Losei Realty Corp. v. City of New York

171 N.E. 899, 254 N.Y. 41, 1930 N.Y. LEXIS 1001
CourtNew York Court of Appeals
DecidedMay 15, 1930
StatusPublished
Cited by40 cases

This text of 171 N.E. 899 (Losei Realty Corp. v. City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Losei Realty Corp. v. City of New York, 171 N.E. 899, 254 N.Y. 41, 1930 N.Y. LEXIS 1001 (N.Y. 1930).

Opinion

Pound, J.

The action is brought to recover damages for breach of a contract by which the defendant agreed to *44 fill in the plaintiff’s property on Jamaica bay with dredged material. The plaintiff has recovered a judgment in the sum of $39,493.41. Both parties have taken an appeal to this court. The defendant contests all the material contentions of the plaintiff but on questions of fact the evidence sustains the judgment against the city. The plaintiff contends that the damages awarded are inadequate as matter of law and asks that the judgment appealed from be modified by increasing the amount thereof by the sum of $130,923.22. •

Plaintiff and defendant owned adjoining lands under water in Jamaica bay at the foot of Flatbush avenue, Brooklyn. The defendant had erected a pier at the foot of Flatbush avenue extending out into Jamaica bay; plaintiff’s lands were next east of the pier and it was necessary to cross such lands to gain access to the pier. The boundary fine between the parties was also in dispute.

In order to enable the city to acquire the plaintiff’s lands under water adjoining its Flatbush avenue pier without resorting to condemnation proceedings, and to settle the boundary line dispute, agreements upon which this action is based were made and entered into between the plaintiff and the defendant. These agreements were made under the provisions of the Greater New York Charter and were as follows:

First. On July 13, 1916, the Commissioners of the Sinking Fund approved and adopted an agreement presented to them and directed the Corporation Counsel,, the Mayor and the City Clerk to execute the necessary papers to carry it out. This was the real agreement, between the parties, being made by the Commissioners of the Sinking Fund, the only authorized agency of the city to make such agreements. (Greater New York Charter, § 205.)

Second. On October 11, 1916, the formal deed fixing and describing the boundary fine, conveying the plaintiff’s lands under water adjoining the Flatbush avenue *45 pier and setting forth the other provisions of the sinking fund agreement, was executed by the plaintiff and the Mayor and City Clerk in pursuance of the provisions of the sinking fund agreement and duly delivered. This agreement and the formal deed of execution in accordance therewith constitute the contract between the plaintiff and the defendant.

The plaintiff was to erect a bulkhead upon its property, thirty feet inshore of the new bulkhead line established by the agreements. The defendant agreed within nine months from October 11, 1916, to do the following:

1. To dredge to a depth of eighteen feet outside the bulkhead line established by the agreements.

2. To dredge the lands between such bulkhead line and the plaintiff’s bulkhead thirty feet inshore therefrom, in an “ even slope of natural repose,” so that there should be five feet of water at the plaintiff’s bulkhead at mean low tide.

3. To deposit the dredged material, first upon the lands of the plaintiff “all to a surface and approximately uniform grade averaging 10 feet above mean low water.”

The defendant’s agreement then contained this provision:

“ The City of New York may vary the said order of filling, but from said dredged material or from other sources, shall at all events fill in the lands of said Losei Realty Corporation to the grade aforesaid with due diligence.” This clause is omitted from the formal deed in so far as it requires the fill to be made from other sources ” but the omission does not modify the agreement.

