L.P. Cavett Company v. United States Department of Labor

101 F.3d 1111, 3 Wage & Hour Cas.2d (BNA) 993, 1996 U.S. App. LEXIS 30984, 1996 WL 688966
CourtCourt of Appeals for the Sixth Circuit
DecidedDecember 3, 1996
Docket95-3902
StatusPublished
Cited by12 cases

This text of 101 F.3d 1111 (L.P. Cavett Company v. United States Department of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.P. Cavett Company v. United States Department of Labor, 101 F.3d 1111, 3 Wage & Hour Cas.2d (BNA) 993, 1996 U.S. App. LEXIS 30984, 1996 WL 688966 (6th Cir. 1996).

Opinion

KEITH, Circuit Judge.

Plaintiff-Appellant, L.P. Cavett Company (“Cavett”) appeals from an order of the magistrate judge granting summary judgment in favor of the Department of Labor in an action to review the Department’s determination that Cavett and its subcontractor violated the Davis-Bacon Act while performing work on a federally-funded highway construction project. Cavett contends that the district court erred in finding that the prevailing wage requirements of the Davis-Bacon Act were intended to apply to truck drivers hauling asphalt from a temporary batch plant to a highway construction project. See 892 F.Supp. 973, 981-82 (S.D.Ohio 1995). We agree with Cavett that the wage provisions of the Davis-Bacon Act were not intended to apply to the truck drivers. In addition, we find that the Federal-Aid Highways Act does not impose an obligation on Cavett to pay the truck drivers prevailing wages. As a result, we REVERSE the decision of the magistrate judge and REMAND this case to the district court with instructions to enter judgment in favor of Cavett.

I. Background

On June 10, 1985, the Indiana Department of Highways awarded a contract to Cavett to resurface roughly 10.8 miles of Indiana state road. The contract specified that Cavett would perform surface and shoulder removal, widening of the highway and then resurfacing with a bituminous mix. On June 12, 1985, representatives of Cavett and the Indiana Department of Highways decided that a bituminous plant would be established approximately three miles from the midpoint of the highway to be reconstructed. Cavett subcontracted with George St. John’s Trucking (“St. John’s”) to haul materials, supplies *1113 and equipment from the batch plant to the highway. Cavett’s contract with St. John’s did not contain a Davis-Bacon Act prevailing wage standard provision even though the highway project was financially assisted by federal funds.

In 1988, the Department of Labor initiated an investigation of the highway project. On May 16, 1989, the Wage and Hour Administrator issued a ruling that the truck drivers hauling asphalt from the batch plant to the highway site should have been paid at the prevailing Davis-Bacon wage rate because the batch plant could be considered as part of the “site of work” pursuant to 29 C.F.R. § 5.2(1)(2). The Administrator found that the batch plant was part of the “site of work” because (1) the batch plant was established after the contract was awarded, (2) the batch plant was three to five miles from the construction site, and (3) the material produced at the batch plant was furnished exclusively, or nearly so, to the highway project. Thereafter, Cavett was assessed $11,202.10 in back wages — $9,403.87 of which was due for prevailing wages and $1,798.23 for overtime wages.

On June 14, 1989, Cavett filed a petition for review before the Wage Appeals Board. The Board found that the bituminous batch plant was part of the “site of the work,” as defined in the applicable regulations at 29 C.F.R. § 5.2(l), and that therefore, the Davis-Bacon Act prevailing wage rates applied to St. John’s truck drivers.

Cavett petitioned the district court for review on September 22, 1993. The parties stipulated to having a magistrate judge decide the case. On July 20, 1995, the magistrate judge upheld the Department’s regulatory interpretation of the “site of the work,” and thus, affirmed the Wage Appeals Board’s decision that the truck drivers were working on the “site of the work” for purposes of prevailing wage coverage. The magistrate judge found that the statutory phrase “directly upon the site of the work” was ambiguous, and that section 5.2(0 represented a permissible construction of that phrase. Ca-vett filed a timely notice of appeal to this Court.

II. Discussion

A Standard of Review

We review de novo the magistrate judge’s decision to grant summary judgment in favor of the Department of Labor. Brooks v. American Broadcasting Co., 932 F.2d 495, 500 (6th Cir.1991), cert. denied, 510 U.S. 1015, 114 S.Ct. 609, 126 L.Ed.2d 574 (1993). Summary judgment is appropriate when the “pleadings, depositions, answers to interrogatories and admissions on file, together with affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.Proc. 56(c). Under the Administrative Procedure Act, judicial review of a Wage Appeals Board’s decision is limited to the question of whether the agency action was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); Communities, Inc. v. Busey, 956 F.2d 619, 623 (6th Cir.), cert. denied, 506 U.S. 953, 113 S.Ct. 408, 121 L.Ed.2d 332 (1992).

B. Davis-Bacon Act

The Davis-Bacon Act, 40 U.S.C. § 276a, was passed in 1931. It provides that for all contracts involving federal construction projects, “mechanics and laborers employed directly on the site of the work” shall be paid local prevailing wage rates as determined by the Secretary of Labor. The dual purposes of the Act are to give local laborers and contractors fair opportunity to participate in building programs when federal money is involved and to protect local wage standards by preventing contractors from basing their bids on wages lower than those prevailing in the area. See S.Rep. No. 963, 88th Cong., 2d Sess. (1964), reprinted in 1964 U.S.C.C.A.N. 2339, 2340.

In finding that the truck drivers employed by St. John’s Trucking Company were entitled to prevailing wages under the Davis-Bacon Act, the Department of Labor included in the site of the work both a batch plant located at a quarry more than three miles away from the highway construction project and the Indiana highway system that was used to transport materials from the batch *1114 plant to the construction project. In support of this determination, the Department of Labor relied on its own definition of “site of the work” contained in 29 C.F.R. § 5.2(l). That regulation states:

(1) The site of the work is limited to the physical place or places where the construction called for in the contract will remain when work on it has been completed and, as discussed in paragraph (l )(2) of this section,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Wall v. Circle C Construction, LLC
43 F. Supp. 3d 853 (M.D. Tennessee, 2014)
Bockelman Trucking v. Pennsylvania Prevailing Wage Appeals Board
30 A.3d 616 (Commonwealth Court of Pennsylvania, 2011)
Long v. Interstate Ready-Mix, L.L.C.
83 S.W.3d 571 (Missouri Court of Appeals, 2002)
State, Bus. & Indus. v. Granite Constr. Co.
40 P.3d 423 (Nevada Supreme Court, 2002)
Board of Trade, Inc. v. State
968 P.2d 86 (Alaska Supreme Court, 1998)
Griffin v. Reich
956 F. Supp. 98 (D. Rhode Island, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
101 F.3d 1111, 3 Wage & Hour Cas.2d (BNA) 993, 1996 U.S. App. LEXIS 30984, 1996 WL 688966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lp-cavett-company-v-united-states-department-of-labor-ca6-1996.