KENNETH K. HALL, Circuit Judge.
This civil action was brought under Section 301 of the Labor Management Relations Act of 1947, 29 U.S.C. § 185(a), by Local 217 of the International Chemical Workers Union (“Union”) against Lever Brothers Company (“Company”) seeking injunctive relief to prevent the Company from transferring its Baltimore, Maryland, soap production operation to Hammond, Indiana, until the Company complied with what the Union contended were certain specified contractual prerequisites to the move. The District Court granted a temporary restraining order and then a preliminary injunction enjoining the plant relocation pending the completion of arbitration to construe certain terms of the labor contract and conditioned recovery on the injunction bond upon a determination by the District Court, the Court of Appeals, or the Supreme Court of the United States that the Company had been wrongfully enjoined or restrained.
The Company unsuccessfully moved to dissolve the injunction, the Union initiated grievance was found to be arbitrable, and an award was rendered in favor of the Company. The preliminary injunction expired, as ordered, and the Company presumably has relocated its plant facility. The Company appeals seeking a determination that the preliminary injunction was wrongfully issued, and also seeks a determination that the injunction bond should have been conditioned on the outcome of the arbitration. We affirm.
Three issues are involved in this appeal. They are: (1) whether the grievance filed by the Union should have been submitted to the arbitrator in accordance with the terms of the collective bargaining agreement; (2) whether the District Court properly issued the preliminary injunction in order to maintain the
status quo
pending the completion of arbitration; and (3) whether the District Court properly conditioned the security required by F.R.C.P. 65(c) to be provided by the Union based upon whether or not the Company should be found to have been wrongfully enjoined or restrained, instead of conditioning it upon the Company’s success or failure on the merits of the arbitration.
I
ARBITRABILITY
The Company and the Union had entered into a collective bargaining agreement covering its plant located at Baltimore, Maryland. On October 28, 1975, the Company advised the Union that it was
permanently
closing its Baltimore plant and
transferring
that production to its Hammond, Indiana facility which was represented by the Oil, Chemical and Atomic Workers union.
The Union argued that since the Hammond plant was represented by a union other than the International Chemical Workers, then the Company action constituted “outside contracting” under the collective bargaining agreement, and the Union was entitled to “due consideration” before the actual assignment of work to the outside contractors (i. e. the transfer to Indiana) occurred.
The Company argued that the transfer was an “elimination” under the collective bargaining agreement.
requiring only two weeks written notice to the Union in advance of the move, which notice it had given. Thus, the release of “full information,” necessary when there was a “contracting out,” was not required.
Section 6.9, the grievance-arbitration clause, provided:
“Grievances within the meaning of the Grievance procedure and of this arbitration clause shall consist only of disputes about the interpretation or application of particular clauses of this Agreement and about alleged violations of the Agreement. The Arbitrator shall have no power to add to, or subtract from, or modify any of the terms of this Agreement, nor shall he substitute his discretion for that of the Company or the Union where such discretion has been retained by the Company or the Union, nor shall he exercise any responsibility or function of the company or the Union.”
On November 14, 1975, the Union filed a grievance concerning the pending plant transfer, contended that it was “contracting out” rather than an “elimination” of work, and requested that the Company refrain from moving the plant until the “due consideration-full information” contractual prerequisites were met. The Company denied the grievance and this litigation ensued.
On appeal, the parties agree that the District Court initially had to determine whether the dispute was subject to arbitration under the collective bargaining agreement.
International Union of Operating Engineers, Local 150 v. Flair Builders, Inc.,
406 U.S. 487, 92 S.Ct. 1710, 32 L.Ed.2d 248 (1972), but they disagree that the issue presented was arbitrable.
The Union contends that its grievance concerned the interpretation of various clauses of the Agreement and was arbitrable. The Company contends that the District Court too readily found arbitrability and failed to determine first, what the dispute was, and second, whether the parties had contractually agreed to submit such a dispute to arbitration.
