Livingston v. Anderson

30 Fla. 117
CourtSupreme Court of Florida
DecidedJune 15, 1892
StatusPublished
Cited by15 cases

This text of 30 Fla. 117 (Livingston v. Anderson) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Livingston v. Anderson, 30 Fla. 117 (Fla. 1892).

Opinion

Mabry, J.:

The first error assigned by appellant is the decision of the court sustaining the demurrer to his plea. The record shows that a replication was first filed to this plea, and subsequently, without regard to the replication. the demurrer was filed. No objection, it appears, was made to this course in the trial court, and no exception is based upon it here. We will consider the demurrer, as it is treated by the parties, as properly filed to the plea.

The suit is instituted upon articles of agreement, under seal, containing mutual covenants on the part [123]*123of appellant and appellee. The declaration alleges performance of all covenants on the part of plaintiff (appellee here), and a failure of performance on the part of appellant in paying the stipulated price for the work to be done. The plea alleges generally “that the plaintiff has not performed and carried out the contract set forth in his declaration, as he agreed to do, and did not perform the work therein mentioned in a faithful and workmanlike manner.” The nineteenth section of Chapter 1096, Laws-of Florida, being an act to amend the pleading and practice in the courts of this State, provides “that it shall be lawful for the plaintiff or defendant in any action to aver performance of conditions precedent generally, and the opposite party shall not deny such averment generally, but shall specify in his pleading the condition, or condition precedent, the performance of which he intends to contest.” Under the terms of the articles of agreement sued on in this case, the performance of the work by appellee was a condition precedent to the payment of the stipidated price by the appellant. This precedent condition required the appellee to perform the work of erecting the building in question according to certain plans and specifications, in a faithful and workmanlike manner. The contract, plans and specifications imposed upon appellee the duty of furnishing all the labor and material, and performing all the work of every kind to complete the building. He alleged generally performance of all his conditions. [124]*124We think the plea is bad. The allegation, that plaintiff has not performed and carried out his contract as he agreed to do, is unquestionably too general, and is prohibited by the statute. The further averment that he did not perform the work-therein mentioned in a faithful and workmanlike manner, does not relieve the plea of the same objection. It is simply a general denial of the averment that plaintiff .had performed all the work in a faithful and workmanlike manner, and under the statute it was necessary for the plea to -specify the particulars wherein the work was not performed in a faithful and workmanlike manner.