The plaintiff erected its bulkhead. Defendant agreed, first, to dredge the land “ so that there should be five feet of water at the plaintiff’s bulkhead at mean low tide; ” secondly, to fill plaintiff’s lands ■ at an average grade of “ 10 feet above mean low water.” The defendant let a dredging and filling contract to P. Sanford Ross, Inc., not, however, to carry out the entire agreement with *46 plaintiff. The two contracts are not in terms related. The Ross company had four months in which to perform, which would give it until September 12, 1917, to complete its contract, although the defendant had agreed to complete its agreement with plaintiff on July 11, 1917. The Ross company actually completed its wrork on October 17, 1917. It did its work of dredging improperly and negligently and by so doing broke down plaintiff’s bulkhead. In the end the fill provided for was practically but not fully completed by the city but not until December 2, 1922. The plaintiff sued to recover for damages to the bulkhead and for the cost of the completed fill and it has recovered therefor. It also sued for damages for delay in completing the work but the trial judge held that it was entitled to no damages for delay on the ground that the wrong was complete on July 11, 1917, nine months from October 11, 1916, and plaintiff could not lie by, neglecting to make the necessary reparation and hold the wrongdoer liable for loss sustained by the delay. This rule is properly applicable to actions in tort for damages for unlawful injury to property, where the ordinary measure of damages is the depreciation in value caused by the wrrongful act (Slavin v. State, 152 N. Y. 45)., but it is not applicable to actions to recover for breach of contract. One who violates his contract with another is liable for all the direct and proximate damages which result from the violation.” (Wakeman v. Wheeler & Wilson Mfg. Co., 101 N. Y. 205, 209.) The Appellate Division affirmed with a slight modification not material in this connection.

The city recognized its obligations to plaintiff and undertook to carry them out. Much delay resulted from various causes. Plaintiff waited from July 11, 1917, until April 8, 1920, when it began this action on the theory that the contract had not been terminated or abandoned but was still in full force and effect. The fill was after-wards completed by the city, with the exception of 63,285 *47 cubic yards, on December 2, 1922. Plaintiff now contends that it is entitled to damages due to such delay from July 11, 1917, to December 2, 1922.

The purpose of the contract was to improve the city water front and to give plaintiff a usable property with a proper depth of water. This was a legitimate exercise of the power of the city over the improvement of navigation facilities. (Matter of City of New York, 240 N. Y. 68.) The plaintiff is entitled to recover as damages the loss reasonably resulting from the delay. The question remains as to the measure of such damages and as to the reasonableness of plaintiff’s conduct in relation thereto.

Plaintiff might within a reasonable time after default have put an end to the contract (Taylor v. Goelet, 208 N. Y. 253) and completed the fill itself, or sued for damages, or it might have treated the contract as abandoned by the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trust v. Love Funding Corp.
736 F. Supp. 2d 716 (S.D. New York, 2010)
Aristocrat Leisure Ltd. v. Deutsche Bank Trust Co. Americas
727 F. Supp. 2d 256 (S.D. New York, 2010)
APL Co. PTE Ltd. v. Blue Water Shipping U.S. Inc.
592 F.3d 108 (Second Circuit, 2010)
International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
Clark Oil Trading Co. v. J. Aron & Co.
172 Misc. 2d 552 (New York Supreme Court, 1997)
Holy Properties Ltd. v. Kenneth Cole Productions, Inc.
661 N.E.2d 694 (New York Court of Appeals, 1995)
Jewish Press, Inc. v. Willner
190 A.D.2d 841 (Appellate Division of the Supreme Court of New York, 1993)
Atkins v. Lowin (In Re Monetary Group)
91 B.R. 138 (M.D. Florida, 1988)
Kaiser v. Fishman
138 A.D.2d 456 (Appellate Division of the Supreme Court of New York, 1988)
Haven Associates v. Donro Realty Corp.
121 A.D.2d 504 (Appellate Division of the Supreme Court of New York, 1986)
Northern Paiute Nation v. United States
9 Cl. Ct. 639 (Court of Claims, 1986)
Tynan Incinerator Co. v. International Fidelity Insurance
117 A.D.2d 796 (Appellate Division of the Supreme Court of New York, 1986)
Golbar Properties, Inc. v. North American Mortgage Investors
78 A.D.2d 504 (Appellate Division of the Supreme Court of New York, 1980)
Litton Industries Credit Corp. v. Catanuto
394 A.2d 191 (Supreme Court of Connecticut, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.E. 899, 254 N.Y. 41, 1930 N.Y. LEXIS 1001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/losei-realty-corp-v-city-of-new-york-ny-1930.