We hold that the District Court correctly determined, first, that a dispute
did exist between the Company and the Union regarding the characterization of the plant transfer as an “elimination” or as “contracting out.” Second, we hold that the District Court properly analyzed the parallels which existed between the broad arbitration clause in
United Steelworkers of America v. Warrior & Gulf Navigation Co.,
363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960),
and the above-quoted arbitration clause in this case, between the management rights clause in
Warrior &
Gulf
and language of similar import in this case,
and correctly concluded that neither the contract in
Warrior & Gulf,
nor the contract in this case expressly excluded a particular grievance from arbitration. Thus, the District Court correctly held the grievance in this case to be a matter for consideration by the arbitrator. In this case, it cannot be said with positive assurance that the arbitration clause was not susceptible of an interpretation that covered the asserted dispute.
United Steelworkers of America v. Warrior & Gulf Navigation Co.,
363 U.S. 574, 582-3, 80 S.Ct. 1347. The question of the interpretation of the collective bargaining agreement was properly left to the arbitrator, and not predetermined by the Court on the ruling on the preliminary injunction.
United Steelworkers of America v. Enterprise Wheel & Car Corp.,
Free access — add to your briefcase to read the full text and ask questions with AI
KENNETH K. HALL, Circuit Judge.
This civil action was brought under Section 301 of the Labor Management Relations Act of 1947, 29 U.S.C. § 185(a), by Local 217 of the International Chemical Workers Union (“Union”) against Lever Brothers Company (“Company”) seeking injunctive relief to prevent the Company from transferring its Baltimore, Maryland, soap production operation to Hammond, Indiana, until the Company complied with what the Union contended were certain specified contractual prerequisites to the move. The District Court granted a temporary restraining order and then a preliminary injunction enjoining the plant relocation pending the completion of arbitration to construe certain terms of the labor contract and conditioned recovery on the injunction bond upon a determination by the District Court, the Court of Appeals, or the Supreme Court of the United States that the Company had been wrongfully enjoined or restrained.
The Company unsuccessfully moved to dissolve the injunction, the Union initiated grievance was found to be arbitrable, and an award was rendered in favor of the Company. The preliminary injunction expired, as ordered, and the Company presumably has relocated its plant facility. The Company appeals seeking a determination that the preliminary injunction was wrongfully issued, and also seeks a determination that the injunction bond should have been conditioned on the outcome of the arbitration. We affirm.
Three issues are involved in this appeal. They are: (1) whether the grievance filed by the Union should have been submitted to the arbitrator in accordance with the terms of the collective bargaining agreement; (2) whether the District Court properly issued the preliminary injunction in order to maintain the
status quo
pending the completion of arbitration; and (3) whether the District Court properly conditioned the security required by F.R.C.P. 65(c) to be provided by the Union based upon whether or not the Company should be found to have been wrongfully enjoined or restrained, instead of conditioning it upon the Company’s success or failure on the merits of the arbitration.
I
ARBITRABILITY
The Company and the Union had entered into a collective bargaining agreement covering its plant located at Baltimore, Maryland. On October 28, 1975, the Company advised the Union that it was
permanently
closing its Baltimore plant and
transferring
that production to its Hammond, Indiana facility which was represented by the Oil, Chemical and Atomic Workers union.
The Union argued that since the Hammond plant was represented by a union other than the International Chemical Workers, then the Company action constituted “outside contracting” under the collective bargaining agreement, and the Union was entitled to “due consideration” before the actual assignment of work to the outside contractors (i. e. the transfer to Indiana) occurred.
The Company argued that the transfer was an “elimination” under the collective bargaining agreement.
requiring only two weeks written notice to the Union in advance of the move, which notice it had given. Thus, the release of “full information,” necessary when there was a “contracting out,” was not required.
