Lopez v. C.G.M. Development, Inc.

124 Cal. Rptr. 2d 227, 101 Cal. App. 4th 430, 67 Cal. Comp. Cases 1023, 2002 Daily Journal DAR 9632, 2002 Cal. Daily Op. Serv. 7687, 2002 Cal. App. LEXIS 4527
CourtCalifornia Court of Appeal
DecidedMay 31, 2002
DocketB150621
StatusPublished
Cited by15 cases

This text of 124 Cal. Rptr. 2d 227 (Lopez v. C.G.M. Development, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lopez v. C.G.M. Development, Inc., 124 Cal. Rptr. 2d 227, 101 Cal. App. 4th 430, 67 Cal. Comp. Cases 1023, 2002 Daily Journal DAR 9632, 2002 Cal. Daily Op. Serv. 7687, 2002 Cal. App. LEXIS 4527 (Cal. Ct. App. 2002).

Opinion

Opinion

MALLANO, J.

Plaintiff, an employee of a subcontractor on a construction project, was injured on the job and brought this action against the owner of *434 the property, seeking damages for personal injuries. The property owner moved for summary judgment on the ground that it had not breached a duty to plaintiff. The trial court granted the motion. Plaintiff has appealed.

We conclude that summary judgment was properly granted because this action is barred by the exclusive remedy provisions of the Workers’ Compensation Act, and the property owner did not affirmatively contribute to the cause of plaintiffs injuries.

I

Background

On October 23, 1997, C.G.M. Development, Inc. (CGM), a property owner, entered into a contract with Dekkon Development, Inc., a general contractor, to develop commercial property located at 17232 Railroad Street in the City of Industry. The contract provided in part: “[Dekkon] shall supervise and direct the Work, using its best skill and attention. [Dekkon] shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instructions concerning these matters.”

Dekkon entered into a subcontract with L & E Builders to frame the roof. L & E’s work complied with the architectural plans drafted by the architect, John Cataldo. The materials were supplied by Dekkon (with the exception of nails) in accordance with the general contract, which stated: “Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery . . . and other facilities and services necessary for proper execution and completion of the Work . . . .”

George Sanchez, the construction superintendent and an employee of Dekkon, scheduled the work of the subcontractors and supervised their work. He also reviewed the plan details with the architect, engineers, city inspectors, and the owners of the building. Sanchez wrote daily reports on the progress of the construction. Once a week, he held a safety meeting with the workers. Sanchez was the only construction superintendent on the site; no one worked directly for him; there was no foreman.

Larry Endresen, a partner in L & E, supervised the employees on the roof. Sanchez told Endresen to provide his employees with safety ropes or similar equipment. On June 8, 1998, Endresen brought his crew down from the roof *435 until he could supply them with safety equipment, more specifically, harnesses. Endresen told the employees that they were to wear the harnesses while working in designated areas on the roof. L & E was a licensed contractor but did not have workers’ compensation insurance. In other words, L & E was illegally uninsured. (See Lab. Code, §§ 3700, 3700.5; all further section references are to the Labor Code unless designated otherwise.) 1

Peichin Cheng was a vice-president of COM and represented the company with respect to the construction of the building. Sanchez would contact her when he needed an “owner decision,” namely, anything that was not in the plans. He never said anything to her about the use of safety equipment or that there were any problems with the subcontractors. Between January 19, 1998, and June 11, 1998—a period of almost five months—Cheng visited the site about 12 times, almost always to complain that the project was behind schedule. At no time did Cheng supervise L & E’s employees, nor did she ever tell them how to do their job.

One of L & E’s employees was plaintiff Bias Lopez. On June 18, 1998, Lopez was at his workstation, standing on a wooden platform that was attached to the roof with a metal hanger. He was not wearing a harness or other safety equipment. The metal hanger failed to support the wooden platform, causing Lopez to fall approximately 30 feet onto the concrete floor below. He sustained serious injuries.

