L.G. Lefler, Inc. v. United States

32 Cont. Cas. Fed. 73,039, 6 Cl. Ct. 514, 6 I.T.R.D. (BNA) 1922, 1984 U.S. Claims LEXIS 1270
CourtUnited States Court of Claims
DecidedOctober 30, 1984
DocketNo. 681-83C
StatusPublished
Cited by5 cases

This text of 32 Cont. Cas. Fed. 73,039 (L.G. Lefler, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.G. Lefler, Inc. v. United States, 32 Cont. Cas. Fed. 73,039, 6 Cl. Ct. 514, 6 I.T.R.D. (BNA) 1922, 1984 U.S. Claims LEXIS 1270 (cc 1984).

Opinion

ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

OPINION

SETO, Judge.

In this suit brought under the Contract Disputes Act of 1978, 41 U.S.C. § 609 (Supp.1984), plaintiff seeks review of the decision of a Veteran’s Administration (“VA”) Contracting Officer, approving a credit, taken by the VA under the changes clause of the contract in question, for plaintiff’s use of nondomestic structural steel. The credit followed a post-award waiver of the Buy American Act. The issue to be resolved is whether the reduction in contract price is warranted under the specific circumstances of this case. For the reasons stated below, plaintiff’s motion for summary judgment is granted, defendant’s cross-motion for summary judgment is denied, and judgment is to be entered for plaintiff in the amount of $108,000.00.

FACTS

On July 7, 1982, the VA issued an Invitation for Bids for the construction of an addition to the VA Medical Center in Tuscon, Arizona. As a contractor unsophisticated in the bidding process for government contracts, plaintiff, L.G. Lefler, Inc., d/b/a Defco Construction Company (“Def-co”), interpreted the bid documents as permitting the use of foreign materials as the basis for its bid, provided the cost of comparable domestic material exceeded the cost of the foreign material by at least six percent (6%). Proceeding on this basis, Defco submitted a bid to the VA totalling $11,331,500, of which $1,028,000 was for structural steel work. The structural steel price was based on a bid received by Defco from the Phoenix Steel Manufacturing Company (“Phoenix”) of $737,000, which partly was based on $439,000 worth of wide flange structural steel fabricated in Japan. Because the lowest quoted price for comparable domestic steel was $108,000 (24.6%) higher than the price quoted by Phoenix for Japanese steel, Defco assumed that its bid to the VA could incorporate the price for foreign steel.

Following a pre-bid conference on July 29, 1982, the bids were opened on August 18, 1982. Defco’s bid was adjudged to be the low bid by $365,554 and the contract was awarded to Defco on September 30, 1982.

At a preconstruction conference on October 14, 1982, Defco was advised that no nondomestic products could be used on the [517]*517project because none had been identified in its bid, as required by the Buy American Act (“BAA”). Because it was no longer possible to cancel the order placed with the Japanese supplier, Defco met with the VA again on October 28, 1982, to indicate its intent to use nondomestic steel. On November 5,1982, Defco submitted a letter to the VA documenting the fact that the cost of the nondomestic steel upon which its bid was based was more than 6% lower than the cost of domestic steel and requesting a waiver of the applicable provisions of the Buy American Act.

Following the advice of the VA’s General Counsel, the VA Administrator approved a waiver of the BAA on January 20, 1983, thereby authorizing Defco to use the non-domestic steel on the project. However, to “deny the contractor any benefit from violating the Buy American Act,” the VA imposed a credit against the contract price for Defco’s use of the foreign steel. To implement this decision, the VA Contracting Officer issued Proceed Order No. 1 on February 24, 1983, characterizing the use of non-domestic steel as a change in work governed by Clause 3 (Changes Clause) of the contract. The Proceed Order requested Defco to submit a proposal for an equitable adjustment in the contract price, noting that the contract price would be decreased by $108,000 pending issuance of a change order.

On March 21, 1983, the Office of the Inspector General (“IG”) at the VA completed a special report delineating the facts and circumstances regarding the decision to waive the Buy American Act. The IG Report indicates that (1) there is no evidence Defco received a direct financial gain by using foreign steel, (2) the evidence submitted establishes that Defco’s bid was based on the cost of foreign steel, and (3) Defco would have remained the lowest bidder even if it had based its bid on the higher cost of domestic steel.

After evaluating Defco’s certified claim of April 27, 1983, the Contracting Officer issued a final decision on July 20, 1983. In denying Defco’s claim, the Contracting Officer indicated that the $108,000 reduction in contract price was necessary “to negate any unfair advantage you and your subcontractors may have gained by incorrectly basing your bid on nondomestic steel.” On July 29, 1983, the Contracting Officer issued a unilateral change order implementing his final decision and decreasing the contract price by $108,000. Defco filed its action in this court on November 10, 1983, seeking relief as requested in its certified claim.

DISCUSSION

At oral argument on October 4, 1984, counsel for plaintiff conceded that Defco was in violation of the Buy American Act until it received a waiver from the VA Administrator on January 20, 1983. However, plaintiff contests the propriety of the subsequent credit, taken by the VA under the auspices of the changes clause of the contract, for Defco’s use of the foreign steel covered by the waiver. Plaintiff contends that there is no basis in law or equity for the imposition of such a credit. Defendant rejoins that the equitable adjustment to the contract price is appropriate because the VA was entitled to receive domestic steel under the contract terms and that the subsequent change order permitting the use of foreign steel decreased plaintiff’s cost of performance.1 Defendant further contends that the $108,000 credit was necessary to preclude plaintiff from deriving any profit from its violation of the Buy American Act, and to protect the competitive bidding process and the public interest.2

In implementing the waiver of the BAA, the VA contracting officer issued Proceed Order No. 1 “in accordance with Clause 3 of the General Provisions of the Contract”, and stated that “the matter of contract price and time will be subject to equitable adjustment as provided therein.” The [518]*518change order of July 29, 1983, reflecting the contracting officer’s final decision, effected a decrease in the contract price of $108,000 — the difference between the cost of the domestic and foreign steel. Clause 3 of the contract reads, in pertinent part, as follows:

(d) If any change under this clause causes an increase or decrease in the contractor’s cost of ... the performance of any part of the 'work under the contract, ... an equitable adjustment shall be made

Therefore, before the contract price can be decreased, there must exist a concommi-tant decrease in the contractor’s cost of performance resulting from the change order.

In the instant ease, there is no evidence that the change order effected a decrease in plaintiff’s cost of performance so as to warrant the claimed equitable adjustment. The evidence submitted, including the report of the Inspector General of the VA, indicates that plaintiff based its bid on the lower cost of the foreign steel.3 Because the original contract price, as bid by plaintiff, incorporates the price of the foreign steel, a later change order permitting its use does not decrease plaintiff’s cost of performance. As a result, the changes clause, by itself, does not entitle defendant to an equitable adjustment in the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John C. Grimberg Company, Inc. v. The United States
869 F.2d 1475 (Federal Circuit, 1989)
Blinderman Construction Co. v. United States
34 Cont. Cas. Fed. 75,516 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,039, 6 Cl. Ct. 514, 6 I.T.R.D. (BNA) 1922, 1984 U.S. Claims LEXIS 1270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lg-lefler-inc-v-united-states-cc-1984.