RKI Construction, LLC v. WDF Inc.

CourtDistrict Court, E.D. New York
DecidedNovember 6, 2020
Docket1:14-cv-01803
StatusUnknown

This text of RKI Construction, LLC v. WDF Inc. (RKI Construction, LLC v. WDF Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RKI Construction, LLC v. WDF Inc., (E.D.N.Y. 2020).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF NEW YORK --------------------------------------X RKI CONSTRUCTION, LLC,

Plaintiff, MEMORANDUM AND ORDER 14-cv-1803 (KAM)(VMS) -against-

WDF INC.; LIBERTY MUTUAL INSURANCE CO.; ANDRON CONSTRUCTION CORP.; and TRAVELERS CASUALTY AND SURETY CO. OF AMERICA,

Defendants,

-against-

CITIZENS INSURANCE CO. OF AMERICA; LEROY KAY; and ALICE KAY

Additional Defendants on the Third-Party Claims. --------------------------------------X KIYO A. MATSUMOTO, United States District Judge: Plaintiff RKI Construction, LLC (“RKI”) commenced this diversity breach of contract action against WDF Inc. (“WDF”),1 which filed a counterclaim against RKI, a third-party breach of contract claim against Citizens Insurance Company of America (“Citizens”), which issued a subcontractor performance bond (the “Bond”) to secure RKI’s performance under a subcontract with

1 Andron Construction Corp. (“Andron”) and Liberty Mutual Insurance Company (“Liberty”) were originally named as defendants in this action. On April 18, 2016, Andron and Liberty settled with RKI and were dismissed by RKI, without prejudice. (See ECF No. 98, Stipulation of Partial Settlement and Partial Dismissal without Prejudice.) Travelers Casualty and Surety Company of America (“Travelers”) is also listed as a named defendant but has not asserted any counterclaims. WDF, and a third-party claim against Leroy Kay and Alice Kay for fraud.2 (See ECF Nos. 32, 38, Amended Complaint (“Am. Compl.”) and Answer.)

On February 25, 26, 27, and 28, March 1, and April 3, 2019, the court conducted a six-day bench trial, where it considered the parties’ claims arising out of a sub-subcontract between RKI and WDF to install piping for WDF’s HVAC work, for construction of a five-story elementary school in Ridgewood, Queens (the “Project”).3 Having considered the evidence presented at trial, assessed the credibility of the witnesses, and reviewed the parties’ post-trial submissions,4 the court makes the following findings of fact and conclusions of law pursuant to Federal Rule of Civil Procedure 52 (“Rule 52”).5

2 By Memorandum and Order issued April 3, 2017, the court: (i) denied RKI's motion for summary judgment on its claim against WDF and WDF’s counterclaim, and (ii) granted Citizens' motion for summary judgment and dismissed WDF’s third-party claim against Citizens. (ECF No. 113)(RKI Construction, LLC v. WDF, Inc., No. 14-cv-1803 (KAM) (VMS), 2017 WL 1232441 (E.D.N.Y. Apr. 3, 2017).) 3 The trial addressed the parties’ liability and damages. The court reserved judgment on any issues regarding the award of fees until after its ruling on liability. Specifically, the court held the following claims in abeyance: (i) WDF's claim for legal fees; (ii) the Kay’s counterclaim for fees; (iii) RKI's fifth claim for interest based on WDF's violation of New York General Business Law § 756-a; (iv) and RKI's, Leroy Kay's and Alice Kay's claim against WDF for making a wrongful claim against the Bond. (See ECF Minute Entry dated Feb. 22, 2019.) 4 The post-trial submissions of the parties consist of the following: ECF No. 198, Plaintiff’s Proposed Findings of Fact and Conclusions of Law (“Pl. Mem.”); ECF No. 200 Defendant’s Proposed Findings of Fact and Conclusions of Law (“Def. Mem.”); ECF No. 201, Plaintiff’s Response to Defendant’s Proposed Findings of Fact and Conclusions of Law (“Pl. Resp.”); ECF No. 203, Defendant’s Response to Plaintiff’s Proposed Findings of Fact and Conclusions of Law (“Def. Resp.”). 5 “In an action tried on the facts without a jury . . ., the court must find the facts specially and state its conclusions of law separately. The Based on the trial record, for the reasons set forth below, the court concludes that RKI proved its claim for breach of contract by a preponderance of the evidence, and WDF failed to prove its