In this action, Lopez sued COM on a negligence theory, alleging that it had maintained dangerous working conditions at the jobsite and had not provided Lopez with safety equipment. Other parties were sued on various theories. Several cross-complaints were filed. At some point, a second amended complaint was filed.

On August 28, 2000, COM filed a motion for summary judgment. Lopez and other parties filed opposition papers, contending that COM was liable under the “peculiar risk” doctrine. The parties later filed supplemental papers. On February 9, 2001, the trial court granted the motion, explaining its decision in a three-page order. Judgment was entered in favor of COM. Lopez filed a timely appeal. 2

*436 II

Discussion

Based on the principles governing summary judgment motions and the substantive law applicable to Lopez’s claim, we conclude that CGM was entitled to summary judgment.

A. Summary Judgment

A motion for summary judgment must be granted if all the papers submitted show that there is no triable issue as to any material fact and that the moving party is entitled to judgment as a matter of law. (Code Civ. Proc., § 437c, subd. (c).)

“ ‘A defendant seeking summary judgment has met the burden of showing that a cause of action has no merit if that party has shown that one or more elements of the cause of action cannot be established [or that there is a complete defense to that cause of action], ... In reviewing the propriety of a summary judgment, the appellate court independently reviews the record that was before the trial court. . . . We must determine whether the facts as shown by the parties give rise to a triable issue of material fact. . . . [T]he moving party’s affidavits are strictly construed while those of the opposing party are liberally construed.’ . . . We accept as undisputed facts only those portions of the moving party’s evidence that are not contradicted by the opposing party’s evidence. ... In other words, the facts alleged in the evidence of the party opposing summary judgment and the reasonable inferences therefrom must be accepted as true.” (Jackson v. County of Los Angeles (1997) 60 Cal.App.4th 171, 178-179 [70 Cal.Rptr.2d 96], citations omitted.)

“[F]rom commencement to conclusion, the party moving for summary judgment bears the burden of persuasion that there is no triable issue of material fact and that he is entitled to judgment as a matter of law. That is because of the general principle that a party who seeks a court’s action in his favor bears the burden of persuasion thereon. . . . There is a triable issue of material fact if, and only if, the evidence would allow a reasonable trier of fact to find the underlying fact in favor of the party opposing the motion in accordance with the applicable standard of proof.” (Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 850 [107 Cal.Rptr.2d 841, 24 P.3d 493], citation and fn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holman v. County of Butte
California Court of Appeal, 2025
Holman v. County of Butte CA3
California Court of Appeal, 2025
Colantuono v. Lake CA4/2
California Court of Appeal, 2021
Horne v. Ahern Rentals, Inc.
California Court of Appeal, 2020
Werner v. OneWest Bank Group CA2/6
California Court of Appeal, 2015
Rogers v. Wells Fargo Bank CA1/1
California Court of Appeal, 2015
Katrenick v. Bank of America CA6
California Court of Appeal, 2015
Gallardo v. MTDS, Inc. CA6
California Court of Appeal, 2015
Wm. Jefferson & Co. v. Assessment Appeals Bd.
California Court of Appeal, 2014
William Jefferson & Co. v. Orange County Assessment Appeals Board No. 2
228 Cal. App. 4th 1 (California Court of Appeal, 2014)
San Juan v. PSC Industrial Outsourcing, Inc.
240 P.3d 1026 (Nevada Supreme Court, 2010)
Michael v. Denbeste Transportation, Inc.
40 Cal. Rptr. 3d 777 (California Court of Appeal, 2006)
Bell v. Greg Agee Construction Inc.
23 Cal. Rptr. 3d 33 (California Court of Appeal, 2004)
Hartford Casualty Insurance v. Mt. Hawley Insurance
20 Cal. Rptr. 3d 128 (California Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
124 Cal. Rptr. 2d 227, 101 Cal. App. 4th 430, 67 Cal. Comp. Cases 1023, 2002 Daily Journal DAR 9632, 2002 Cal. Daily Op. Serv. 7687, 2002 Cal. App. LEXIS 4527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lopez-v-cgm-development-inc-calctapp-2002.