Section 6.9, the grievance-arbitration clause, provided:
“Grievances within the meaning of the Grievance procedure and of this arbitration clause shall consist only of disputes about the interpretation or application of particular clauses of this Agreement and about alleged violations of the Agreement. The Arbitrator shall have no power to add to, or subtract from, or modify any of the terms of this Agreement, nor shall he substitute his discretion for that of the Company or the Union where such discretion has been retained by the Company or the Union, nor shall he exercise any responsibility or function of the company or the Union.”
On November 14, 1975, the Union filed a grievance concerning the pending plant transfer, contended that it was “contracting out” rather than an “elimination” of work, and requested that the Company refrain from moving the plant until the “due consideration-full information” contractual prerequisites were met. The Company denied the grievance and this litigation ensued.
On appeal, the parties agree that the District Court initially had to determine whether the dispute was subject to arbitration under the collective bargaining agreement.
International Union of Operating Engineers, Local 150 v. Flair Builders, Inc.,
406 U.S. 487, 92 S.Ct. 1710, 32 L.Ed.2d 248 (1972), but they disagree that the issue presented was arbitrable.
The Union contends that its grievance concerned the interpretation of various clauses of the Agreement and was arbitrable. The Company contends that the District Court too readily found arbitrability and failed to determine first, what the dispute was, and second, whether the parties had contractually agreed to submit such a dispute to arbitration.
We hold that the District Court correctly determined, first, that a dispute
did exist between the Company and the Union regarding the characterization of the plant transfer as an “elimination” or as “contracting out.” Second, we hold that the District Court properly analyzed the parallels which existed between the broad arbitration clause in
United Steelworkers of America v. Warrior & Gulf Navigation Co.,
363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960),
and the above-quoted arbitration clause in this case, between the management rights clause in
Warrior &
Gulf
and language of similar import in this case,
and correctly concluded that neither the contract in
Warrior & Gulf,
nor the contract in this case expressly excluded a particular grievance from arbitration. Thus, the District Court correctly held the grievance in this case to be a matter for consideration by the arbitrator. In this case, it cannot be said with positive assurance that the arbitration clause was not susceptible of an interpretation that covered the asserted dispute.
United Steelworkers of America v. Warrior & Gulf Navigation Co.,
363 U.S. 574, 582-3, 80 S.Ct. 1347. The question of the interpretation of the collective bargaining agreement was properly left to the arbitrator, and not predetermined by the Court on the ruling on the preliminary injunction.
United Steelworkers of America v. Enterprise Wheel & Car Corp.,
363 U.S. 593, 599, 80 S.Ct. 1358, 4 L.Ed.2d 1424 (1960);
Buffalo Forge Co. v. United Steelworkers of America, AFL-CIO,
428 U.S. 397, 96 S.Ct. 3141, 3148-3149, 49 L.Ed.2d 1022 (1976).
II
THE INJUNCTION PENDING ARBITRATION
Before issuing the preliminary injunction, the court below analyzed the prerequisites to the issuance of injunctive relief and concluded that as to the first prerequisite, the Union had shown a “probable right,” that is, a likelihood that the Union would prevail at a trial on the merits.
The court equated this with the likelihood that the Union would prevail in its contention that the dispute in issue was one for the arbitrator. Thus, the preliminary injunction was issued halting the transfer of the plant and insuring the maintenance of the
status quo
until the arbitration could be completed.
The Union contends that the injunction properly issued to protect its contractual right to arbitrate grievances and had it prevailed in the arbitration, it would have been provided with “full information” regarding the reasons for the transfer and would have marshalled economic evidence to attempt to persuade the Company not to make the transfer. Thus, the injunction preserved the
status quo
in order to save the arbitration clause. See:
