L.G. Lefler, Inc., D/B/A Defco Construction Company v. The United States

801 F.2d 387, 33 Cont. Cas. Fed. 74,605, 1986 U.S. App. LEXIS 20341, 8 I.T.R.D. (BNA) 1401
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 16, 1986
DocketAppeal 86-800
StatusPublished
Cited by14 cases

This text of 801 F.2d 387 (L.G. Lefler, Inc., D/B/A Defco Construction Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.G. Lefler, Inc., D/B/A Defco Construction Company v. The United States, 801 F.2d 387, 33 Cont. Cas. Fed. 74,605, 1986 U.S. App. LEXIS 20341, 8 I.T.R.D. (BNA) 1401 (Fed. Cir. 1986).

Opinion

DAVIS, Circuit Judge.

L.G. Lefler, Inc., doing business as Defco Construction Company (Defco), prevailed in the Claims Court on its contract suit. 6 Cl.Ct. 514 (1984). The Government took no appeal from that decision. Defco then sought attorney fees and expenses under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412. In an unpublished order, the Claims Court (Seto, J.) granted fees and expenses. No. 681-83C (Oct. 30, 1985). The Government appeals, but we affirm on the ground that Defco met the EAJA standards for receiving such fees and expenses from the Government.

I.

In July 1982 the Veterans Administration (VA) invited bids for construction of an addition to the VA Medical Center in Tucson, Arizona. Defco erroneously interpreted the bid documents as permitting the use of foreign materials provided the cost of comparable domestic materials exceeded the foreign cost by at least 6%. Defco bid on that basis — including a substantial amount of structural steel fabricated in Japan. On opening of the bids, Defco was adjudged the low bidder and the contract was awarded to it on September 30, 1982.

At a preconstruction conference on October 14,1982, Defco was told that no non-domestic products could be used on the project because none had been identified in its bid, as required by the Buy American Act. It was too late to cancel the steel order with the Japanese supplier, and Def-co informed the VA (in October and November 1982) that it intended to use the foreign steel and documented the fact that that steel was more than 6% lower than *388 that of domestic steel. Defco requested a waiver of the Buy American Act under the regulations, and this was granted by the VA Administrator. 1

At the same time, the VA decided to impose a credit against the contract price— because, it was said, of Defco’s violation of the Buy American Act in casting its bid on the basis of foreign steel, without saying so. Accordingly, the contracting officer treated the VA’s waiver as imposing a contract change and asked Defco to submit an equitable adjustment decreasing the contract price because of the permission given it to use the foreign steel. In July 1983, a unilateral change order was issued decreasing the contract price by $108,000. 2 Defco sought review of that unilateral decision, under the Contract Disputes Act, by filing a “direct access” suit in the Claims Court. On cross-motions for summary judgment, the Claims Court (Seto, J.) held for Defco and entered judgment in its favor for $108,-000. 6 Cl.Ct. 514 (1984). The gist of the court’s ruling was that (a) Defco’s cost of performance was not lowered by the waiver of the Buy American Act’s requirements; (b) Defco would have been the low bidder even if it had bid entirely on domestic materials; (c) the regulatory standards for waiver of the Buy American Act’s requirements were clearly met; and (d) Defco did not receive any benefit or obtain any unfair advantage from its original violation of the Buy American Act. As we have said, the Government did not appeal this ruling.

The current appeal relates to Defco’s fee application which followed upon its victory in the contract suit. Judge Seto awarded $26,321.76.

II.

The EAJA authorizes a fee award to a “prevailing party” unless the position of the Government “was substantially justified or that special circumstances make an award unjust.” 28 U.S.C. § 2412(d)(1)(A). As recently amended, the Act directs that, in making the determination of substantial justification vel non, courts should take account, not only of the Government’s litigation position in court, but also of the record with respect to the “action or failure to act by the agency upon which the civil action is based.” 28 U.S.C. § 2412(d)(1)(B) and § 2412(d)(2)(D) (Supp. III 1985). Gavette v. Office of Personnel Management, 785 F.2d 1568, 1579 (Fed.Cir.1986) (in banc), holds that, to be substantially justified, the Government’s position must be “clearly reasonable in asserting its position, including its position at the agency level, in view of the law and the facts” (emphasis in original).

There is no doubt, and no question, that Defco was the “prevailing party”; the Claims Court held it entitled to all the relief it requested. See Keely v. Merit Systems Protection Board, 793 F.2d 1273, 1275 (Fed.Cir.1986); Keely v. Merit Systems Protection Board, 760 F.2d 246, 248 (Fed.Cir.1985); Austin v. Department of Commerce, 742 F.2d 1417, 1419-20 (Fed.Cir.1984). The only issues are whether the Government’s position was “substantially justified” or whether “special circumstances make an award unjust.”

In this appeal the United States stresses the latter standard, urging, first, that this contract case presented a legal issue of first impression involving the relationship of the regulation implementing the Buy American Act with the Changes clause in the contract, and, second, that the Comp *389 troller General had earlier taken a parallel position in cases the Government deemed similar. We are also directed to the House Committee’s reason why the alternative standard — where “special circumstances make an award unjust” — was included in the EAJA:

This “safety valve” helps to insure that the Government is not deterred from advancing in good faith the novel but credible extensions and interpretations of the law that often underlie vigorous enforcement efforts. It also gives the court discretion to deny awards where equitable considerations dictate an award should not be made.

H.R.Rep. No. 1418, 96th Cong., 2d Sess. 11, reprinted in 1980 U.S. Code Cong. & Ad. News 4958, 4984, 4990. It is said that here both the VA and the Government’s litigators in the Claims Court advanced in good faith a novel but credible position which deserved ventilation.

In the circumstances of this case, we reject this contention that it would be unjust to award fees or that the Government’s position was substantially justified. In doing so, we follow the established rule that the Claims Court’s factual findings (in its ruling on the merits and its Memorandum Order on fees and expenses) must be accepted unless clearly erroneous. Alger v. United States, 741 F.2d 391, 394-95 (Fed.Cir.1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conquistador Dorado Joint Venture
Armed Services Board of Contract Appeals, 2024
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)
Information Sciences Corp. v. United States
86 Fed. Cl. 269 (Federal Claims, 2009)
Brickwood Contractors, Inc. v. United States
49 Fed. Cl. 148 (Federal Claims, 2001)
Swiney v. Gober
14 Vet. App. 65 (Veterans Claims, 2000)
Felton v. Brown
7 Vet. App. 276 (Veterans Claims, 1994)
American Air Parcel Forwarding Co. v. United States
697 F. Supp. 505 (Court of International Trade, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
801 F.2d 387, 33 Cont. Cas. Fed. 74,605, 1986 U.S. App. LEXIS 20341, 8 I.T.R.D. (BNA) 1401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lg-lefler-inc-dba-defco-construction-company-v-the-united-states-cafc-1986.