M L Building Corp. v. Cnf Industries, No. Cv92-50204 (Jul. 6, 1992)

1992 Conn. Super. Ct. 5742, 7 Conn. Super. Ct. 871
CourtConnecticut Superior Court
DecidedJuly 6, 1992
DocketNo. CV92-50204
StatusUnpublished

This text of 1992 Conn. Super. Ct. 5742 (M L Building Corp. v. Cnf Industries, No. Cv92-50204 (Jul. 6, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M L Building Corp. v. Cnf Industries, No. Cv92-50204 (Jul. 6, 1992), 1992 Conn. Super. Ct. 5742, 7 Conn. Super. Ct. 871 (Colo. Ct. App. 1992).

Opinion

These cases arise from a construction contract by which M L Building Corporation (hereinafter "M L") was to construct a new headquarters building in Meriden, Connecticut for CNF Industries, Inc. (hereinafter "CNF".) The contract was dated March 5, 1991 and provided for a contract price of $2,550,000.00, for a three story 37,500 square foot and 20,500 square foot buildings. Completion was due on September 30, 1991.

On August 1, 1991, after commencement of work on the project, the relationship between the parties broke down. At such time the project had not been completed.

The agreement between the parties contained an arbitration clause which provided in pertinent part:

Article 7. Arbitration

7.1 Agreement to arbitrate. Claims, disputes and matters in question arising out of or relating to this agreement . . . shall be decided by arbitration. . . . . . .

7.6 Arbitrability. Any question of arbitrability shall be decided by the appropriate court and not by arbitration.

On August 1, 1991, CNF demanded arbitration under the contract and terminated M L for default.

On August 8, 1991, M L filed an answer and counterclaim in the arbitration.

The arbitrators, after hearings, entered an award dated April 9, 1992. Though CNF was awarded $101,503.31, on its claim, M L was awarded on its counterclaim $1,132,760.00, interest of $59,500.00, and attorneys' fees of $112,000.00. CNF was further ordered to pay expenses for the arbitration process.

M L seeks to confirm the award pursuant to Connecticut General Statutes 52-417, and CNF asks the court to vacate the award pursuant to Connecticut General Statutes 52-418. CT Page 5743

ARBITRABILITY

CNF Industries argues that the award of the arbitrators was not arbitrable and therefore should be vacated. CNF claims that the arbitrators rescinded the contract between CNF and M L and by doing so they threw out the arbitration clause thus wresting jurisdiction from the arbitrators. M L claims that even if the arbitrators rescinded the contract as suggested by CNF, the arbitration clause was severable and therefore the arbitrators still had jurisdiction to decide the dispute.

"`Whether a particular dispute is arbitrable is a question for the court, unless, by appropriate language, the parties have agreed to arbitrate that question, also.'" Welch Group, Inc. v. Creative Drywall, Inc., 215 Conn. 464, 467, 576 A.2d 153 (1990). There is no dispute that the contract between CNF and M L called for any question of arbitrability to be determined by the court. Article 7.6 of the parties' agreement states: "Any question of arbitrability shall be decided by the appropriate court and not by arbitration." Article 7.6 (Exhibit A, CNF's Motion to Vacate the Arbitrator's Award).

CNF claims that the question of arbitrability did not arise until after the arbitrators rendered their decision. CNF asserts that the arbitrators "threw out" or rescinded the contract at the request of M L thereby nullifying the arbitration clause, leaving the arbitrators without jurisdiction. The authority for this proposition cited by CNF is the case of Metcalfe v. Talarski, 213 Conn. 145,567 A.2d 1148 (1989), in which the court held that "[t]he effect of a rescission is to extinguish the contract . . . [which] waives the right to sue on it." Metcalfe, supra, 159. The claim is that since the contract was rescinded, the arbitration clause was thrown out with it and therefore the arbitrators were without jurisdiction to hear the case.