The second error assigned is, that the court submitted the cause to the jury “when no issue was joined on plaintiff’s replication to defendant’s first and second pleas, which replication required a demurrer, or a rebutter, to produce an issue.” The first amended plea alleges that plaintiff did not perform the work in a faithful and workmanlike manner, but did the same in an unskillful, unfaithful and unworkmanlike man ner, to the great damage of defendant. And the second alleges that the walls of said building are so unskillful]y and defectively erected as to damage defendant to an amount of not less than three thousand dollars. The reply to these pleas is, that plaintiff, as he has before complained, “has performed and carried out the said contract in all things, except as to those matters and things wherein he was prevented from carrying out and performing by the wrong and default of de[125]*125fendant.” We are not required to pass upon the sufficiency of either the pleas or the replication. No objection of any kind was made in the Circuit Court to their sufficiency. The question is, did the court err in submitting the case to the jury because no issue was joined on the replication to the pleas ? It may be regarded as settled by our decisions that where a plea or subsequent pleading, responsive to a declaration, or former pleading, sets up new matter in avoidance, a reply nmst be made to, or issue joined on, such pleading, without which it will be error to submit the case to the jury for trial. Miller and Croom vs. Hoc, 1 Fla., 189 ; Bendow vs. Marquis & Co., 17 Fla., 441; Livingston vs. L’Engle, Trustee, 22 Fla., 427. And such an error may be taken advantage of in the appellate court. On the other hand, the absence of a similiter to a plea, or subsequent pleading, the office of which is simply to accept an issue tendered, and is really no part of the pleading, will not cause a reversal of a judgment where the parties have voluntarily gone to trial without insisting on it. Huling vs. Florida Savings Bank, 19 Fla., 695. The similiter was used only when the pleading concluded to the contrary, and its office was to join in the issue tendered by the opposite party. If no replication at all had been filed to the pleas we do not see that we could reverse the judgment for want of a formal joinder in issue. The plaintiff alleges in his declaration full performance of conditions in the contract on his part, and defendant replies that plaintiff: has not performed and carried out his contract, in this, that he did not [126]*126perform the work in a faithful and workmanlike manner, and the walls of the building are so defectively erected as to cause defendant damage. The formal conclusions of pleas are not required with us, but if they were, there is nothing in the pleas to prevent the defendant from concluding to the contrary. These pleas tender an issue to the allegation of performance of conditions on the part of the plaintiff. If a demurrer had been interposed by plaintiff to the first plea, no doubt it would have been sustained, because the plea does not specify the particulars wherein the plaintiff did not perform the work in a workmanlike manner. We think the replication filed by the plaintiff below can have no other effect than to join issue on the pleas. It alleges that plaintiff, as he has before complained, has performed and carried out his contract in all things. It is true that there is a qualification added to the replication in the nature of an exception as to those matters and things wherein plaintiff was prevented from performing, by the wrong and default of defendant. This exception, however, does not amount to any reply to the pleas of defendant, nor can it be regarded as a good replication setting up new matter in confession and avoidance. If the purpose of the plaintiff was to set up by this replication an excuse for non-performance of the contract on his part on account of the acts and interference of the defendant, it is evident that there would be a departure in pleading on his part. In his declaration he alleges full performance of covenants, and a failure of performance of the part of defendant. The plaintiff [127]*127would not have a right to recover upon a new cause of action alleged the first time in his replication to defendant’s pleas. Hooker vs. Johnson, 10 Fla., 198. The clause in the latter part of the replication, “ except as to those matters and things wherein he was prevented from carrying out and performing by the wrong and default of defendant,” does not allege in what respect plaintiff was prevented from performing his contract by the wrong or default of defendant. We do not regard this replication as such a pleading setting up new matter as to require a rejoinder to form an issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryan and Sons Corp. v. Klefstad
237 So. 2d 236 (District Court of Appeal of Florida, 1970)
Knabb v. Reconstruction Finance Corporation
197 So. 707 (Supreme Court of Florida, 1940)
Hazen v. Cobb-Vaughan Motor Co.
117 So. 853 (Supreme Court of Florida, 1928)
Holman Livestock Co. v. Louisville & Nashville Railroad
81 Fla. 194 (Supreme Court of Florida, 1921)
Carlton-Moore Co. v. Vanderipe
86 So. 346 (Supreme Court of Florida, 1920)
Florida East Coast Railway Co. v. Carter
65 So. 254 (Supreme Court of Florida, 1914)
Franklin Phosphate Co. v. International Harvester Co. of America
62 Fla. 185 (Supreme Court of Florida, 1911)
Globe Theatre & Amusement Co. v. Watt
62 Fla. 196 (Supreme Court of Florida, 1911)
Supreme Lodge Knights of Pythias v. Lipscomb
50 Fla. 406 (Supreme Court of Florida, 1905)
Muller v. Ocala Foundry & Machine Works
49 Fla. 189 (Supreme Court of Florida, 1905)
Southern Pine Co. v. Powell
48 Fla. 154 (Supreme Court of Florida, 1904)
Frank Herman & Co. v. Williams
36 Fla. 136 (Supreme Court of Florida, 1895)
St. Johns & Halifax Railroad v. Shalley
33 Fla. 397 (Supreme Court of Florida, 1894)
South Florida Railroad v. Weese
32 Fla. 212 (Supreme Court of Florida, 1893)
American Lead Pencil Co. v. F. A. Wolfe & Co.
30 Fla. 360 (Supreme Court of Florida, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
30 Fla. 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/livingston-v-anderson-fla-1892.