Amalgamated
Transit Union, Division 1384 v. Greyhound Lines, Inc.,
529 F.2d 1073 (9th Cir. 1976).
1he Company contends that although injunctive relief may have appropriately issued to require arbitration, it was inappropriate to
also
enjoin the transfer of the plant, since the arbitrator could not halt the transfer and only could require compliance with the “Shorey” letter
relying upon
Hoh v. Pepsico, Inc.,
491 F.2d 556 (2nd Cir. 1974).
We find the reasoning in
Greyhound Lines, supra,
a case with similar facts to the case
sub judice,
more persuasive than that contained in
Pepsico,
and hold, as did the court in
Greyhound Lines,
that:
“. . . a plaintiff, without regard to whether he is the employer or the union, seeking to maintain the status quo pending arbitration pursuant to the principles of
Boys Markets [Inc., v. Retail Clerks Union,
398 U.S. 235, 90 S.Ct. 1583, 26 L.Ed.2d 199 (1970)] need only establish that the position he will espouse in arbitration is sufficiently sound to prevent the arbitration from being a futile endeavor. If there is a genuine dispute with respect to an arbitrable issue, the barrier [to the issuance of an injunction] we believe appropriately sic] has been cleared.” (529 F.2d 1073, 1077-1078).
The District Judge did not abuse his discretion by issuing the preliminary injunction preserving the
status quo
until the completion of the pending arbitration.
HI
THE CONDITIONS OF THE BOND
The District Court conditioned the issuance of the preliminary injunction upon the Union filing a bond in the amount of $60,000 as security for the payment of such costs and damages as may have been incurred or suffered by the Company should it later have been determined by the District Court, the Court of Appeals, or the Supreme Court of the United States that the Company had been wrongfully enjoined or restrained. See Rule 65(c) of the Federal Rules of Civil Procedure.
The Company contends that the bond should have been conditioned upon the outcome of the merits of the arbitration and not left for determination by the courts.
We hold that the District Court correctly conditioned the injunction bond upon the possible wrongful issuance of the preliminary injunction, and not upon the outcome of the merits of the arbitration. Rule 65(c) of the Federal Rules of Civil Procedure does not stand as authority that injunction bonds in labor cases are to be conditioned on the outcome of the merits of arbitration. Rather, it is settled that the recoverable damages under such a bond are those that arise from the operation of the injunction itself and not from damages occasioned by the suit independently of the injunction.
Greenwood County v. Duke Power Co.,
107 F.2d 484, 489 (4th Cir. 1939);
Amalgamated Transit Union, Division 1384 v. Greyhound Lines,
529 F.2d 1073, 1079 (9th Cir. 1976); 7 J. Moore,
Moore’s Federal Practice,
¶ 65.10[1], 65-96, 97 (1975); 11 C. Wright & A. Miller,
Federal Practice and Procedure,
§ 2973, 652-654 (1973).
We are in agreement with the Third and Ninth Circuits that an injunction bond posted in a
Boys
Markets
case is payable only if the preliminary injunction is found to have been wrongfully issued, where, for example, the court erroneously issues a preliminary injunction over a labor dispute not
covered by the grievance-arbitration provisions of the contract.
See, Amalgamated Transit Union, Division 1384 v. Greyhound Lines,
529 F.2d 1073, 1079 (9th Cir. 1976);
United States Steel Corporation v. United Mine Workers of America,
456 F.2d 483, 488 (3rd Cir. 1972). Further, as the court noted in
Greyhound Lines,
to accept the Company’s contention that the bond should be contingent upon the merits of the arbitration in this case would be inconsistent with our holding in Part II
supra
that a showing by the Union of probable success in the arbitration is not necessary in order to obtain a
Boys Market
preliminary injunction.
Amalgamated Transit Union, Division 1384 v. Greyhound Lines,
529 F.2d 1073, 1077.
We add only that the parties to the collective bargaining agreement did not agree to indemnify one another contingent upon the outcome of arbitration. rather, they agreed to arbitrate. As we have held in Parts I and II of this opinion, the preliminary injunction was properly issued pending arbitration over an arbitrable dispute, and therefore was not wrongfully issued. The requirement that the injunction bond be posted in accordance with Rule 65(c), F.R. C.P., was correct, and the action of the District Court is
AFFIRMED.
