Local No. 1710, Intl. Assn. of Fire Fighters, AFL-CIO v. Chicopee, 430 Mass. 417, 421 (1999), quoting from AT&T Technologies, Inc. v. Communications Wkrs. of Am., 475 U.S. 643, 649 (1986). Although the clause in question is not the standard, broad clause that was at issue in Drywall Sys., Inc. v. ZVI Constr. Co., 435 Mass, at 665,7 it does not, by its terms, exclude c. 93A claims; nor does the arbitration clause, or any other part of the contract, place descriptive limits upon the matters that may be arbitrated. Compare Royal Indem. Co. v. Blakely, 372 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Beverly v. Bass River Golf Mgmt., Inc.
93 N.E.3d 852 (Massachusetts Appeals Court, 2016)
Brown v. Office of the Commissioner of Probation
35 N.E.3d 1 (Massachusetts Appeals Court, 2015)
Sheriff of Suffolk County v. Jail Officers & Employees of Suffolk County
990 N.E.2d 1042 (Massachusetts Supreme Judicial Court, 2013)
Massachusetts Highway Department v. Perini Corp.
947 N.E.2d 62 (Massachusetts Appeals Court, 2011)
North American Assurance Co. of America v. Payzant
27 Mass. L. Rptr. 226 (Massachusetts Superior Court, 2010)
T. Bedrosian, LLC v. Town of Mendon
24 Mass. L. Rptr. 344 (Massachusetts Superior Court, 2008)
Pitcherville Sand & Gravel, Inc. v. Holden Sand & Gravel Co.
24 Mass. L. Rptr. 243 (Massachusetts Superior Court, 2008)
Fiske v. Town of North Attleboro
22 Mass. L. Rptr. 242 (Massachusetts Superior Court, 2007)
Scott v. Commerce Insurance
816 N.E.2d 1224 (Massachusetts Appeals Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
809 N.E.2d 1062, 61 Mass. App. Ct. 278, 2004 Mass. App. LEXIS 634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-oconnor-contracting-inc-v-city-of-brockton-massappct-2004.