Louisiana Power & Light Co. v. Allegheny Ludlum Industries, Inc.

517 F. Supp. 1319, 32 U.C.C. Rep. Serv. (West) 847, 1981 U.S. Dist. LEXIS 9832
CourtDistrict Court, E.D. Louisiana
DecidedJuly 17, 1981
DocketCiv. A. 79-3308
StatusPublished
Cited by16 cases

This text of 517 F. Supp. 1319 (Louisiana Power & Light Co. v. Allegheny Ludlum Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Power & Light Co. v. Allegheny Ludlum Industries, Inc., 517 F. Supp. 1319, 32 U.C.C. Rep. Serv. (West) 847, 1981 U.S. Dist. LEXIS 9832 (E.D. La. 1981).

Opinion

MEMORANDUM AND ORDER

JACK M. GORDON, District Judge.

This breach of contract case is before the Court on plaintiff’s motion for summary judgment. The material facts which are not in dispute are as follows:

Plaintiff, Louisiana Power & Light Company (hereinafter referred to as “LP&L”), entered into a contract with defendants, Allegheny Ludlum Industries, Inc. and Allegheny Ludlum Steel Corporation (hereinafter referred to collectively as “Allegheny,”) in which Allegheny agreed to supply condenser tubing to LP&L for use at LP&L’s Waterford 3 nuclear power plant. The contract was awarded to Allegheny Ludlum Steel Corporation, then a division of Allegheny Ludlum Industries, Inc., after the solicitation of bids by LP&L’s agent, Ebasco Services, Incorporated. The contract, dated February 8, 1974, was accepted by Allegheny in mid-March of 1974.

Pursuant to the terms of the contract Allegheny undertook to furnish, fabricate and deliver to LP&L stainless steel condenser tubing in accordance with the specifications of LP&L’s agent, Ebasco. Equal shipments of the tubing were to be made on June 1, 1976; June 15, 1976, and July 1, 1976, for a total price of $1,127,387.82. The contract also provided that if LP&L delayed shipment beyond August 31, 1976, but not later than January 31, 1977, the contract price would be increased by three percent (3%). A further adjustment at the rate of ten percent (10%) would take place if LP&L delayed shipment beyond January 31, 1977, but not later than January 31, 1978. No other escalation clauses were included in the contract.

On May 19, 1975, Allegheny sent a letter to LP&L seeking “additional compensation” for performance under the contract. Allegheny informed LP&L that subsequent to the formulation of the contract its “costs [had] risen at such a high rate that escalators built into our contracts have in no way adequately compensated for them. For example, since March of 1974 the price of electrolytic nickel has increased 24%, low carbon ferrochrome 185% and labor 21%.” 1 Allegheny sought the opportunity to meet with representatives of LP&L in order to discuss Allegheny’s price increases and possible solutions to Allegheny’s problem. Allegheny suggested a renegotiation of the contract price, but LP&L chose not to meet with Allegheny to discuss the matter.

In October of 1975, LP&L, through Ebas-co, advised Allegheny that it considered Allegheny’s price increases to be business risks which must be absorbed by Allegheny. On November 4, 1975, Allegheny informed LP&L, by letter from C. R. Hastings, General Manager of Allegheny’s Wallingford Tubular Products Division, that a “[c]urrent review of this matter suggests that Allegheny Ludlum might be well advised not to perform under the contract.” On November 19, 1975, Ebasco wrote to Allegheny’s Wallingford Tubular Products Division, and demanded written assurances within thirty days, pursuant to Section 2-609 of the New *1322 York Commercial Code, 2 that Allegheny would fully and properly perform under the contract.

As of January 19, 1976, LP&L had not received any such written assurance of performance from Allegheny and on January 30,1976, LP&L notified Allegheny by letter that it considered the contract repudiated by Allegheny. Thereafter, on February 17, 1976, C. R. Hastings at Allegheny wrote to LP&L informing it that Allegheny was willing to “make delivery under the subject purchase order at $1.80 per lb. ... [Allegheny’s] full cost of producing the material >1

LP&L rejected Allegheny’s offer to supply the tubing at Allegheny’s cost and through its agent, Ebasco, LP&L solicited bids from other vendors for supply of the requisite condenser tubing. LP&L steadfastly rejected the offer of Allegheny to supply the tubing at Allegheny’s cost, a price higher than that specified in the LP&L/Allegheny contract. On June 16, 1976, LP&L, through Ebasco, entered into a contract with Trent Tube Division of Crucible, Inc. for the purchase of condenser tubing at a price of $1,729,278.

