Leo Spear Construction Company, Inc. v. The Fidelity and Casualty Company of New York and Brookfield-Baylor, a Joint Venture

446 F.2d 439, 1971 U.S. App. LEXIS 9166
CourtCourt of Appeals for the Second Circuit
DecidedJuly 1, 1971
Docket35696_1
StatusPublished
Cited by14 cases

This text of 446 F.2d 439 (Leo Spear Construction Company, Inc. v. The Fidelity and Casualty Company of New York and Brookfield-Baylor, a Joint Venture) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leo Spear Construction Company, Inc. v. The Fidelity and Casualty Company of New York and Brookfield-Baylor, a Joint Venture, 446 F.2d 439, 1971 U.S. App. LEXIS 9166 (2d Cir. 1971).

Opinions

MOORE, Circuit Judge:

This is an appeal from a judgment awarding plaintiff damages under a quantum meruit theory of recovery in the amount of $90,845 plus interest of $5,910.99 and in addition $50,000 damages under a theory involving tortious interference with business relations.

On June 20, 1967, Leo Spear Construction Company (Spear), plaintiff herein, entered into a contract with F. H. Mc-Graw and Company, Inc. (McGraw), the prime contractor in the construction of new student housing at the University of Vermont at Montpelier (the University), wherein Spear as a subcontractor agreed to perform certain work in connection with that construction job for a contract price of $618,000.

In December, 1968, McGraw defaulted in the performance of the prime contract and on December 19, the University chose to terminate McGraw’s contract effective December 29, 1968. The defendant Fidelity and Casualty Company (F & C) was MeGraw’s surety and had issued both payment and performance bonds to the University which bonds were drawn on a form of the Department of Housing and Urban Development. Under the terms of this bond, it was to be void if the contractor, McGraw, made prompt payment to the subcontractors and materialmen.

At the time of McGraw’s default, Spear was faithfully performing its obligations under its subcontract. However, its activities had been thwarted in a number of ways by McGraw. These included Mc-Graw’s failure to provide sufficient winter heat, delays from changes in the pier footing, compaction problems and, as a result of dynamiting operations by McGraw, the cracking of various walls and other concrete structures installed by Spear. Besides necessary corrective work, however, Spear had placed 152,000 [442]*442out of 164,000 bricks which had to be placed in the project or 92.1%, and he had placed 161,000 out of 163,000 cement blocks or 98.77%.

On December 9, 1968, Spear and one of its suppliers notified the defendant F & C that they were filing a mechanic’s and materialman’s lien respectively. Two days later, Spear again wrote F & C, indicating that it stood ready to cooperate with F & C in completing the project, and asking F & C to outline its position regarding the entire situation.

On January 2, 1969, the University notified F & C to complete the project pursuant to its performance bond. . Thereafter, F & C contracted with Brookfield-Baylor (Brookfield) which was to accomplish this completion. Brookfield was, of course, under no duty to contract with Spear to complete the work covered by Spear’s subcontract, and both defendants seem to have been having doubts about allowing Spear to finish the job because of its questionable financial status. F & C had become aware of Spear’s financial problems as early as December 12, 1968 when it had learned of an all-monies assignment of funds due Spear under the McGraw contract to the Chittenden Trust Company of Burlington, Vermont. Thus on February 5, Phil Scaglione of F & C informed plaintiff that the contract would not be renewed. However, on February 13, Spear’s president, Leo Spear, was told at a conference in New York City that Spear would be allowed to finish the contract and receive its unpaid balance if it could furnish an acceptable bond.

A letter of February 28 confirmed the February 13 arrangement but demanded action within ten days. Difficulties then arose over the terms of the bond. The Aetna Insurance Company agreed to write a bond for Spear on condition that F & C rather than Brookfield-Baylor be ■ the only_obligee, a condition which F & C stated “may be acceptable” in the February 28 letter, and also on condition that F & C rather than Brookfield be the contractor. F & C insisted that while the bond could be written to it, the contract must be with Brookfield. F & C points to various legal problems it might have faced had it assumed the role of contractor. Several days later plaintiff was informed that it would not be hired to complete the work it had started.