ADDENDUM TO OPINION
Following the decision by the panel in this case on November 30, 1976, Lever Brothers filed a petition for rehearing and a suggestion for a rehearing
en banc.
In part II of the panel opinion dealing with the injunction pending arbitration, and also in part III of the opinion dealing with the conditions of the bond, this court relied upon
Amalgamated Transit Union, Division 1384 v. Greyhound Lines, Inc.,
529 F.2d 1073 (9th Cir. 1976), finding the reasoning in that case as to both points more persuasive than that contained in
Hoh v. Pepsico, Inc.,
491 F.2d 556 (2d Cir. 1974).
Unbeknownst to counsel, on the day oral argument was heard in this case, the Supreme Court granted certiorari in
Greyhound Lines,
vacated the judgment in that case and remanded it to the United States Court of Appeals for the Ninth Circuit “for further consideration in light of
Buffalo Forge Co. v. United Steelworkers of America,
428 U.S. 397, 96 S.Ct. 3141, 49 L.Ed.2d 1022 (1976).”
See Greyhound Lines, Inc.
v.
Amalgamated Transit Union, Division 1384,
429 U.S. 807, 97 S.Ct. 43, 50 L.Ed.2d 68 (1976).
Accordingly, this court entered an order deferring consideration of the petition for rehearing and the suggestion for rehearing
en banc
filed by Lever Brothers pending the receipt and review of supplemental briefs to be filed by counsel, and thereafter until further order of this court. The supplemental briefs have been filed.
As heretofore noted, the Ninth Circuit reconsidered its previous ruling and has reversed itself, holding:
There being neither an express nor implied in fact promise by Greyhound to preserve the status quo, the injunction to preserve it pending arbitration was improperly entered.
Amalgamated Transit Union, Division 1384 v. Greyhound Lines, Inc.,
550 F.2d 1237 at 1239 (9th Cir. 1977), hereinafter Greyhound Lines II.
Lever Brothers of course places great reliance on
Greyhound Lines II,
and basically sets forth two
contentions which it be
lieves justifies reversal of the original panel opinion. We adhere to our previous opinion.
First. Lever Brothers argues that
Buffalo Forge
was incorrectly applied by the panel in our earlier decision, and that the issuance of a preliminary injunction to preserve the
status quo
pending arbitration is explicitly barred by the
Buffalo Forge
doctrine absent an actual agreement
to preserve the
status quo. See Greyhound Lines II, supra.
Again, upon the facts of the instant case, we disagree.
The district court correctly issued the preliminary injunction to preserve the
status quo
pending the completion of arbitration. It did not order the plant moved to Indiana. It did not order the plant to remain in Baltimore. It simply preserved a status of neutrality so the parties could arbitrate the underlying differences between them as to the interpretation of the collective bargaining agreement. Had the district court not preserved the
status quo,
Lever Brothers would have
permanently transferred
their plant from Baltimore, Maryland, to Hammond, Indiana. If the union then prevailed in the arbitration, they would have had a double burden to satisfy —first, to convince the company that it should not have moved the plant to Hammond, Indiana — a
fait accompli,
and then it would have had the burden to convince the company to move the plant back to Baltimore, Maryland. The arbitration in this sense would undoubtedly have been “but an empty victory” for the union.
See Brotherhood of Locomotive Engineers v. Missouri-Kansas-Texas Railway Co.,
363 U.S. 528, 534-535, 80 S.Ct. 1326, 4 L.Ed.2d 1435 (1960).
A comparison of the effect of the decision in
Greyhound Lines
versus the decision in the instant case demonstrates the injury which would occur to the arbitral process if the permanent transfer of the plant was permitted in this case pending arbitration.