M L's position is, assuming arguendo that the contract was thrown out as CNF suggests, that the arbitration clause was severable and survived despite the rescission. M L relies on two cases in which the Connecticut Supreme Court held that the arbitration clause was severable and survived termination of the contract. The two cases are International Brotherhood v. Trudon and Platt Motor Lines, Inc., 146 Conn. 17, 147 A.2d 484 (1958) and Batter Building Materials Co. v. Kirschner, 142 Conn. 1,110 A.2d 464 (1954). In Batter, the court held that "`[t]he contract is not put out of existence [by a repudiation or total breach], though all further performance of the obligations undertaken by each party in favor of the other may cease. It survives for the purpose of measuring the claims arising out of the breach, and the arbitration clause survives for determining the mode of their settlement. The purposes of the contract have failed, but the arbitration CT Page 5744 clause is not one of the purposes of the contract.'" Batter, supra, 10. In International Brotherhood, supra, the court held that "even if it were found that the agreement was terminated, the parties would not be relieved of the obligation to arbitrate a dispute which arose while the agreement was in force." International Brotherhood, supra, 20.

Neither of the cases cited by M L is directly on point. In Batter, supra, the court found that if the contract was breached or repudiated, not rescinded, the arbitration clause would still be given effect. While in International Brotherhood, supra, the court found that if the contract terminated by its own terms, the arbitration clause would still be enforced if the dispute arose during the life of the contract. In the case at bar, the question is what effect would rescission have on the arbitration clause. The cases do reflect the deference and respect afforded the arbitration process by Connecticut courts. Waterbury Board of Education v. Water Teachers Assn., 168 Conn. 54, 62, 357 A.2d 466 (1975). Our supreme court, in a case cited by both CNF and M L, considered, but did not answer this question. In A. Sangivanni Sons v. F.M. Floryan Co., 158 Conn. 467,262 A.2d 159 (1969), the court stated that "[t]he question [of] whether the plaintiff could enforce the arbitration clause if it sought rescission instead of damages is not before us. Note, 91 A.L.R.2d 936, 942. We are only required to hold under the circumstances that where rescission is not sought by the defrauded party, the arbitration clause remains enforceable." A. Sangivanni Sons, supra, 472.73. The court's reference to the American Law Reports Second, provides a case that sheds light on the subject.

In Housekeeper v. Lourie, 333 N.Y.S.2d 932 (1972), the New York Supreme Court, Appellate Division, discusses the effect of fraud in the inducement of an agreement to arbitrate. The court in Housekeeper, supra, stated:

The right to demand and compel arbitration of a controversy or dispute presupposes the existence of a valid and enforceable agreement for arbitration and challenge in court may be made to the existence of such an agreement. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of New Britain v. Connecticut State Board of Mediation & Arbitration
424 A.2d 263 (Supreme Court of Connecticut, 1979)
City of Bridgeport v. Bridgeport Police Local 1159
438 A.2d 1171 (Supreme Court of Connecticut, 1981)
A. Sangivanni & Sons v. F. M. Floryan & Co.
262 A.2d 159 (Supreme Court of Connecticut, 1969)
Batter Building Materials Co. v. Kirschner
110 A.2d 464 (Supreme Court of Connecticut, 1954)
Waterbury Board of Education v. Waterbury Teachers Assn.
357 A.2d 466 (Supreme Court of Connecticut, 1975)
Housekeeper v. Lourie
39 A.D.2d 280 (Appellate Division of the Supreme Court of New York, 1972)
O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
523 A.2d 1271 (Supreme Court of Connecticut, 1987)
City of New Haven v. AFSCME, Council 15, Local 530
544 A.2d 186 (Supreme Court of Connecticut, 1988)
City of Hartford v. Connecticut State Board of Mediation & Arbitration
557 A.2d 1236 (Supreme Court of Connecticut, 1989)
Metcalfe v. Talarski
567 A.2d 1148 (Supreme Court of Connecticut, 1989)
Welch Group, Inc. v. Creative Drywall, Inc.
576 A.2d 153 (Supreme Court of Connecticut, 1990)
Middlesex Mutual Assurance Co. v. Walsh
590 A.2d 957 (Supreme Court of Connecticut, 1991)
Board of Education v. Hartford Federation of School Secretaries
600 A.2d 1053 (Connecticut Appellate Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 5742, 7 Conn. Super. Ct. 871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-l-building-corp-v-cnf-industries-no-cv92-50204-jul-6-1992-connsuperct-1992.