Allegheny intended that the condenser tubing which was the subject of its contract with LP&L would be supplied by its Wall-ingford Tubular Products Division at Wall-ingford, Connecticut. C. R. Hastings, General Manager of the Wallingford Tubular Division, stated in his deposition that performance under the terms of the LP&L/A1-legheny contract would have caused Allegheny to sustain a projected loss of $428,500 on the contract. Hastings indicated that such a loss would have reduced the planned profit for 1976 at the Wallingford plant from $1,018,000 to $589,500.

Plaintiff seeks by way of its lawsuit to recover from Allegheny the costs of its “cover,” the monetary difference between the LP&L/Allegheny contract and the LP&L/Trent Tube contract, plus the expenses which it incurred in the re-solicitation of bids for the tubing. Allegheny has defended this action on four principal bases: commercial impracticability, mutual mistake, unconscionability and alleged bad faith conduct by LP&L. Plaintiff’s claim and Allegheny’s defenses will be considered in accord with the appropriate standards for summary judgment motions.

LP&L claims that Allegheny breached its contract to supply condenser tubing to LP&L. The first evidence which LP&L received that indicated that Allegheny would not perform under the contract as written was Allegheny’s letter of May 19, 1975 to LP&L in which Allegheny sought “additional compensation” for supplying the condenser tubing. In response to that submission, LP&L sent a letter to Allegheny, invoking the provisions of Section 2-609 of the New York Uniform Commercial Code and requesting assurance from Allegheny that it would perform under the contract.

The pertinent provisions of Section 2-609 of the U.C.C., invoked by LP&L, provide: § 2-609 Right to Adequate Assurance of Performance

(1) A contract for sale imposes an obligation on each party that the other’s expectation of receiving due performance will not be impaired. When reasonable grounds for insecurity arise with respect to the performance of either party the other may in writing demand adequate assurance of due performance ....

******

(4) After receipt of a justified demand failure to provide within a reasonable time not exceeding thirty days such assurance of due performance as is adequate under the circumstances of the particular case is a repudiation of the contract.

The letter which LP&L received from Allegheny requesting “additional compensation” provided LP&L with a reasonable basis for insecurity as to Allegheny’s performance under the contract. LP&L’s letter of November 19, 1975, to Allegheny constituted an adequate demand on Allegheny for an assurance of performance. When LP&L failed to receive such an assurance by Janu *1323 ary 19, 1976, it was justified in characterizing the contract as repudiated. LP&L notified Allegheny of that fact on January 30, 1976. Subsequently, Allegheny indicated to plaintiff that it would perform under the contract for added compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Validsa, Inc. v. PDVSA Services Inc.
632 F. Supp. 2d 1219 (S.D. Florida, 2009)
OWBR LLC v. Clear Channel Communications, Inc.
266 F. Supp. 2d 1214 (D. Hawaii, 2003)
Land O'Lakes, Inc. v. Hanig
610 N.W.2d 518 (Supreme Court of Iowa, 2000)
Canusa Corp. v. a & R LOBOSCO, INC.
986 F. Supp. 723 (E.D. New York, 1997)
7200 Scottsdale Road General Partners v. Kuhn Farm MacHinery, Inc.
909 P.2d 408 (Court of Appeals of Arizona, 1995)
Cliffstar Corp. v. Riverbend Products, Inc.
750 F. Supp. 81 (W.D. New York, 1990)
Dorn v. Stanhope Steel, Inc.
534 A.2d 798 (Supreme Court of Pennsylvania, 1987)
Lawrance v. Elmore Bean Warehouse, Inc.
702 P.2d 930 (Idaho Court of Appeals, 1985)
Gelco Express Corp. v. Ashby
689 S.W.2d 790 (Missouri Court of Appeals, 1985)
McGinnis v. Cayton
312 S.E.2d 765 (West Virginia Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
517 F. Supp. 1319, 32 U.C.C. Rep. Serv. (West) 847, 1981 U.S. Dist. LEXIS 9832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-power-light-co-v-allegheny-ludlum-industries-inc-laed-1981.