In
Greyhound Lines,
the issue concerned a change of work schedules for existing employees who were employed by a bus line. Whether or not Greyhound was permitted to unilaterally alter the work schedules of its employees under the collective bargaining agreement, the employees would still be employed, and still earn wages albeit on different schedules. In his award, the arbitrator
could
subsequently alter pay schedules or revise the work schedules depending on whether he found for the union or the company and return the parties to substantially the
status quo ante.
In the instant case, had there not been an injunction pending arbitration to preserve the
status quo,
the employees at the Baltimore plant
would have been totally and permanently deprived of their employment,
and, as above noted, if the union prevailed at the arbitration, would have had a double burden of convincing the company not only not to move, which it had already done, but to return the plant. It was incumbent upon upon the union to prevail at arbitration, obtain the “full information” which they sought, and then seek to convince the company not to move its plant.
The reasonableness of our holding is consonant with the Ninth Circuit decision in
Greyhound Lines II
wherein that court also recognized that:
[ i]n any event, it is clear that in this case the arbitration of the dispute will be unaffected by Greyhound’s alteration of the status quo. Should Greyhound be wrong in its position in arbitration the situation can be restored substantially to the status quo
ante. Cf. Boys Markets, Inc. v. Retail Clerks Union,
398 U.S. 235, 90 S.Ct. 1583, 26 L.Ed.2d 199 (1970).
(Greyhound Lines II, supra,
550 F.2d 1237 at 1239).
Further, the rule contained in this case is obviously a two-sided coin. An injunction to preserve the
status quo
pending arbitration may be issued either against a company or against a union in an appropriate
Boys Markets
case where it is necessary to prevent conduct by the party enjoined from rendering the arbitral process a hollow formality in those instances where, as here, the arbitral award when rendered could not return the parties substantially to the
status quo ante.
Further, it should be noted that the
policy
espoused in
Buffalo Forge
supports rather than defeats the previous panel decision because of the concern which it expresses for judicial non-interference in the arbitral process. Questions concerning the interpretation of collective bargaining agreements are properly left to the arbitrators, and should not be predetermined by the courts on their rulings on the preliminary injunctions. This has long been the policy of the federal courts.
See United Steelworkers of America v. Enterprise Wheel and Car Corp.,
363 U.S. 593, 599, 80 S.Ct. 1358, 4 L.Ed.2d 1424 (1960);
Buffalo Forge Co. v. United Steelworkers of America,
428 U.S. 397, 96 S.Ct. 3141, 3148-3149, 49 L.Ed.2d 1022 (1976); and, most recently,
Nolde Brothers, Inc. v. Bakery Workers,
— U.S. —, —, 97 S.Ct. 1067, 51 L.Ed.2d 300 (1977). We agree with the commentator’s recent analysis of
Buffalo Forge
to the effect that “. . . the interpretation and application of contractual provisions remain the exclusive province of the arbitrator,” and further that “[cjourts will intervene only when necessary to protect the arbitral jurisdiction and then only in a manner that avoids examination of the merits, and thus respects the process of which it seeks to protect.” Note,
The Supreme Court, 1975 Term,
90
Harv.L.Rev.
56, 251 (1976). Similarly, we agree that “. the lasting significance of
Buffalo Forge
may be chiefly as a limit to the
Boys Markets
doctrine and [as a result, it serves] as a signal to federal judges to stay out of the merits of labor disputes.”
Id.,
at 255.
Second. Regarding the terms and conditions of the bond, we reaffirm our holding that the parties to the collective bargaining agreement in this case did not agree to indemnify one another contingent upon the outcome of arbitration; rather, they agreed to arbitrate. Thus, the bond in this case was properly posted in accordance with F.R. C.P. 65 when it was conditioned upon whether or not the preliminary injunction was found to have been wrongfully issued, as set forth in part III of the panel opinion, rather than being made contingent upon the merits of the outcome of the arbitration.
The panel opinion is
reaffirmed.