counterclaims for breach of contract by a preponderance of evidence and fraud by clear and convincing evidence.6 PROCEDURAL HISTORY RKI commenced this action on March 20, 2014, and filed the operative amended complaint on March 11, 2015. (See Am. Compl.) WDF filed its answer to the Amended Complaint, counterclaim against RKI, and third-party claim against Citizens on March 25, 2015. (See Answer.) The court issued its summary judgment Memorandum and Order on April 3, 2017, granting summary judgment to Citizens and denying summary judgment to RKI. (See ECF No. 113, Mem. and Opinion.) In its summary judgment decision, this court left open the “triable issues of fact as to whether or not RKI performed under the contract, and whether WDF properly deemed RKI to be in default.” (Id. at *5.) Trial

findings and conclusions may . . . appear in an opinion or a memorandum of decision filed by the court.” Fed. R. Civ. P. 52(a)(1). Under Rule 52(a), findings of fact may be determined “based on oral or documentary evidence,” and “findings of fact in a bench trial based on written submissions are accorded the same deference as factual findings that are otherwise determined.” Connors v. Conn. Gen. Life Ins. Co., 272 F.3d 127, 135 (2d Cir. 2001) (citing Fed. R. Civ. P. 52(a)). 6 To establish a fact by a preponderance of evidence means “simply to prove that the fact is more likely true than not true.” United States v. Rosa, 17 F.3d 1531, 1542 (2d Cir. 1994); see also Velasquez v. United States Postal Serv., 155 F. Supp. 3d 218, 227 (E.D.N.Y. 2016). As the finder of fact, the court is entitled to make credibility findings as to the witnesses and their testimony. See Krist v. Kolombos Rest. Inc., 688 F.3d 89, 95 (2d Cir. 2012). began on February 25 and continued through February 28, March 1, and April 3, 2019. FINDINGS OF FACT At trial, plaintiffs presented testimony from David Kay, Alice Kay, two managing members from RKI, RKI counsel

Michael Zicherman, Esq., and WDF counsel Becky Tung, Esq. as witnesses. Defendants called Antonio Gentile, SCA’s project officer, Robert Bailey, Andron project manager, Liam McLaughlin, WDF Senior Vice President, and John Cutrone, WDF project manager, as witnesses. The court was also provided with a Declaration of Mark Wilson, formerly employed by Andron as an operations manager on the Project, which was admitted into evidence without objection.7 (Trial Transcript ("Tr.") 1031:7- 1035:5, 1166:14-16.) Pursuant to Federal Rule of Civil Procedure 52, the court considers the evidence offered at trial and makes the following findings of fact below. The Parties

The New York City School Construction Authority (“SCA”) is “a public benefit corporation established pursuant to New York Public Authority Law §§ 1727 et seq., whose primary purpose is to design, construct, and maintain educational facilities in New York City.” A.F.C. Enterprises v. New York

7 At trial, the parties stipulated that all exhibits in the joint exhibit binders would be admitted into evidence. (Tr. 17:13-16; see ECF Nos. 208-210 (joint trial exhibits cited herein).) City Sch. Const. Auth., No. 98-cv-4534 (CPS), 1999 WL 1417210, at *1 (E.D.N.Y. June 29, 1999). Andron is a corporation organized under the laws of

New York with its principal place of business in Goldens Bridge, New York. (ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoodho v. Holder
558 F.3d 184 (Second Circuit, 2009)
Schipani v. McLeod
541 F.3d 158 (Second Circuit, 2008)
Merrill Lynch & Co. Inc. v. Allegheny Energy, Inc.
500 F.3d 171 (Second Circuit, 2007)
Miller v. Fenton
474 U.S. 104 (Supreme Court, 1985)
Fischer & Mandell LLP v. Citibank, N.A.
632 F.3d 793 (Second Circuit, 2011)
United States v. Bernard McKeon
738 F.2d 26 (Second Circuit, 1984)
Frank Felix Associates, Ltd. v. Austin Drugs, Inc.
111 F.3d 284 (Second Circuit, 1997)
In Re Lavigne
114 F.3d 379 (Second Circuit, 1997)
United States v. Aris Maria, AKA Luis A. Rivera
186 F.3d 65 (Second Circuit, 1999)
Crigger v. Fahnestock
443 F.3d 230 (Second Circuit, 2006)
Krist v. Kolombos Rest. Inc.
688 F.3d 89 (Second Circuit, 2012)
APL Co. PTE Ltd. v. Blue Water Shipping U.S. Inc.
592 F.3d 108 (Second Circuit, 2010)
In Re ADL Contracting Corp.
184 B.R. 436 (S.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
RKI Construction, LLC v. WDF Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rki-construction-llc-v-wdf-inc-nyed-2020.