Dittrich v. Atlantic Mechanical, Inc.

CourtSuperior Court of Maine
DecidedSeptember 3, 2013
DocketSAGcv-11-027
StatusUnpublished

This text of Dittrich v. Atlantic Mechanical, Inc. (Dittrich v. Atlantic Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dittrich v. Atlantic Mechanical, Inc., (Me. Super. Ct. 2013).

Opinion

STATE OF MAINE SUPERIOR COURT SAGADAHOC, ss CIVIL ACTION DOCKET NO. CV-11-027 . J.Aw -5ACr ·1/3 ! ROBERT DITTRICH,

Plaintiff

V. DECISION AND ORDER i\fE ATLANTIC MECHANICAL, INC., ' ·!i"f·ice

Defendant SeP os 1-011 )

INTRODUCTION

This matter arises out of a construction project known as the "Boston Light"

Project on Little Brewster Island in Boston Harbor (Project or Boston Light Project). The

purpose of the project was to build a year-round structure for docking boats transporting

visitors to the oldest lighthouse in the country located on Little Brewster Island. The

United States Coast Guard (USCG) contracted with Atlantic Mechanical, Inc. (Atlantic)

as the general contractor on the Boston Light Project. Atlantic contracted with Patriot

Marine, LLC, (Patriot), the primary subcontractor involved in the Boston Light Project

and responsible for setting the towers at the Project. Patriot is not a party in this action.

The case came before the court for a bench trial on a wage claim that Robert

Dittrich (Dittrich) was not paid for all the hours that he worked on the Boston Light

Project. Dittrich seeks unpaid wages, which he argues are due at a rate required by the

Davis-Bacon Act, 29 U.S.C. §276(a), and an amount equal to twice the unpaid wages as

liquidated damages, costs and attorney fees pursuant to 26 M.R.S. §626-A. Atlantic

responded with a number of affirmative defense, including that Dittrich's alleged work was not performed for Atlantic and he did not work on any part of the Project for which

he was to be paid Davis-Bacon wages.

The issues for resolution are: how many hours did Dittrich actually work on the

Boston Light Project, if at all, and whether time on the East Boston Pier or the barge was

to be compensated in accordance with regular wages or prevailing wages under Davis-

Bacon. Dittrich's claims have been reduced from his original claim of three months for

which he should have been paid Bacon-Davis wages to a two-week period for the weeks

ending August 23, 2009 and August 30, 2009. He has eliminated from his claim that

time spent working on the pier in East Boston. He persists however in claiming Davis-

Bacon wages for time working on the barge, whether tied up at East Boston or Little

Brewster Island, time traveling to and from Little Brewster Island, and time at the site of

the Boston Light Project on Little Brewster Island.

Dittrich's claims at trial were that for the week ending August 23, 2009, he

worked a total of 63 hours of which 50.5 hours were for the Boston Harbor Light Project

and for the week ending August 30, 2009, he worked a total of 57.75 hours of which

22.25 hours were for the Boston Harbor Light Project. For the time he worked on the

Boston Light Project he claims he should have been paid at the required Davis-Bacon

prevailing wage of $42.25. The parties stipulated that for this case the prevailing wage

under Davis-Bacon was $42.25. Dittrich claims that the barge constitutes part of the "site

of work" as defined in 29 C.F.R. §5.2(1) and comes within the Davis-Bacon pay rate.

Atlantic contends that the Davis-Bacon prevailing wage rate does not apply to

travel time and to time spent working at Patriot's shop in East Boston and plaintiff failed

2 to meet its burden of showing that he worked at the job site on Little Brewster Island on

the days he claimed.

The court heard from a number of witnesses, including the following: Deborah

Gerry, paralegal for plaintiff's attorney; Robert Dittrich; Robert Lochyer, the owner of

Patriot; Christy Colby, Atlantic's bookkeeper; Daniel Smith by way of video, Patriot's

manager; Larry Paul, owner of Atlantic; and Nicole Hogland, paralegal for defendant's

attorney. The court also received into evidence 61 exhibits. The parties filed post-trial

briefs

FACTUAL FINDINGS

The evidence in this case permits the court to find the following facts:

Atlantic was the general contractor for the Boston Light Project work performed at

Little Brewster Island in the summer of2009. Patriot was the subcontractor, who

maintained a shop in East Boston and a barge that travelled between an East Boston pier

and Little Brewster Island, the site of the Boston Light Project. Larry Paul (Paul) owns

Atlantic, and Robert Lochyer (Lochyer) owns Patriot.

For the weeks ending August 23 and 30, 2009, Dittrich performed various ·types of

work for either Atlantic or Patriot. As an accommodation to Lockyer and Patriot, Atlantic

processed payroll records for Patriot. The subs submitted certified pay reports on a daily

basis and Paul reviewed those records every morning. Atlantic maintained Patriot's

paperwork because Patriot had only one part-time office employee. Atlantic also paid

Patriot's employees when Patriot had money problems and then Patriot reimbursed

Atlantic.

Paul credibly testified that he never directed Dittrich to work on an offshore project

3 because he was only 21 years old and inexperienced. Paul recalls that Dittrich may have

helped him one time with a delivery to Little Brewster Island. Paul also believed that any

overtime was incurred when Dittrich worked for Lochyer on his new farm in Woolrich,

Maine. Dittrich also drove Lochyer around because Lochyer had lost his license.

According to Paul, anybody who worked on the Boston Harbor Light Project on

Little Brewster Island appeared on the daily construction report, whether an Atlantic or

Patriot employee. (See Ex. 59.) The foreman or site superintendent submitted the daily

construction report. This form reported to the Coast Guard site time only, not barge time

or East Boston time. Paul submitted to the Coast Guard on a weekly basis the daily

construction report attached to the payroll and the two should have matched. Dittrich's

name did not appear on any of the daily construction report forms. There is a reference

on the August 28, 2009 construction report form to the letter "R" without the rest of the

name and the form reports that this was a laborer for the sub, not the prime. The R could

mean Robert Dittrich, but this is mere speculation. The sub would be Patriot. This would

be consistent with Paul's testimony that he (Atlantic) did not direct Dittrich to work at the

Little Brewster site. This is also consistent with Dittrich's own testimony that "Atlantic

directed [him] to go to Boston but once there Patriot's Dan Smith directed [his] work."

Atlantic certified its payroll and submitted it, along with the daily construction

report forms, to the Coast Guard. Atlantic's bookkeeper prepared the certified payroll

and took the information contained in her reports directly from the employees' time

sheets. Atlantic's bookkeeper broke down on the cover sheet to her payroll reports the job

and rate of pay for each employee. (See Exs. 13, 14, 54.) For the week of August 23,

2009, the bookkeeper reported that Dittrich worked 2.75 hours at the shop (E. Boston

4 pier), 2.75 hours at Rob's house (Lochyer's house) and 34.5 hours for Patriot, totaling 40

hours at $15 per hour for $600, which was reported and paid by Atlantic. (Exs. 13, 54.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bockelman Trucking v. Pennsylvania Prevailing Wage Appeals Board
30 A.3d 616 (Commonwealth Court of Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Dittrich v. Atlantic Mechanical, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dittrich-v-atlantic-mechanical-inc-mesuperct-2013.