On April 2, 1969, after being informed that the subcontract would not be maintained in effect by F & C and Brookfield, Spear’s men came onto the site and drove off with a truckload of structural tile. Then they returned and started to load a second truck. However, Brookfield obtained a writ of attachment from the Chittenden District Court in Burlington, Vermont and caused the sheriff to seize and chain the truck. Before this action by the sheriff, Brookfield detained Spear’s truck by parking another vehicle in front of the truck and dumping a load of sand in front of it. However, the defendants at no time caused the writ to be entered since the Chittenden District Court found the injunctive remedy to be inappropriate and defendants decided to assert their claim for conversion as a counter-claim in this action. After the determination by the Chittenden Court that no injunction should issue, Spear’s representatives went onto the job site only to find that much of the material which had been in the truck had been removed, notwithstanding that the truck and its contents were still under the control of the sheriff pursuant to the writ. Spear also complains that Brook-field used various equipment belonging to Spear in the course of its work, and that in addition to Spear’s rights were violated when F & C took these actions since such actions violated an agreement of April 2 to preserve the status quo between Spear and Brookfield-Baylor. Brookfield suggests that this agreement, stated to terminate when the controversy was settled, in fact terminated when the Chittenden suit was terminated.

Spear had seven unpaid suppliers on this job, their total claims amounting to $52,173. After commencement of this [443]*443suit in April, 1969, payment was made by F & C to these suppliers on July 2, 1969. Plaintiff suggests that this payment was unreasonably delayed in that F & C at no time disputed its liability to these materialmen and paid them as per their bills. However, there was some dispute over whether these payments would be made to the materialmen directly or through Spear, since Spear apparently was seeking leverage in an attempt to obtain credit from its materialmen. After these payments were made to the materialmen by joint cheeks written to the materialmen and Spear, some of the suppliers agreed to loan a percentage of these payments to Spear.

I.

Quantum Meruit Recovery

Plaintiff, by an amended complaint, claimed damages under the payment bond on a quantum meruit basis, rather than on the contract. The plaintiff was entitled under Vermont law1 to make this election under the facts and circumstances of this case. Peist v. Richmond, 97 Vt. 97, 122 A. 420 (1923).

Thus, plaintiff was entitled to recover in this suit the fair and reasonable value to the defendant F & C of the work performed and the materials furnished. ' Gilman v. Hall, 11 Vt. 510 (1839); Silos v. Prindle and Prindle, 127 Vt. 91, 237 A.2d 694 (1968). The District Court carefully examined the various items of damage and proof thereof, viewed the construction site in order to make a more accurate judgment as to the proper amount of damages, and concluded that the fair and reasonable value of the work and material supplied by plaintiff was $674,866.92.

This figure was arrived at as follows:

direct labor charges incurred by plaintiff_________$377,393.49

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia-Pacific Corp. v. First Wisconsin Financial Corp.
625 F. Supp. 108 (N.D. Illinois, 1985)
Geofreeze Corp. v. C. Hannah Construction Co.
588 F. Supp. 1341 (E.D. Pennsylvania, 1984)
Parkway Bank & Trust v. City of Darien
357 N.E.2d 211 (Appellate Court of Illinois, 1976)
Salomon v. Crown Life Insurance
536 F.2d 1233 (Eighth Circuit, 1976)
Hoffman Motors Corp. v. United States
473 F.2d 254 (Second Circuit, 1973)
Hoffman Motors Corporation v. United States
473 F.2d 254 (Second Circuit, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
446 F.2d 439, 1971 U.S. App. LEXIS 9166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leo-spear-construction-company-inc-v-the-fidelity-and-casualty-company-ca2-1971.